Administrative Checklist
Certificate of Compliance
General Information:
• All filings must be made on Town of Yarmouth forms.
• All applications must be submitted two weeks prior to the next scheduled Conservation
Commission meeting. Refer to Meeting Schedule.
• Failure to follow the Administrative Checklist shall result in an Administrative Incomplete
Application and will not be scheduled for a Public Hearing.
• Contact the Conservation Office if you need assistance.
Submitting an Application:
1 complete hardcopy of the COC application, plan/sketch, and other supporting
information to the Conservation Office - mailed to or dropped off at Town Hall.
1 complete pdf of the COC application, plan/sketch, and other supporting information
emailed to bdirienzo@yarmouth.ma.us.
______ Signed statement from an Engineer or similar professional to who prepared the
approved plan. – Include in hardcopy and digital submission.
______ As-Built plan – Include in hardcopy and digital submission. Refer to 310 CMR
10.05(9)(d). *Refer to issued Order of Conditions: Special Conditions to determine if
required*.
Local filing fee. Refer to Fee Schedule. Make check payable to “Town of Yarmouth”
and include property address in memo.
All forms, Fee Schedule and Meeting schedule can be found at
https://www.yarmouth.ma.us/696/Filing-Forms.
*Click Yarmouth Street Index for parcel-related Conservation documents.
CONSERVATION
OFFICE
wpaform8a.doc rev. 5/29/14 Page 1 of 2
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 8A Request for Certificate of Compliance
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
DEP File Number:
83-2302
Provided by DEP
A. Project Information
1. This request is being made by:
Jake Simmons
Name
2 Channel Point Road
Mailing Address
Yarmouth
City/Town
MA
State
02673
Zip Code
508-815-55555
Phone Number
2. This request is in reference to work regulated by a final Order of Conditions issued to:
Channel Point LLC
Applicant
Important:
When filling out
forms on the
computer, use
only the tab
key to move
your cursor -
do not use the
return key.
10/28/2021
Dated
83-2302
DEP File Number
3. The project site is located at:
2 Channel Point Drive
Street Address
Yarmouth
City/Town
14
Assessors Map/Plat Number
9
Parcel/Lot Number
4. The final Order of Conditions was recorded at the Registry of Deeds for:
Channel Point LLC
Property Owner (if different)
Barnstable
County
Book
Page
Doc 1,445,006
Certificate (if registered land)
5. This request is for certification that (check one):
the work regulated by the above-referenced Order of Conditions has been satisfactorilycompleted.
the following portions of the work regulated by the above-referenced Order of Conditions have
been satisfactorily completed (use additional paper if necessary).
Upon completion
of the work
authorized in
an Order of
Conditions, the
property owner
must request a
Certificate of
Compliance
from the issuing
authority stating
that the work or
portion of the
work has been
satisfactorily
completed.
the above-referenced Order of Conditions has lapsed and is therefore no longer valid, and the
work regulated by it was never started.
wpaform8a.doc rev. 5/29/14 Page 2 of 2
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 8A Request for Certificate of Compliance
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
DEP File Number:
83-2302
Provided by DEP
A. Project Information (cont.)
6. Did the Order of Conditions for this project, or the portion of the project subject to this request, contain
an approval of any plans stamped by a registered professional engineer, architect, landscape
architect, or land surveyor?
Yes If yes, attach a written statement by such a professional certifying substantial
compliance with the plans and describing what deviation, if any, exists from the plans
approved in the Order.
No
B. Submittal Requirements
Requests for Certificates of Compliance should be directed to the issuing authority that issued the final
Order of Conditions (OOC). If the project received an OOC from the Conservation Commission, submit
this request to that Commission. If the project was issued a Superseding Order of Conditions or was the
subject of an Adjudicatory Hearing Final Decision, submit this request to the appropriate DEP Regional
Office (see http://www.mass.gov/eea/agencies/massdep/about/contacts/find-the-massdep-regional-office-
for-your-city-or-town.html).
Photo 1: View of the rear face of the newly constructed pool, patio, breezeway, and garage on
the property. Facing Northwest.
Photo 2: View of completed pool, patio, and garage, note drain incorporated into patio.
Facing Southwest.
Site Photographs
2 Channel Drive
West Yarmouth, MA
August 2023
Page 1
Photo 3: View of the newly installed pool filter and electric panel along the side of the
Western side of the newly constructed garage. Facing North.
Photo 4: View of the new landscaping in the Northwest corner of the front of the property.
Facing Southwest.
Site Photographs
2 Channel Drive
West Yarmouth, MA
August 2023
Page 2