HomeMy WebLinkAboutZ486.01 - FedEx - South Yarmouth MA - FR31 (1-11-23)NORTHEAST GEOTECHNICAL, INC. DAILY FIELD REPORT
PROJECT: Proposed FedEx Distribution Facility FIELD REPORT NO: 31 PAGE 1 OF 2
PROJECT NO: Z486.01 DATE: 1/11/23
LOCATION: 225 White’s Path, South Yarmouth, MA CLIENT: 225 White’s Path Units 2 and 3, LLC
WEATHER: Cloudy, 35-38°F CONTRACTOR(S): DellbrookǀJKS; Future Fence
Company 1. Henry Tinoco arrived on site at 0730 hours. Left site at 1330 hours.
2. Earthwork equipment:
A) One E88 Bobcat Tracked Excavator with Auger Attachment B) One T66 Bobcat Tracked Loader C) One JCB 507-42 Telehandler
3. Earthwork observed: A) Drilling of the shaft foundations for the proposed sound wall within the southwesterly portion of the
site along the side of the parking lot took place today (see attached Annotated Site Plan, Figure No. 1). The ground surface along the proposed wall alignment in the noted area generally consisted of loam fill at about Elevation 40± feet.
Future Fence Company (FFC) used an E88 Bobcat tracked excavator equipped with a 2.5± foot diameter auger to drill eight proposed shafts which we reference as nos. DS2, DS12 and DS29 through DS34 on the attached Figure No. 1 and drilled shaft log. FFC augured down to a depth of about 8.5± feet for drilled shaft no. DS2, and about 9.5± feet for drilled shaft nos. DS12 and DS29 through DS34.
These drilled shaft excavations appeared to extend through about 4± to 6± inches of surficial loam fill and into sand appearing to generally consist of tan to reddish brown, fine to medium sand, trace silt. These drilled excavations appeared to terminate in similar natural sand. Groundwater was not observed in these drilled excavations.
Two, 2.5 foot diameter sonotubes were installed in the drilled excavation for shaft no. DS2 due to unstable excavation sidewall conditions. The annular space around the sonotubes was backfilled with on-site sand appearing to generally consist of tan, fine to medium sand, trace silt. The backfill was tamped to an apparent firm and stable condition during placement with a 5 inch x 5 inch plate attached to rebar (hand tamper).
ONSITE: TRAVEL:
REPORT: TOTAL:
6.00 hours
1.50 hours
1.00 hour
8.50 hours
Henry Tinoco
FIELD REPRESENTATIVE
Mark Zambernardi, P.E. REVIEWER
Tel: 508-598-3510
NORTHEAST GEOTECHNICAL, INC.
DAILY FIELD REPORT
PROJECT: Proposed FedEx Distribution Facility FIELD REPORT NO: 31 PAGE 2 OF 2
PROJECT NO: Z486.01 DATE: 1/11/23
During drilling of shaft no. DS31, the auger shifted out of alignment between the depths of about 2± to
4± feet due to roots resulting in a wider excavation. FFC installed two, 2.5± foot diameter sonotubes in the drilled excavation. The annular space around the sonotubes was backfilled with on-site sand appearing to generally consist of tan, fine to medium sand, trace silt. The backfill was tamped to an apparent firm and stable condition during placement with the hand tamper.
FFC tamped loosened soil along the bottom of the drilled excavations with the auger and the hand tamper. The exposed sand along the bottom of the drilled excavations appeared firm and stable. 4. Attachments: Drilled Shaft Log
Photo Log Figure No. 1 – Annotated Site Plan
5. Distribution: Greg Bilezikian – 225 White’s Path Units 2 and 3, LLC Rick Fenuccio – ClearPath Advisors, LLC
Kurt Raber – Catalyst Architecture & Interiors Kate Wollman – Catalyst Architecture & Interiors Mike Schmidt – DellbrookǀJKS David Fernandes - DellbrookǀJKS Marina Denisova - DellbrookǀJKS
Scott Mitchell - DellbrookǀJKS Mark Grylls – Town of Yarmouth Building Commissioner Tim Sears – Town of Yarmouth Deputy Building Commissioner
31
Date:1/11/2023
File No.:Z486.01
Observer:Henry Martinez Tinoco
Reviewed By:Mark Zambernardi, P.E
2 8.5±
12 9.5±
29 9.5±
30 9.5±
31 9.5±
32 9.5±
33 9.5±
34 9.5±
1. A 30 inch diameter auger was used during drilled shaft excavation.
NOTES:
2.5±
2.5±
2.5±
2.5±
2.5±
2. 30 inch diameter sonotubes were placed from bottom of hole to ground surface to stabilize excavation.
3. Roots encountered from about 1.5± to 4.5± feet below ground surface (bgs).
4. Future Fence Company personnel attemped to remove roots pior to continuing drilling.
5. Bottom of excavation was tamped with the auger and hand tamper.
1, 2, 5
1, 5
1, 5
1, 5
1, 2, 3, 5
1, 5
1, 3, 4, 5
1, 3, 4, 5
2.5±
2.5±
2.5±
NORTHEAST GEOTECHNICAL, INC.
Project:
DRILLED SHAFT LOG
GROUND
SURFACE
ELEVATION (FT)
GROUNDWATER
DEPTH (FT)
Report No:
FedEx Distribution Facility
225 White's Path
South Yarmouth, MA
SHAFT
LENGTH
(FT)
SHAFT
DIAMETER
(FT)
DESCRIPTION OF SOIL AT
BOTTOM OF SHAFT
SHAFT
NO.
DATE OF
DRILLING NOTES
1/11/23
1/11/23
1/11/23
1/11/23
1/11/23
1/11/23
1/11/23
1/11/23
40±
40±
40±
40±
40±
40±
40±
40±
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Natural Sand
Natural Sand
Natural Sand
Natural Sand
Natural Sand
Natural Sand
Natural Sand
Natural Sand
NORTHEAST GEOTECHNICAL, INC.
Z486.01 Proposed FedEx Distribution Facility – 225 White’s Path, South Yarmouth, MA PHOTO LOG – FIELD REPORT NO. 31 Page 1 of 3
Photograph #1
Description of Photograph:
Drilling of shaft no. DS2.
(Item 3A)
Photograph Taken By:
Henry Martinez Tinoco, dated
1/11/23
Photograph #2
Description of Photograph:
Placement of sonotubes and
backfilling annular space around
sonotubes for drilled shaft no. DS2.
(Item 3A)
Photograph Taken By:
Henry Martinez Tinoco, dated
1/11/23
NORTHEAST GEOTECHNICAL, INC.
Z486.01 Proposed FedEx Distribution Facility – 225 White’s Path, South Yarmouth, MA PHOTO LOG – FIELD REPORT NO. 31 Page 2 of 3
Photograph #3
Description of Photograph:
Start of drilling of shaft no. DS29.
(Item 3A)
Photograph Taken By:
Henry Martinez Tinoco, dated
1/11/23
Photograph #4
Description of Photograph:
Placement of sonotubes in drilled
excavation for shaft no. DS31.
(Item 3A)
Photograph Taken By:
Henry Martinez Tinoco, dated
1/11/23
NORTHEAST GEOTECHNICAL, INC.
Z486.01 Proposed FedEx Distribution Facility – 225 White’s Path, South Yarmouth, MA PHOTO LOG – FIELD REPORT NO. 31 Page 3 of 3
Photograph #5
Description of Photograph:
Drilling of shaft no. DS33, while
Future Fence Company personnel
removes roots from drilled
excavation for shaft no. DS34.
(Item 3A)
Photograph Taken By:
Henry Martinez Tinoco, dated
1/11/23
Photograph #6
Description of Photograph:
Tamping the bottom of drilled shaft
no. DS31 with a rebar rod attached
to a 5x5 inch plate at the end.
(Item 3A)
Photograph Taken By:
Henry Martinez Tinoco, dated
1/11/23
106.3'
164.3'
77.3'
96.7'
29.0'
48.3'
77.3'
87.0'
110°0'0"'
155°0'0"'
165°0'0"'150°0'0"'
ADDRESS:
PLATE NO.
SHEET TITLE
PROJECT NAME:
1866 Woodslee Street
Troy, Michigan 48083
office (248) 680-0400
fax (248) 680-9745
This drawing is copyrighted and is the soleproperty of the owner it is produced solely
for use by the owner and its affiliates.
Reproduction or use of this drawing and/orthe information contained in it is forbidden
without the written permission of the owner.
FedEx Yarmouth Sound Wall
225 Whites Path
South Yarmouth, MA 02664
SITE PLAN
PROJECT NO.:220705
DATE:9/19/22
DRAWN BY: ETT
CHECKED BY:JMC
No.:REVISION DESCRIPTION DATE:
G2-1
OVERALL PLAN
0 40'60'20'10'
GRAPHIC SCALE
START OF 13-FT.
SOUND WALL
STA 0+00
END OF 16-FT.
SOUND WALL
STA 6+87.1
END OF 13-FT. SOUND WALL
START OF 16-FT. SOUND WALL
STA 1+06.6
SEE DETAIL A
WALL CORNER
STA 2+70.9
SEE DETAIL B
WALL CORNER
STA 3+48.8
SEE DETAIL A
WALL CORNER
STA 4+45.4
SEE DETAIL C
WALL CORNER
STA 4+74.4
SEE DETAIL D
WALL CORNER
STA 5+22.8
SEE DETAIL E
WALL CORNER
STA 6+00.3
SEE DETAIL F
NOTES:
1. FIELD LOCATE ALL UTILITIES BEFORE EXCAVATING FOUNDATIONS
2. COORDINATE FOUNDATION LOCATIONS ADJACENT TO EXISTING WATER
LINES AND HYDRANT ACCORDINGLY
DETAIL C
DETAIL D
DETAIL E
DETAIL F
\\troy\geotechnical\2022 geotechnical\220705 fedex yarmouth sound wall\cad\220705.dwgDETAIL A
DETAIL B
SEE NOTE 2
SEE NOTE 2
11/4/22Architectural Review111/4/2022