Loading...
HomeMy WebLinkAboutEngineer Certification BSC GROUP �5 _ �r - • APR 1 1 2005 657 Main Street, Yarmouth Board Of Health April 8, 2005 Unit 6, 1164, Route 28 HEALTH BEN Route 28 South Yarmouth, MA 02664 West Yarmouth, MA 02673 Re: 228 Route 28, Septic System Replacement - Cape Cod Super Buffet Tel: 508-778-8919 Fax: 508-778-8966 Members of the Board: This letter is to document BSC's observations of the construction of the septic system at the above listed site. BSC staff has performed site reviews on a regular basis during installation of the septic system. The reviews included testing of the septic tank and pump chamber for leakage, observation of the construction of the soil adsorption system and observation of the operation of pumps/controls and as-built surveys. The following is a summary of the reviews. March 2, 2005: Interior plumbing was found to be at a different elevation (lower) than expected . Orangeburg piping was replaced with new building sewer to the septic tank. As a result of the lower elevation of the building sewer, the septic tank and pump chamber will be set slightly lower than designed. Plumber also found some sinks going directly to the septic tank. According to Bill McMahon, project manager for Robert B. Our Co, the internal piping was redirected to the grease trap. March 2, 2005: The excavation for the pump chamber was reviewed. The hole was free of standing water (two dewatering pumps working continuously) and the stone bed was installed. Seals for the tank joints were installed during the installation of the tank. March 3-5, 2005: The septic tank(a sectional tunnel tank) was installed on a stone bed. Dewatering pumps were in operation and no evidence of water was visible in the excavation. March 5, 2005: The pump chamber was filled with water(from the dewatering pumps)to 8" from the top and covers closed for the weekend. March 7, 2005: The pump chamber covers were removed after 48 hours and the water remained at 8" indicating no leakage. The piping from the building to the tanks were ncltngineers connected and as such the tank could not have received any inflow during the test. Environmental March 7, 2005: The grease trap was installed. A new 6" C.I. piping was installed from tieentists building to the grease tank. GIS Consultants March 9, 2005: The septic tank was filled with water(from the dewatering pumps) and Landscape left overnight. Architects Planners Surveyors I' _ zk>" . Cape Cod Super Buffer r_ Page 2 of 2 March 10, 2005: The water level in the septic tank was found to be down 2 feet indicating significant leakage. All water was pumped out and joint seals were repaired. r" March 10—11, 2005: The soil removal around and under the soil adsorption system and associated sand fill soil replacement were reviewed by BSC. March 14, 2005: Even though the restaurant was closed, water was found flowing into the grease trap that was concluded to be coming from a food cooler. (Two other coolers were not in use). Because the septic system is not designed to accept this additional flow and because this is clean cooling water (not wastewater) BSC recommended re-plumbing of the piping from the coolers and installation of a separate recharge chamber for the cooler water rather than discharge it to the ground as is typical of this equipment. (As of April 8, 2004 connection of the cooling water discharge pipe to the recharge pit remains to be completed). March 14-15, 2005: The septic tank was re-filled with water and no difference in water level was observed 24 hours later indicating no leakage. March 15-16, 2005: Stone bedding and piping of soil adsorption system visually reviewed. March 17, 2005: Pumps/alarms/pressure dose system reviewed during an operational test. All end holes in the laterals producing the same discharge height of approximately 20 inches. Pumps and controls appeared to operate as intended. 4f�xy. March 18, 2005: The area over the leaching fields were backfilled and metal covers were set to protect and provide access to the cleanouts at the end of the lines. Grade was brought up to within 3"to 4" of the top of metal covers. Final gravel /bituminous pavement to be installed at a later date. Based on observation of the contractors control stakeout,the system is substantially in the location shown on the design plan, there are manholes to grade at all significant manholes and clean outs and at the direction of the Board of Health Agent, no as-built survey was completed. Based on these reviews, BSC is of the opinion that the system has been installed in substantial compliance with the approved plans. e BSC Group Inc, avid J. Crispin PE, Sr. Associate k���z