November 15,2023
Yarmouth Conservation Committee
1146 Route 28
South Yarmouth,MA 02664
Re: Extension Request for 5E83-2215,Hyannis Marina,Project Location,21 Arlington St.,
West Yarmouth,Map 286 Parcel 17
Dear Members,
The Order of Conditions(OOC)for Hyannis Marina#SE83-2215 currently expires on 3/29/24
from the extension granted through COVID.
We request an extension of the order(which would be our first extension)as parts of the
project are incomplete and parts of the project require perpetual maintenance.Please see the
attached.
The maintenance dredging will be ongoing for as long as the Steamship Authority operates in
Hyannis Harbor.The vinyl sheeting is 85%complete.The 1200 gallon settling/pump chamber is
complete but we have further piping upgrades planned and the piping and the smaller chamber
is not complete.The shed has not been replaced and there is foundation repair to finish.
Respectfully,I request the maximum extension allowed by the Commission due to ongoing
general maintenance and maintenance dredging.
W aey,-e-441AAPA Pam.
Wayne Kurker
Hyannis Marina
Sea, iooL, KEY WEST CaNTENDER HBO � i id
5 : 00 pneN
E83-22.15
BRAMILLN FailT,TRINTEVING & ASSOC, LLC
4+,
61 Allen Street, Marion, MA 0273B
508-748-9669
AT :ps‘.CHIVIENT “A"
ITAYANNIS MARINA, YARiMOUTII
IT IS PROPOSED TO REPLACE 2 SECTIONS OF TH EXISTING WOODEN WALL
ON THE 'WESTERLY END OF THE BUILDING AT 21 ARLINGTON STREET (AKA
BUILDING I) WITH A CONCRE-nt, I CINDER BLOCK FOOTING AND
FOUNDATION WALL WHICH WELL BE UP TO 6 ABOVE GROUND LEVEL AND
PLACE SIDING TO THE ORIGINAL SIDING HEIGHT, TO REPLACE 7iLIE
WHALERS ON THE EXISTING TIMBER WALL BULKHEAD AS NECESSARY, TO
REFACE THE EXISTING TIMBER WALL BULKHEAD WITH VINYL SHEETING,
TO COMPLETE ALL PREVIOUSLY APPROVED IMPROVEMENTS AND
REPAIRS.
tr-4'1\
TO MAINTAIN, REPAIR, CONSTRUCT/DREDGE, CLEAN, WASH, REFINISE,
TRIM AND REPLANT ALL PREVIOUSLY AUTHORIZE IMPROVEMENTS 1[1\I
ACCORDANCE WITH PREVIOUS APPROVALS AND DREDGE LIMITS IN
ACCORDANCE WITH LICENSED DRAWINGS WITH WORK TO BE PER_FORMED
BY MECHANICAL METHODS WITH UPLAND DISPOSAL OR DISPOSAL AT
SEA, INCLUDING USE AND MA-NTENANCE OF SEASONAL DEWATERING
AREAS AND TO MAINTAIN, RESURFACE, REFACE, ALL CONSTRUCTED SITE
FEATURES IN PLACE AND IN KIND, INCLUDING BUT NOT NECESSARILY
LIMITED TO BUILDINGS, TENTS, PARKING AREAS, FENCES, GATES, SEPTIC
SYSTEMS, UTILITIES BOTH UNDERGROUND AND 4% 11'OVEGROUND
INCLUDING SEWER SYSTEMS, WASTE WATER SYSTEMS, WATER,
ELECTRIC, NATURAL GAS LINES, DIMLING SYSTEMS, TELEPEONE,
CABLEVISION, SECURITY SYSTEMS, WASTE WATER DRAINAGE SYSTEMS
INCLUDING BOTTOM WASH WASTE WATER SYSTEMS, IRRIGATION
SYSTEMS, GROUNDS, PAVED AND GRAVEL SURFACES, VEGETATION,
RETAINAGE, PIERS, PLIINGS, BULKHEADS INCLUDING REFACING WITH
VINAL SHEETING, RIP-RAP, FLOATS, DOCKS, PILINGS, RAMPS AND
UTILIZATION OF PREVIOUSLY APPROVED CHAPTER 91 AND ARMY CORPS
OF ENGINEERS RECONFIGURATION ZONE IN ACCORDANCE WITH THE
TERMS OF THOSE AUTHORIZATIONS.
REFER TO D.E.Q.E & D.E.P FILE NOS. SE3-1232, SE3-1333, SE3-780, SE3-1160,
SE3-1094, SE3-890, SE3-826, SE3-2423, 8E3-2833, SE83-508, SE83-456, SE83-338,