HomeMy WebLinkAboutFedEx Ground-Controlled Construction Report_3 01.05.2023 January 5th, 2023 Mark Grylls, Building Commissioner Town of Yarmouth 1146 Route 28 South Yarmouth, MA 02664 RE: Controlled Construction - Report No. 3 For the Period Nov. & Dec 2022 FedEx Ground Distribution Center 225 Whites Path Units B & C, Yarmouth, MA Dear Mr. Grylls, Construction activities at the subject project continued in a proper manner during the months of November and December of 2022, and the following general work has occurred: 1. Unit B · Steel erection and modifications continued, this work was inspected by Briggs Engineering and the SER, Consulting Structural Engineers, Inc.. · A minor amount of steel welding work remains. · MEP systems in Unit “B” are virtually complete, but have not yet been energized or started up. · Alterations in office areas also continued with framing of new partitions, installation of new lighting, ceilings, painting, etc. · New mechanical systems were installed for the office area and the make- up air systems are nearly complete. · Roof penetrations for MEP systems has just begun and should be complete in the next month. 2. Unit C · The new internal stair to the roof access hatch is installed. The new roof hatch was also installed. · Steel erection and modifications continued, this work was inspected by Briggs Engineering and the SER, Consulting Structural Engineers, Inc.. · A minor amount of steel welding work remains. · MEP systems in Unit “B” are virtually complete, but have not yet been energized or started up. · Alterations in office areas also continued with framing of new partitions, installation of new lighting, ceilings, painting, etc. · New mechanical systems were installed for the computer server room and the make-up air systems are nearly complete. · Roof penetrations for MEP systems has just begun and should be complete in the next month. 3. Site Work · The parking area has been paved, base course only. Final paving will be completed once all other site work is complete. · The retaining walls which contain the new vehicle access ramps have been formed and poured. · Controlled backfill operations will ensure the fill between the ramp walls is adequate for the intended loads. · The trench drain at the new loading dock apron is complete. · All other underground drainage structures have been installed. Briggs Engineering and Testing continues to conduct concrete, welding and structural and reinforcing steel testing, these reports are sent to your attention directly. Northeast Geotechnical Solutions have been monitoring all earthwork operations and their reports have also been shared with your office. They will only have a few more visits to observe paving work. If you have any questions about the testing reports, please contact my office. Catalyst has been attending weekly job meetings and conducting site visits frequently to monitor work in progress and adherence to the construction documents. All work completed to date has been done in a good and workmanship-like manner and in general accordance with the construction documents and applicable code. The following text and images describe some of the highlights of the work recently completed work: Pic -2.1 Parking area with base course of asphalt paving Pic-2.2 Truck parking area with 8” CIP concrete slab Pic 2.3 Concrete retaining walls at one of two similar vehicle ramps w/ controlled backfill Pic 2.4 New Trench Drain at Truck Loading & Unloading Apron Pic 2.5 The new roof access hatch, installed new demising wall between unit “B” and “C” Pic 2.6 Typical new plumbing penetration in existing EPDM roof. If you have any questions, please feel free to contact me at any time. Sincerely, Kurt E. Raber Principal-In-Charge CC: Tim Sears (Town of Yarmouth Deputy Building Commissioner) Greg Bilezikian (Owner) David Fernandes (Dellbrook|JKS) Marina Denisova (Dellbrook|JKS) Scott Mitchell (Dellbrook|JKS) Mike Schmidt (Dellbrook|JKS) Rick Fenuccio (OPM, ClearPath Advisors) Kate Wollman (Catalyst Architecture & Interiors)