HomeMy WebLinkAboutDYIMS PE Site report 20220929 Architect: Perkins Eastman DPC Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File ARCHITECT’S SITE OBSERVATION REPORT DATE OF VISIT: 09/27/2022 & 09/29/2022 PROJECT: Dennis Yarmouth Intermediate Middle School 286 Station Avenue South Yarmouth, MA 02664 DATE OF ISSUE: 10/05/2022 PROJECT NO: 71011 WEATHER CONDITIONS: Bright, sunny, low 70s (09-27) Partly cloudy, high 60s (09-29) ARCHITECT: Perkins Eastman, DPC 20 Ashburton Street 8th floor Boston, MA The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit. WORK IN PROGRESS: 1) Drywall taping 2) Classroom casework installation 3) Linoleum flooring installation 4) Tack board and marker board installation 5) Millwork installation 6) Ceiling framing; ceiling installation 7) MEP/FP finish work—light fixtures etc. 8) Interior painting 9) Rigging installation 10) ACM panel installation 11) Curtain wall finishing 12) Exterior caulking 13) Exterior AVB installation 14) Site work FIELD OBSERVATIONS: PE visited the site on Tuesday 09-27 and also Thursday 09-29, to review ongoing progress. Interior Items 1. Linoleum flooring installation is ongoing in the area D corridors (see photo on page 3). 2. H. Carr is still installing the wood slat ceilings in D 2nd floor corridor. 3. J Cohn is installing 3x3 tile floors in the connectors on level 2 (see photo on page 3). 4. Installation of mirrors and grab bars in D is underway. 5. Linoleum flooring in Area C classrooms is complete. 6. At Area B Pavillion is installing the polished concrete topping slab; specifically in the art rooms (Area B) at the time of observation (see photo on page 3). 7. Wood floor installation in the gym is well underway (see photo on page 5). 8. Epoxy flooring in the locker areas is complete and at the time of observation Walker was installing the toilet and changing stall partitions. 9. At area B, Wright was in the process of installing custom millwork in the media center (see pages 3 and 4), as well as the Area A cafetorium (see photo on page 5). 10. The cafetorium/kitchen overhead doors have now been installed, as well as the loading bay rolling door at the custordial work area. 11. Stage Rigging for the “cafetorium” stage is going in (also see issue #9294 below). 12. At Area A. Colony has taped the drywall at the music rooms and is about to start taping the drywall at the auditorium lobby. 13. At the time of observation, H. Carr was building the bump outs for the angled wall panels on the south wall of the auditorium. H. Carr has installed the ceiling grids in the music rooms (see photo on page 4). REPORT BY: ABH Page 2 of 6 Exterior items: 1. At the time of observation, Lambrian was completing the CW Caps at curtain wall type C3 (auditorium lobby corridor)--see photo at the bottom of page 3. 2. The exterior envelope cladding is nearing completion. At the time of observation on 9-29 Lymo had completed the ACM panel installation on the front facade, including (with Lambrian) for the curtain wall spandrel panels at the auditorium corridor (see 9-29 photo on page 5). 3. The final GFRC panel infill at the east elevation of Area C has been completed (see photo on page 6) 4. The only major item that Lymo still has to complete is missing panels at the roof bulkheads and back parapets. Site work: 1. At the time of observation on 9-27, RBO was installing the boulders for the round ‘cul-de-sac’ next to D wing on the West (see photos in attached TLA site report K1008-18). 2. RBO has started installing the athletic field light posts (see photo on page 6 in TLA site report K1008-18). 3. EA Quinn is in the process of installing landscaping in the courtyards and elsewhere around the site (see photos in attached TLA site report K1008-18). 4. Playground equipment installation is ongoing (see page 4 in attached TLA site report K1008-18). 5. At the time of observation, RBO was putting in the crushed stone for the front plaza area in prep for concrete installation, as well as installing the soil “mounds” at the planting areas (see TLA report K1008-18). DISCREPANCIES, SPECIAL INSTRUCTIONS New items 9291. Archway at cafetorium entrance: (9-27) CB informed PE that, due to sprinkler pipe conflicts, the “river ceiling” in the main lobby 1st floor is not going to meet the intended design height of 9’-0” to the bottom of the straight slats. (The same issue is observable at some of the corridor crossings in the academic wings.) For the main lobby in B, PE asked CB to “pause” the adjacent millwork portal installation, so that PE can try to lower the head of the portal, along with the ceiling, and thus the ‘portal’ won’t end up going above the ceiling. (Exact Solution TBD). 9292. The light grey accent wall paint in some classrooms in D looks splotchy; On 9-29 PE discussed this issue with O’Byrne’s foreman, Brendan, who stated that he was planning to return to the classroom wings to touch up that and other areas, but that the priority now is to keep everything moving in Areas A and B. 9293. De-fillibrator (AED) recess. PE pointed out that we apparently missed the blocking and the cutout/recess for the emergency cardiac de-fillibrator (AED) at the Wixon entrance, per Bulletin #29. It was supposed to go on the west side of the lobby adjacent to the Wixon entrance. PE noticed that there is already an electrical outlet at that location that will preclude Arden from installing it exactly per Bulletin #29, but CB said they would have Colony install it on the north side of the portal. 9294. RFI #441- cafetorium stage rigging conflict (9-29) CB showedPE that the conflict between the main stage curtain (HC2) and the track for the folding partition is more severe than the theater consultant had suggested in the drawing that was issued with the response to RFI #441. The pipes will need to shift further west, so in order to make everything fit PE directed CB to omit one of the valences (pipe #4). Prior items 9201. (from 9-20 site report) Ceiling height issue at wood “arches” in C and D Still open. 9202. (from 9-20 site report) Line of Black “structural deck” paint Still open. 9151. (from 9-15 site report) Unprotected return at the auditorium seventh tier. Still open. 9152. (from 9-15 site report) Finish at the short faces of the arched portals. Still open 9081. (from 9-08 site report) Gap at the west elevation. Still open. 9082. (from 9-08 site report) Grading at PCC base. Still open. 8182. (from 8-18 site report) Shot put concrete curb in wrong location: Update: CB and Traverse have worked out the rectification of the shot put curbing layout (see page 2 of attached TLA report K1008-18). —item to be removed 8111. (from 8-11 site report) Water filling station at Level 2. Still open 7191. (from 07 19 site report) Exterior Sealant at brick pattern at inside link corner. still open 4211. (from 04 21 site report) Steel protrusion at auditorium. Update: Colony has enclosed the steel—item to be removed Attachments: · TLA site report K1008-18 dated 10-03-22, from 9-28-22 REPORT BY: ABH Page 3 of 6 SITE PHOTOS FLOORING IN CORRIDOR (AREA D) TILE FLOORING IN LINK (C-D LEVEL 2) MILLWORK PROGRESS IN MEDIA CTR POLISHED CONC. FLR INSTALLATION CW CAP INSTALLATION AT AREA A EAST AREA C SOUTH EAST CORNER REPORT BY: ABH Page 4 of 6 (9-29) MUSIC ROOM PROGRESS (AREA A EAST) (9-29) CASEWORK INSTALLATION AT MEDIA CENTER (AREA B ) (9-29) CASEWORK INSTALLATION AT CAFETORIUM (AREA A) REPORT BY: ABH Page 5 of 6 (9-29) WOOD GYM FLOOR INSTALLATION (AREA B) (9-29) INSTALLED CANOPY / SPANDREL ACM PANELS FROM WIXON ENTRANCE (AREA A) (9-27) OVERALL VIEW FROM SE (AREA A) REPORT BY: ABH Page 6 of 6 (9-27) FINE GRADING / COMPACTION WORK AT ATHLETIC FIELD B (9-29) COMPLETED EAST FACADE (AREA C) (9-29) UNEVEN PAINT (AREA D) (9-29) INSTALLED OVERHEAD DOOR (CUSTODIAL WORK – AREA A) Traverse Landscape Architects 150 Chestnut Street 4th Floor Providence RI 02903 Landscape Architects Field Observation Report DYIMS 296 Station Avenue South Yarmouth, MA 02664 (US) Report number: K1008-18 Date: October 03, 2022 02:39 PM Current Work In Progress Traverse visited the site on September 28th, 2022 for general observation. Attendees and Distribution Role and company name Name Contact information Present Project Manager [Commodore Builders] Ricky Sughrue 508-463-7958 rsughrue@commodorebuilders.com ✔ Landscape Architect, Associate [Traverse Landscape Architects] John Luca 401.383.4950 jluca@traversela.com ✔ Superintendent [Commodore Builders ] Rick Mills 774-404-4575 rmills@commodorebuilders.com ✔ Senior Associate [PMA] John Pope 781.794.1404 ext 1792 jpope@pmaconsultants.com ✔ Consultant [PMA Consultants ] Nicholas Hull nhull@pmaconsultants.com ✔ Associate [PMA Consultants ] Mitch Miller 781-794-1404 ext. 1842 mmiller@pmaconsultants.com ✔ Superintendent [Commodore Builders ] Ryan Dirico 617-614-3500 rdirico@commodorebuilders.com ✔ Discussions on Site Report created by John Luca 1 / 6 1120 Depot Lane SE Cedar Rapid IA 52401 • 401.383.4950 • www.traversela.com Observations Observation Description Concrete ✔ Shot Put 18.1 September 28, 2022 Commodore and Traverse confirmed final adjustments to the shot put curbing layout via phone call and email on September 27th. Traverse reviewed the layout on site on September 28th. October 03, 2022 02:44 PM General Front Plaza 18.2 September 28, 2022 Front plaza landscape islands are formed. Base stone for concrete was in place and was being graded. Slopes on landscape berming shall be eased so as to not be too steep for mulch and planting. Contractor to grade out if too steep, see photos. Traverse met with Ryan of EA Quinn about boulder placement at the front plaza. Contractor to refer to plans and specifications for boulder placements. October 03, 2022 02:48 PM Check slope Report created by John Luca 2 / 6 1120 Depot Lane SE Cedar Rapid IA 52401 • 401.383.4950 • www.traversela.com Site Hardscape Boulder Seat Wall 18.3 September 28, 2022 Traverse and EQ Quinn discussed the landscape boulder wall on the west side. One adjustment was to be made to the center boulder to correct its exposed height (left arrow in photo). Commodore confirmed that the boulder was adjusted. One additional boulder was to be adjusted post-site visit ( boulder A24 shall be switched with boulder A18). October 03, 2022 02:52 PM Left arrow- Boulder was adjsuted.Boulder A24 -Right arrow Report created by John Luca 3 / 6 1120 Depot Lane SE Cedar Rapid IA 52401 • 401.383.4950 • www.traversela.com Equipment Playground Area 18.4 September 28, 2022 Playground equipment installation is progressing. Ricky Sughrue of Commodore reached out to Traverse about the play surfacing. Multiple playground/fitness equipment pieces are delayed and may cause potential issues with play surface installation scheduling. Traverse is looking into potential solutions with Commodore. In addition to reviewing equipment use zones and clearances per specifications, Traverse recommends that a playground manufacturer rep or contractor review and confirm all play equipment per approved shop drawings plans prior to play surface installation. Contractor shall receive approval from the owner's representative prior to installing the playground surface per specification 32 18 16. Refer to specifications for all play surface testing. Basketball court pavement was being installed. Traverse takes no exception to the work. October 03, 2022 03:06 PM Report created by John Luca 4 / 6 1120 Depot Lane SE Cedar Rapid IA 52401 • 401.383.4950 • www.traversela.com Planting ✔ Planting 18.5 September 28, 2022 Planting around the site is progressing. Traverse spoke with Poncho of EA Quinn about any questions on site. Traverse takes no exception to the planting to date. October 03, 2022 03:14 PM Report created by John Luca 5 / 6 1120 Depot Lane SE Cedar Rapid IA 52401 • 401.383.4950 • www.traversela.com Electrical Field lights 18.6 September 28, 2022 Rick Mills of Commodore asked if driving equipment over the synthetic turf field was acceptable in order to install the light pole bases and poles at the synthetic turf athletic fields. Traverse informed Commodore that no equipment should be driving on turf. Commodore, Traverse, PMA to discuss further prior to base and pole installation to confirm the best course of action. October 03, 2022 03:17 PM Contractor shall refer to the photos and observations above. Contractor shall comply with all requirements instructed by the Landscape Architect on all previous field reports until such requirements are fulfilled. The Landscape Architect shall not be responsible for any items not addressed in previous field reports which may result in cost or damage. All work shall comply with that which is shown in the Contract Documents. General conditions Site visits performed by the Landscape Architect under this contract have been conducted under the limited conditions as described by site observations in the General Conditions of the Contract for Construction, as referenced in the Owner-Architect Agreement. Information contained in this Field Observation Report by Traverse Landscape Architects has been prepared to the best of our knowledge according to observable conditions at the site. This information will be approved record unless written notice to the contrary is received within seven (7) calendar days of the issue date of this document. Written corrections shall be reported to observer at Traverse Landscape Architects. Oral rebuttals will not be accepted. Report created by John Luca 6 / 6 1120 Depot Lane SE Cedar Rapid IA 52401 • 401.383.4950 • www.traversela.com