HomeMy WebLinkAboutROAD 2024-1 228 Rte 28 - Application Narrative and Supp MaterialsGreen Seal Environmental, LLC
114 State Road, Bldg. B, Sagamore Beach, MA 02562
T: 508.888.6034 F: 508.888.1506
www.gseenv.com
ENGINEERING | ENVIRONMENTAL | SURVEY
MassDOT Certified
May 9, 2024
Joanne Crowley, Chair
Yarmouth Planning Board
1146 Route 28
South Yarmouth, MA 02664
RE: Application for ROAD - Proposed A Plus Market
228 Route 28
GSE Project No. CNSR-2023-0001:1
Dear Ms. Crowley and members of the Board:
On behalf of our client, ConServ Group Inc., we are submitting an application under the provisions of
Zoning Bylaw Section 411, the Revitalization Overlay Architectural District (“ROAD”) for the
referenced project. Our client is proposing to construct a new building at the referenced location to
house a retail business, an A Plus Market. The second floor of the building will be residential
apartments. This construction is shown on the attached Site Plans and Building Plans.
These plans have been prepared in reference to Zoning Bylaw Sections 103.3.1, Site Plan Review and
Section 103.3.4, Plans. The applicant believes that these plans are consistent with and substantially
comply with the Yarmouth Architectural and Site Design Standards.
Project Description
The property was previously occupied by a restaurant which has since been demolished. The
applicant proposes to construct a new 2-story mixed-use building as shown on the plans submitted.
The building style, color, and materials are in keeping the Standards and have been revised to
respond to comments from Planning staff. Under the proposal the site will be landscaped in
accordance with the bylaw and standards, which represents a substantial improvement of the
existing condition of the site. New paved parking will be provided, with sufficient parking to address
the bylaw requirements. Lighting and stormwater controls will be provided, to include a “rain
garden” that will provide attractive plantings in addition to the stormwater function.
None of the proposed work is within 100 feet of a vegetated wetland. We understand that the
Stormwater Management Regulations are administered by the Conservation Department and
stormwater calculations and reports will be submitted to them as part of that process.
The septic system serving that restaurant is still in place, and as shown on the Site Plans, the client
intends to connect the new building to it. The site is located in Phase 1 of Sewer Contract 6, which is
anticipated to be completed in 2026. As shown on the plan, a new force main from the existing
Green Seal Environmental, LLC
2
septic system to a proposed sewer manhole near the frontage will be installed to facilitate
connection to municipal sewer when that becomes available.
We understand that the Massachusetts Department of Transportation (MassDOT) is planning on
corridor improvements to Route 28. Their current design will need to be modified to address the
improved driveway locations on the proposed site plan. We will coordinate with them during the
curb cut approval process, after all zoning permits are issued by the Town of Yarmouth (MassDOT
will not initiate plan review until all local permits are issued.)
The existing driveways are separated by 79.3 feet. The proposed driveways will substantially
improve the separation, increasing it to 167.3 feet. These driveways cannot meet the separation
requirements in Section 301.4.7, and are not required to, as the Section states: “… shall observe
minimum separations as follows, unless precluded by lot configuration in existence on the date of
adoption of this bylaw”. The Yarmouth Zoning Bylaw was adopted on April 11, 1978, and
Massachusetts adopted zoning in 1954. The records on file in the Barnstable Registry of Deeds
indicate that this lot configuration hasn’t changed since 1945 or earlier. Regardless, MassDOT has
jurisdiction over driveways on State Highways.
Economic and Other Benefits to the Town of Yarmouth
The project will provide economic benefit to the Town of Yarmouth in many ways. As is stated in
the Site Plan Review report, mixed-use developments along the Route 28 corridor benefit the town
in that they preserve the commercial corridor while also providing much needed apartment rental
housing. In this case, approximately 9,985 square feet of retail is proposed on the ground floor. The
retail use will be a local provider of food-related items, supporting restaurants and community
residents. It will also provide employment, and the presence of new workers will bring more activity
to nearby businesses for such things as eating out, auto service, shopping, etc. This applies both to
the short-term construction workers and the workers who will run the business.
A total of 13 new dwelling units are proposed on the second floor, to include ten 1-bedroom units
and three 2-bedroom units. The addition of these units can support housing for an estimated 32
persons. In accordance with Section 412.2.3, two of these units will qualify as affordable. These
dwellings are conveniently located near businesses that can provide employment, shopping, local
library and other services for the residents. As stated above, local businesses will benefit from the
increased activity provided by more residents located within the community.
The previous restaurant building was demolished. According to the Yarmouth Assessor’s office, the
property is taxed only on the land value and the small value of the asphalt paving that remains.
Constructing the new building will result in substantially increased property value, which provides
an economic benefit to the town in the form of increased ongoing tax revenue.
Replacing a vacant parcel without access controls with a new, occupied building will provide
additional value to the community. The attractive building and site proposed will improve aesthetics
Green Seal Environmental, LLC
3
along this corridor. A new mixed-use building, occupied with active business and housing is a more
productive use of the property than a single-use active business or vacant land. This is true in terms
of increased property taxes and also year-round occupied space with a healthy mix of commerce
and residential use, which is beneficial to abutters, the Town of Yarmouth and its residents.
There will be tax revenue benefits from this mixed-use project. The annual Real Estate Taxes for the
vacant land are approximately $3,600.00. This is based upon the 2024 total valuation of
$496,200.00 for the land and paving-asphalt improvement and the tax rate for the Town of
Yarmouth for Fiscal Year 2024 of $7.38 per thousand. The annual Real Estate Taxes for this mixed-
use project are estimated to be $36,600.00. This is a $33,000 increase over the current real estate
tax paid and is based upon the estimate that the mixed-use property will be valued at approximately
$5,500,000.00. Additionally, this is a $20,000 increase over an alternate single-use property with
approximately 9,985 square feet of retail proposed on the ground floor. The annual Real Estate
Taxes for an alternate single-use project are estimated to be $16,600 based upon the estimate that
the single-use property estimated will be valued at approximately $2,500,000.
The project was subject to Site Plan Review. The report arising from that review is attached. The
plans have been revised to address that review, in our opinion. There are several review comments
that warrant some explanation:
Photometric plan. A photometric plan has been added to the Site Plan.
Snow Storage. A designated snow storage area, along with a description of snow removal,
has been added to the Site Plan.
In-lot trees. The provision of in-lot trees has been modified to meet the interpretation of
the bylaw requirement, in part by adding substantial new landscaped areas.
Pavement area for truck turning has been reduced substantially to accomplish
this.
Rain garden. The proposed rain garden in front of the building has been reduced in depth
and reconfigured to allow for more tree plantings.
Front buffer trees. Additional trees have been added to the site frontage, in excess of the
minimum required.
Architecture. Suggested changes to the design have been considered and some changes
made. No front facing entrance has been provided, the side entrance is closer
to parking and a front entrance will require walkways and compromise the
front landscaping when few pedestrians are expected.
Plantings. Tree plantings have been revised to specifically address bylaw requirements.
Dumpster. The dumpster has been relocated to allow for more landscaping.
Pedestrian access. Concrete sidewalk from Route 28 to the retail entrance and near the dwelling
entrance has been added to the Site Plan.
Pavement. Delivery truck and fire equipment simulations have been included in the Site
Plan.
Curb cut access. MassDOT will not review or approve curb cuts until all local zoning approvals
have been issued. Since the site has two long-established curb cuts, and the
Green Seal Environmental, LLC
4
proposal increases their separation and conforms with their written
requirements, MassDOT approval is expected.
Loading bay pump. The configuration and pumps are required to discharge runoff to the
stormwater system.
O&M report. A stormwater Operations & Maintenance Report was included in the
Stormwater Report.
Stormceptor. The stormwater sizing calculations in the Report confirm that it can
accommodate the small watershed served. The model chosen works with a
grate installed.
Fire lanes. Fire lane markings have been added to the Site Plan.
Grease trap. The Site Plans include an inspection schedule.
Domestic supply. The 1 inch domestic water supply has been changed to PE tubing.
Kindly advise us if you need additional copies of these documents, or if there are any other
requirements not addressed in this submittal. We look forward to reviewing this project at the next
available Planning Board meeting.
Sincerely,
GREEN SEAL ENVIRONMENTAL, INC.
Jack O’Leary PG CPESC
Vice President of Operations
cc: ConServ Group, Inc.
Town Clerk (1 copy)
Planning Department (1 copy)
Design Review Committee (1 copy)
Community and Economic Development Committee (1 copy)
Encl.: Site Plans (7 full size)
Building Plans (7 full size)
Stormwater Report (1 copy)
Completed ROAD Application
Certified List of Abutters
Application Fee ($200 payable to the Town of Yarmouth)
Site Plan Review report
228 ROUTE 28, WEST YARMOUTH, MA 02673Emad Zahran, A Plus Real Estate LLCComposite Shingles Light MistComposite Lap Siding Pearl GrayRoofing Shingles 7:12 Georgetown Gray GT GrayX Vinyl Clad WhiteX Storefront Mill Finish1x4 1x6 WhiteX PVC WhiteX Aluminum WhiteX Aluminum BlackNA NARefer to Landscaping PlanSiding Type & Material: Base - Brick Veneer with Brick Sill Color: PlatinumMaterial Selections Attached
PVC Trim
228 Route 28 South Yarmouth
Color: White
Fiber Cement Lap Siding
228 Route 28 South Yarmouth
OPTION 1
OPTION 2
Fiber Cement Shingles
228 Route 28 South Yarmouth
FINISH COLOR
Roofing
228 Route 28 South Yarmouth
Certainteed
Landmark Shingles
Color: Georgetown Gray
Brick Base
228 Route 28 South Yarmouth
Interstate Brick
Color: Platinum
(Mortar Color to closely
match brick)