HomeMy WebLinkAboutfinal affidavit 11/7/24 Efficiency Energized.
RISE
11/7/2024
Town of Yarmouth
Building Department
1146 Route 28
South Yarmouth, MA 02664
RE: Insulation Permit BLDX-23-3530
Good afternoon,
The MassSave subcontractor that pulled the permit for the weatherization work at 36 Clinton Drive in
Yarmouthport, is no longer in business and is no longer participating in the MassSave program.This customer,
Anna Cannon, reached out to inform us the permit is still open.The basement insulation on the permit was
inspected by a certified Building Performance Institute (BPI) representative.
The measures implemented were observed to meet local and state requirements.
Thank you,
Tic 4Ke- 1a
Dan Ancahas
QA/QC Supervisor,The RISE Group Inc.
765 Attucks Lane
Hyannis, MA 02601
508-568-1926 x6621
Program
RISE Engineering cic-HEs Installation
RISE A division of Thielsch Engineering Client# Receipt
765 Attacks Lane,Hyannis,MA 02601 337525
508-568-1926 X-6609 FAX 508-5684933 Work Order
26103 Page 1
Contractor: 0041 McCarthy Construction Contract Date Start Date
Address: PO Box 52 West Dennis,MA 02670
3/24/2022 *"'utr5
•jrt
Primary Anna Cannon Phone: Alt.Phone: Auditor
Service 36 Clinton Drive Donald Bok
Yarmouthport,MA 02675
Home Phone: (781)706-9558 Work
Cell Phone: Email(s):afc64@hotmaii.com
AIR SEALING:
Performed 2-- working-hours of air sealing.
Including:
Blower Door Test
Combustion Safety Test
Combustion Safety&Blower Door Test
M Final CFM50: (1•1 `� c`
BASEMENT CEILING: Install(1240)square feet of R-30 faced fiberglass insulation.
I agree to all changes listed above and understand there might be an increase In my co-payment for which I will be
responsible for paying.
I also confirm the measures have been completed to my satisfaction and have received a Certificate of Completion.
I understand this does not void any warranties provided to me by the Contractor.
RISE/CONTRACTOR SIGNATURE V CUSTOMFR SIGNATURE
SIGN DATE SIGH DAT
4/1/2022 11:10:48 AM