HomeMy WebLinkAboutOOC 2426Page 7a of 9 *ELECTRONIC COPY
WPA FORM 5-ORDER OF CONDITIONS
SPECIAL CONDITIONS-PAGE 7A OF 9
SE83-2426, Mariana O’Connor
20 Seaside Village Road
1. This Order shall apply to any successors and assigns in interest or control and any other person engaging in activity
on the property identified in the Notice of Intent.
2. The applicant/owner shall be responsible for always having a copy of the “Order of Conditions” on the job site and
shall be responsible for insuring that all persons performing the permitted activity are fully aware of its terms and
conditions. Failure to do so may result in the revocation of these "Orders", a fine or both.
3. The Conservation Commission, its agent(s) or assigned(s) shall have the express right of entry upon the job site at all
reasonable times for the purposes of establishing compliance with the "Order of Conditions", "By -Laws" and
"Regulations". Commission members and the Conservation Administrator may acquire any information,
measurements, photographs, observations and/or materials or may require the submittal of any data/information
deemed necessary by this Commission for that evaluation.
4. A preconstruction review shall be arranged by the contractor with the Conservation Administrator and shall occur
prior to the commencement of any work.
5. Any change in the approved plan(s) shall require the Applicant to file, in writing, a notice of project change with this
Commission. The Commission will determine the significance of the change and determine whether administrative
approval or an "Amended Order of Conditions" is required. Should the project be changed without permission or
found by the Yarmouth Conservation Commission to be altered in any way from the approved plan(s), all work will
immediately cease until the project is reapproved by the Commission.
6. The "Order of Conditions" is valid for three years from the date of issuance unless otherwise specifically noted in the
"Orders". Extension Permit requests must be applied for at least 30 calendar days prior to the expiration date of the
original Orders". Failure to do so will result in a new "Notice of Intent" filing.
7. Noncompliance with these conditions shall constitute grounds for an Enforcement Order and possible fines. Fines
shall not exceed $300.00 per day/per violation.
8. Gutters and downspouts directed into adequately sized drywells or similar shall be provided for roof drainage. At no
time shall roof run off be directed to a wetland resource area or abutting properties.
9. Grading shall be accomplished so that the project shall not cause flooding or storm damage to Wetland Resource
Areas.
10. A "work limit " line shall be established with Erosion Controls (i.e. straw bales, staked filter fabric, bark mulch, “silt
sacks”, products made with r ice straw, and other weed-free products or approved by the Commission). Hay bales
are not allowed. It is the applicant's responsibility to implement and maintain appropriate and adequate erosion
controls measures throughout the construction process.
11. Species of the replacement trees are to be confirmed with the CA prior to planting. These trees shall be in place and
established for 2 years, and any trees that have died may require replacement prior to the COC being issued
12. Debris, including litter, shall be picked up immediately. Any excess material that is excavated from the job site shall
be disposed of at a location approved by the Conservation Administrator or in a covered dumpster.
13. Any area that is disturbed during construction shall be revegetated immediately or as soon after the growing season
commences, with appropriate native plantings. Permanent stabilization shall be carried out in order to minimize
erosion.
14. Upon completion of the project, a "Request for a "Certificate of Compliance" shall be submitted by the applicant to
the Conservation Commission for review. The "Order of Conditions" shall be considered incomplete until the
"Certificate of Compliance" is issued by the Conservation Commission and recorded at the Registry of Deeds.