Architect: Perkins Eastman DPC
Distribution: Commodore PMA Consultants Sandra Cashen Mark Grylls File
ARCHITECT’S SITE OBSERVATION REPORT
DATE OF VISIT: 10/06/2022 PROJECT: Dennis Yarmouth Intermediate
Middle School
286 Station Avenue
South Yarmouth, MA 02664
DATE OF ISSUE: 10/12/2022 PROJECT NO: 71011
WEATHER
CONDITIONS:
Bright, sunny, low 70s
ARCHITECT: Perkins Eastman, DPC
20 Ashburton Street
8th floor
Boston, MA
The purpose of the Site Observation Report is to record general observations of the work in progress at the time of the Architect’s visit.
WORK IN PROGRESS:
1) Drywall finishing
2) Classroom casework installation
3) Linoleum flooring installation
4) Tack board and marker board installation
5) Millwork installation
6) Ceiling framing; ceiling installation
7) MEP/FP finish work—light fixtures etc.
8) Interior painting
9) Overhead door installation
10) Stage rigging installation
11) ACM panel punch list
12) Exterior Aluminum Door installation
13) Site work
FIELD OBSERVATIONS:
PE visited the site on Thursday 10-06, to review ongoing progress.
Interior Items
1. Linoleum flooring installation is ongoing in the Area D first floor corridors (see Figure 11).
2. H. Carr is still installing the wood wall panels in the second floor collaboration areas in Area D (see Figure 2); they
are also in the process of installing the felt slat ceilings in Areas D and C (see Figures 1 and 9) .
3. J. Cohn is installing 3x3 tile floors in the east connectors on level 2.
4. Installation of mirrors and grab bars is ongoing in C.
5. At Area B Pavillion is installing the polished concrete topping slab in the Mattacheese school entry/lobby area; the
polished concrete at the kitchen servery area had been partially installed at the time of observation (see Figure 4).
6. Wood floor installation in the gymnasium is ongoing; subfloor installation has been completed.
7. Installation of toilet and changing stall partitions is complete.
8. Above-ceiling MEP work is ongoing at the admin area (Area B).
9. Installation of custom millwork is ongoing –currently Wright is focusing on the Cafetorium and Media Center; at
the time of observation they were also installing the wall panels at the front walls of the cafetorium and auditorium
(see Figure 7).
10. Classroom casework installation is ongoing—currently working in the music wing (Area A).
11. At the time of observation Walker was installing the glass folding door at the auditorium stage (see Figure 5).
12. H. Carr has completed the enclosures supporting the acoustical wall panels on the south wall of the auditorium.
Exterior items:
1. At the time of observation Lambrian was installing the aluminum exterior doors in Area C. They have nearly
finished installing mullion caps at curtain wall type C3 (auditorium lobby corridor).
REPORT BY: ABH Page 2 of 5
2. The exterior envelope cladding is nearing completion. At the time of observation roof bulkheads and back
parapets had been completed and Lymo was substantially finished with their cladding work (see Figure 13).
Site work:
1. At the time of observation, RBO was installing bollards at the east side of the gymnasium.
2. The ‘sprintturf’ installer is in the process of putting down the synthetic turf at field B.
3. Installation of landscaping in the two main courtyards appears complete; landscaping work by EA Quinn is
ongoing elsewhere around the site.
4. Playground equipment installation is done except for delayed items (see Figure 12).
5. At the time of observation, RBO had installed the the soil “mounds” at the front entry plaza and was continuing to
prep for walkway and pavement installation there (see Figure 13).
DISCREPANCIES, SPECIAL INSTRUCTIONS
New items
10061. Furring at Room A120. PE observed that the back wall of the Staff Lunch room was missing the Gyp furring
layer that is indicated in wall type M08D.
10062. Sight line issues to deck at Media Center central circulation area (see Figure 8). PE discussed with CB and
proposed to add opaque covering above the wood coffers to close off above-ceiling views. H. Carr
suggested 1/8” acrylic panels, and CB agreed to price.
10063. Sight line issues to deck at type 2.1 (felt slat) ceilings in the C and D corridors (see Figure 1); PE issued a
revision to add black ceiling tile above the grid to close off above-ceiling views at the east and west edges of
these ceilings (see Bulletin #47).
10064. Corner Trim at Rulon wall panels. PE noted the lack of a corner trim detail for the rulon wall panels
(equivalent to PE’s detail 18/A-5.41 for the ceiling panel trim). PE issued a new corner trim detail to make the
edges of the wall panels and ceiling panels align (see Bulletin #47).
10065. Exit sign junction box excessively low. PMA/PE asked CB to ask the electrical contractor to raise the junction
box for the exit sign at the type 2.1 ceiling (Area D). See Figure 9.
10066. Lowering ceiling at cafetorium. PE was told that the MEP rough-in placements will force the auditorium
ceiling down by 11 inches relative to design height, without recourse. PE issued a drawing in Bulletin #47 to
add film at the top 24” of the 2nd floor windows into the cafetorium so as to hide views above the wood
ceiling.
10067. Sidewall duct at Wixon media center entrance. PE is asking O’Byrne to re-paint the one low black sidewall
duct above the door so that it is white below the arrow in Figure 10 (so that it will be less obtrusive once the
felt slat ceiling is installed.)
Prior items
9291. (from 9-29 site report) Archway at cafetorium entrance: Updates: 1. PE issued a drawing lowering the
head of the portal (Bulletin #47). 2. PE discussed with CB and asked if Rustic could lower or reconfigure pipe
shown in figure 3 so that for H.Carr’s purposes it is at 9’-7” and would not force ceiling slats down.
9292. (from 9-29 site report) The light grey accent wall paint in some classrooms in D looks splotchy; Still open
9293. (from 9-29 site report) De-fillibrator (AED) recess. Update: PE relocated the AED device in order to avoid
the electrical device (see Bulletin #47)
9294. (from 9-29 site report) RFI #441- cafetorium stage rigging conflict (9-29) Still open
9201. (from 9-20 site report) Ceiling height issue at wood “arches” in C and D Update: Wood Portals are going to
remain as designed (to avoid cost) - Item to be closed.
9202. (from 9-20 site report) Line of Black “structural deck” paint Still open.
9151. (from 9-15 site report) Unprotected return at the auditorium seventh tier. Update: PE discussed with CB
and CB reported that United is working on a COR to address this problem.
9152. (from 9-15 site report) Finish at the short faces of the arched portals. Still open
9081. (from 9-08 site report) Gap at the west elevation. Still open.
9082. (from 9-08 site report) Grading at PCC base. Still open.
8111. (from 8-11 site report) Water filling station at Level 2. Still open
7191. (from 07 19 site report) Exterior Sealant at brick pattern at inside link corner. still open
Attachments:
· RJK site report number FR22 dated 10-05-22, from 9-27-22
· RJK open item tracking log from 9-27-22
REPORT BY: ABH Page 3 of 5
SITE PHOTOS
Figure 1. Site Line Issue @. Slat ceilg. Figure 2. Edge Trim Detail Issue @ Rulon Figure 3. Sprinkler Branch at 9’-3” aff
Fig. 4. Polished Conc. Floor Progress Figure 5. Folding exterior Door Installation Figure 6. CW Door Installation (Area C)
REPORT BY: ABH Page 4 of 5
Figure 7. Proscenium Panel Installation at Cafetorium
Figure 8. Sight Line Issues above Coffer Detail in Media Center Circulation
Figure 9. Low Exit Sign Junction box (D level 2 East Corridor) Figure 10. Paint Change at Media Ctr sidewall duct
REPORT BY: ABH Page 5 of 5
Figure 11. Linoleum Flooring Installation at Area D level 1 Corridor
Figure 12. Playground Equipment Installation Progress
Figure 13. Landscaping Progress at Main Entry Plaza
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
10/05/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
2.3 Wetted Polyisocyanurate
Insulation
Part D Roof Open
2.4
Upside Down Insulation Part D Roof 05/17/22: Written approval
from the manufacturer that the
orientation is acceptable for the
assembly will close the item,
otherwise correction of
installation methods.
Open
3.4
Wet Polyisocyanurate
Insulation and Cover Board Is
Installed
Part C 05/12/22: Testing will be
necessary to confirm materials
are dry and without organic
growth.
Open
3.5
Incomplete Night Tie-In Part C 05/17/22: Testing should be
conducted at the location to
ensure no moisture intrusion
occurred at the incomplete tie
in.
Open
4.3
Interior Air Barrier Seal at
Windows
Part D 04/28/22: Please provide
approved direction for the issue. Open
FR-1, 12/15/2021
FR-3, 12/28/2021
FR-2, 12/22/2021
FR-4, 1/6/2022
G:\RJK\WORD\32301 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 10-05-22 1 of 6
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
10/05/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
4.4
Window Fastening Part D 04/28/22: Please provide
photos of sealant at fasteners.
09/21/22: Window installation
continued without sealant at
screws as observed during site
installation on 09/14/22.
Open
4.5
Wet Polyisocyanurate
Insulation and Cover Board Is
Installed
Part C and Part
D Roofs
05/12/22: Testing will be
necessary to confirm materials
are dry and without organic
growth.
Open
4.6
Pitch Pocket Detail Part C 04/28/22: No change.
09/21/22: Installation
procedures have not changed
and no manufacturer's letters
have been submitted to approve
the installation.
Open
4.7
Uncut Clamping Rings Part C 04/07/22: Multiple clamping
rings still left uncut at Part C.
04/28/22: No change.
Open
6.1 Voids in Damproofing From
Damage
Part D and Part
C Open
6.3
Roof Debris Typical 04/28/22: Some large
equipment is on plywood,
although screws, pipes and
other debris are still observed
on the membrane.
Open
FR-5, 3/21/2022
FR-6, 4/7/2022
G:\RJK\WORD\32301 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 10-05-22 2 of 6
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
10/05/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
6.4
Roof Ponding Part C to Part B 04/28/22: Additional ponding
is observed at the west
breezeway.
05/12/22: Ponding is
continuously observed at both
locations.
09/21/22: No change.
Open
8.2
Discontinued AVB at Curtain
Wall Column
Part B, East
Elevation Rising
Wall, Grid Lines
M.9-L
Open
8.4
Roof Discontinuation Between
Vapor Barrier and PVC
Membrane
Part B,
Gymnasium
Roof, Grid Lines
B24 - B25
Open
13.1
End Dams at Through-Wall Part B, East
Elevation, Grid
Line B33
Open
FR-10, 6/10/2022
No New Issues
FR-12, 6/21/2022
No New Issues
FR-9, 5/17/2022
FR-8, 5/12/2022
FR-7, 4/28/2022
No New Issues
FR-11, 6/16/2022
FR-13, 7/1/2022
No New Issues
G:\RJK\WORD\32301 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 10-05-22 3 of 6
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
10/05/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
15.1
Glazed in ACM Panels Part B, South
Elevation,
Curtain Wall,
Grid Lines A17-
B21
09/21/22: The glazed in plate is
installed before the metal
panels.Closed
17.1
Damaged Metal Panels Part C,
Courtyard East
Elevation,
Parapet Level
09/21/22: The panels have
been replaced. Closed
17.2
Disconnect Between PVC Roof
Membrane and AVB
Part B, South
Elevation,
Parapet
09/21/22: The AVB membrane
was stripped in to extend under
the PVC membrane. Closed
17.3
Unsealed Prefabricated Pipe
Flashing
Part B Roof,
Grid Lines L,
B16
Open
FR-16, 8/8/2022
FR-15, 8/1/2022
No New Issues
FR-14, 7/8/2022
FR-19, 8/30/2022
No New Issues
FR-18, 8/22/2022
FR-17, 8/18/2022
G:\RJK\WORD\32301 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 10-05-22 4 of 6
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
10/05/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
19.1
Damaged and Unsealed
Prefabricated Pipe Flashing
South B, Low
Roof, Grid Lines
B26.5, N.6
09/21/22: Sealant has been
added to the pipe. It is unclear
through visual inspection if the
sealant was first installed under
the flange or just over. Also,
the state of the flashing should
be reviewed by the
manufacturer to see if it is
warrantable.
09/28/22: Email from Paul
Genereux (Commodore)
contains photo of repair. The
flashing appears to have been
replaced and sealant was
applied.
Closed
19.2
Roof Membrane Damage Part C, East,
Grid Lines C19,
G
09/21/22: No change at this
time.Open
19.3
Open Pipe Penetrations Part C, East,
Grid Lines C20,
F.5
09/21/22: Sealed hoods are
installed above the flashing. Closed
21.1
Unsealed Bolts on Mechanical
Curbs
Part A, West
Low Roof, Grid
Lines K - P, B1 -
B4
Open
FR-22, 9/27/2022
FR-20, 9/14/2022
FR-21, 9/19/2022
No New Issues
G:\RJK\WORD\32301 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 10-05-22 5 of 6
Building Envelope Field Report Tracking Log
Q504 - Mattacheese DYMIS Yarmouth
Tracking Log
10/05/2022
Item #Issue Location Contractors Response Owner's Project Rep RJK Comments Status
22.2
Short Roof Penetrations Part B Roof,
Grid Lines B17 -
B19, K - K.8
Open
G:\RJK\WORD\32301 Q504 Mattacheese DYIMS Yarmouth FR Tracking Log 10-05-22 6 of 6
FIELD REPORT
RJK discussed the issues with CB prior to leaving the site.
Work Observed
• Various Cladding Installation
• Roofing Installation
Observations
• Part B, South Elevation Low Parapet Wall, Gridlines A17 - A21 - Sheet metal hat channel is installed, wet
set in sealant and fastened utilizing screws, prior to installation of the ACM panels. (Figure 1)
• Part B, South Elevation Low Parapet Wall, Gridlines A17 - A21 - ACM parapet panels were installed and
fastened utilizing panel clips to the horizontal sheet metal hat channel. Factory outside corner panels were
installed and fastened utilizing clips to the horizontal sheet metal hat channel. (Figure 2)
• Part A, East Elevation, Gridlines R - Q, Second Floor - ACM panels are installed in the curtain wall
assembly. A framing structure was installed, set in sealant against the glazed aluminum panels and the
angled ACM panels. The panels are installed to the curtain wall framing and fastened utilizing a pressure
bar. (Figures 3 - 5)
• Part C, East Elevation, Grid Lines C22, G - F.5, Second Floor - Rieder Öko Skin high performance
cementitious wall panels were installed and are fastened to the horizontal galvanized hat channel with
color matched screws. (Figure 6, Figure 7)
• Part B, Grid Lines L - M.5, B17 - B21, Upper Roof - Walk pad was installed on the roofing membrane in
high traffic areas, adhered with Sika Sarnafil Sarnacol 2170 VC Membrane Adhesive. The walk pad was
folded back and glue was rolled applied to the back of the membrane and to the top of the field membrane.
The adhesive was allowed to become tacky to the touch and the walk pad was set into place. The laps
were to be heat welded following adhesion. (Figures 8 - 10)
Project: Q504 - Mattacheese, Dennis-Yarmouth Intermediate
Middle School Report Number: FR-22
Property Address: 276 Station Avenue, South Yarmouth, MA 02664
Client: Perkins Eastman
Date of Site Visit: Tuesday, September 27, 2022
Report Date: Wednesday, October 5, 2022
Weather: Overcast 69 - 74 °F
Purpose of Visit: Observe Building Enclosure Construction
On-Site During Visit: Michael Groome - R. J. Kenney Associates, Inc. (RJK)
Paul Genereux - Commodore Builders (CB)
Report By: Michael Groome
Report Attachments: Detailed Photographs
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-22
10/5/2022
Report
G:\RJK\WORD\32300 Q504 Mattacheese DYIMS Yarmouth FR22 Report 9-27-22.docx Page 2 of 9
Discussion
22.1 Short Roof Penetrations - Part B Roof, Grid Lines B17 - B19, K - K.8 - Three duct penetrations collars are
less than 6 inches off the roof membrane height and unsealed. The flashing membrane should extend a
minimum of 6 inches up the penetrations and be set in sealant with a clamping ring applied over the
membrane and sealant. (Figures 11 - 13)
END OF REPORT
RJK has no contractual responsibility in the design or actual construction of the project and is acting solely in a consultant and/or in an
advisory capacity to the Client. Any and all modifications, changes, recommendations, suggestions, etc., relating to the design and/or
construction, should be forwarded, reviewed, and approved by the designer of record prior to implementation. RJK reserves the right
to change or amend this report as new information becomes available.
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-22
10/5/2022
Appendix A
G:\RJK\WORD\32300 Q504 Mattacheese DYIMS Yarmouth FR22 Report 9-27-22.docx Page 3 of 9
Callouts:
1. Sealant bleed out
Comments:
0927 014 R. J. Kenney Associates, Inc.
Figure 1 ‐ Hat Channel
Callouts:
1. Attachment clips
Comments:
0927 015 R. J. Kenney Associates, Inc.
Figure 2 ‐ Parapet Metal Panels
1
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-22
10/5/2022
Appendix A
G:\RJK\WORD\32300 Q504 Mattacheese DYIMS Yarmouth FR22 Report 9-27-22.docx Page 4 of 9
Callouts:
Comments:
0927 007 R. J. Kenney Associates, Inc.
Figure 3 ‐ ACM Panels at Curtain Wall
Callouts:
Comments:
0927 012 R. J. Kenney Associates, Inc.
Figure 4 ‐ ACM Clips at Curtain Wall
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-22
10/5/2022
Appendix A
G:\RJK\WORD\32300 Q504 Mattacheese DYIMS Yarmouth FR22 Report 9-27-22.docx Page 5 of 9
Callouts:
1. Pressure bar
Comments:
0917 017 R. J. Kenney Associates, Inc.
Figure 5 ‐ Pressure Bar on ACM Panels
Callouts:
Comments:
0927 036 R. J. Kenney Associates, Inc.
Figure 6 ‐ Rieder Öko Skin High Performance Cementitious Wall Panels
1
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-22
10/5/2022
Appendix A
G:\RJK\WORD\32300 Q504 Mattacheese DYIMS Yarmouth FR22 Report 9-27-22.docx Page 6 of 9
Callouts:
Comments:
0927 038 R. J. Kenney Associates, Inc.
Figure 7 ‐ Cementitious Wall Panels Fastening
Callouts:
Comments:
0927 059 R. J. Kenney Associates, Inc.
Figure 8 ‐ Adhesive Application on Roof Membrane
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-22
10/5/2022
Appendix A
G:\RJK\WORD\32300 Q504 Mattacheese DYIMS Yarmouth FR22 Report 9-27-22.docx Page 7 of 9
Callouts:
Comments:
0927 055 R. J. Kenney Associates, Inc.
Figure 9 ‐ Adhesive Application on Walk Pad
Callouts:
Comments:
Work-in-progress. Perimeter
of sheets were not yet welded.
0927 056 R. J. Kenney Associates, Inc.
Figure 10 ‐ Adhered Walk Pads
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-22
10/5/2022
Appendix A
G:\RJK\WORD\32300 Q504 Mattacheese DYIMS Yarmouth FR22 Report 9-27-22.docx Page 8 of 9
Callouts:
1. Low flashing
Comments:
0927 052 R. J. Kenney Associates, Inc.
Figure 11 ‐ Penetrations with Low Flashing
Callouts:
Comments:
0927 053 R. J. Kenney Associates, Inc.
Figure 12 ‐ Low Penetration Flashing
1
1
1
Q504 - Mattacheese, Dennis-Yarmouth Intermediate Middle School
Report Number: FR-22
10/5/2022
Appendix A
G:\RJK\WORD\32300 Q504 Mattacheese DYIMS Yarmouth FR22 Report 9-27-22.docx Page 9 of 9
Callouts:
Comments:
0927 054 R. J. Kenney Associates, Inc.
Figure 13 ‐ Open Penetration Flashing