HomeMy WebLinkAboutCOC request 7.2.2025ILEX Environmental
kbarnicle@ilexenvironmental.com
508-843-7981
July 2, 2025
Yarmouth Conservation Commission
1146 Route 28
Yarmouth, MA 02664-4492
Re: Request for Certificate of Compliance
Cape Cod Hospital, Cranberry Bog Restoration Work
Yarmouth, Massachusetts
MassDEP File No 83-1415 (1997)
Dear Members of the Commission:
On behalf of the Cape Cod Hospital, ILEX Environmental, Inc. (ILEX) is requesting a Certificate of
Compliance for the restoration of former cranberry bogs at the Cape Cod Hospital bogs in
Yarmouth, Massachusetts approved by the Order of Conditions issued on August 13, 1997
(MassDEP File No. 83-1415). Supplemental restoration work was submitted under a separate
Notice of Intent (MassDEP File No. 82-1525) issued in 2000.
The wetland restoration work approved by the Order of Conditions was subject to an agreement
between the Cape Cod Hospital and the US Environmental Protection Agency (EPA) in regard to
enforcement action taken in 1996 and subject to a 1997 Compliance Consent Agreement. The
Notice of Intent was submitted soon after the EPA agreement was approved.
The restoration of previously-farmed bogs included modifications to flood control (or outlet)
structures to maintain wetland hydrology, grading and seeding of upland areas, and removal of
irrigation system components. Figure 3 included with the Notice of Intent is attached for your
convenience which identifies outlet structures and areas where work was proposed and
completed as summarized by the following bullets:
• Outlet structures replaced with new flashboards (C1 and D1)
• Outlet structures maintained with existing flashboards (A1, A2, and B1)
• Outlet structure repaired with new flashboards (E1)
• Rip-rap overflow channel installed (Area 1)
• Dike stabilized with seed mix (Area 2)
• Sand pit stabilized through grading and seeding (by Bog F)
• Removal of irrigation system components
• Installation of piezometers for five year long monitoring period
All work proposed was performed in accordance with the Order of Conditions as supported by the
enclosed 2002 Monitoring Report prepared by ENSR (dated May 2003) which details the fifth and
final year of monitoring required by the EPA. As such, we request that the Yarmouth Conservation
Commission issue a Certificate of Compliance for this Order of Conditions.
Page 2
We have enclosed the filing fee of $150.00. In addition, we have attached the following documents:
• Request for Certificate of Compliance Form
• Administrative Checklist
• Waiver of 21 Day Requirement
We look forward to working with the Yarmouth Conservation Commission to obtain the Certificate
of Compliance for this project and close out this file. Please do not hesitate to contact me with any
questions. Thank you.
Sincerely,
Kathryn S. Barnicle
ILEX Environmental, Inc.
kbarnicle@ILEXenvironmental.com
508-843-7981
Cc: Michael G. Jones, Cape Cod Hospital
Attachments: Figure 3 from Notice of Intent
2002 Monitoring Report prepared by ENSR (dated May 2003)
wpaform8a.doc •• rev. 5/29/14 Page 1 of 2
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 8A – Request for Certificate of Compliance
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
DEP File Number:
SE83-1415
Provided by DEP
A. Project Information
Important:
When filling out
forms on the
computer, use
only the tab
key to move
your cursor -
do not use the
return key.
1. This request is being made by:
Kathryn S. Barnicle
Name
35 Vernon Street
Mailing Address
Plymouth
City/Town
MA
State
02360
Zip Code
508-843-7981
Phone Number
2. This request is in reference to work regulated by a final Order of Conditions issued to:
Cape Cod Hospital
Applicant
August 13, 1997
Dated
SE83-1415
DEP File Number
Upon completion
of the work
authorized in
an Order of
Conditions, the
property owner
must request a
Certificate of
Compliance
from the issuing
authority stating
that the work or
portion of the
work has been
satisfactorily
completed.
3. The project site is located at:
0 Rosetta Street
Street Address
Yarmouth
City/Town
28 (formerly 23)
Assessors Map/Plat Number
58.1.1 (formerly S001)
Parcel/Lot Number
4. The final Order of Conditions was recorded at the Registry of Deeds for:
Cape Cod Hospiral
Property Owner (if different)
Barnstable
County
10919
Book
206
Page
Certificate (if registered land)
5. This request is for certification that (check one):
the work regulated by the above-referenced Order of Conditions has been satisfactorily completed.
the following portions of the work regulated by the above-referenced Order of Conditions have
been satisfactorily completed (use additional paper if necessary).
the above-referenced Order of Conditions has lapsed and is therefore no longer valid, and the
work regulated by it was never started.
wpaform8a.doc •• rev. 5/29/14 Page 2 of 2
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 8A – Request for Certificate of Compliance
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Town of Yarmouth Wetland By-law, Chapter 143
DEP File Number:
SE83-1415
Provided by DEP
A. Project Information (cont.)
6. Did the Order of Conditions for this project, or the portion of the project subject to this request, contain
an approval of any plans stamped by a registered professional engineer, architect, landscape
architect, or land surveyor?
Yes If yes, attach a written statement by such a professional certifying substantial
compliance with the plans and describing what deviation, if any, exists from the plans
approved in the Order.
No
B. Submittal Requirements
Requests for Certificates of Compliance should be directed to the issuing authority that issued the final
Order of Conditions (OOC). If the project received an OOC from the Conservation Commission, submit
this request to that Commission. If the project was issued a Superseding Order of Conditions or was the
subject of an Adjudicatory Hearing Final Decision, submit this request to the appropriate DEP Regional
Office (see http://www.mass.gov/eea/agencies/massdep/about/contacts/find-the-massdep-regional-office-
for-your-city-or-town.html).
Rev 3/2025
Administrative Checklist
Certificate of Compliance
General Information:
•All filings must be made on Town of Yarmouth forms.
•All applications must be submitted two weeks prior to the next scheduled Conservation
Commission meeting. Refer to Meeting Schedule.
•Failure to follow the Administrative Checklist shall result in an Administrative Incomplete
Application and will not be scheduled for a Public Hearing.
•Contact the Conservation Office if you need assistance.
Submitting an Application:
Hardcopy of the COC application mailed to or dropped off at the Conservation
office in Town Hall.
______
______
Signed statement from an Engineer or similar professional to who prepared the
approved plan stating the date of a recent site inspection and certifying compliance
with the permit and outlining departures from the approved plan, if any exist.
As-Built plan – *Refer to issued Order of Conditions: Special Conditions to
determine if required*.
Pdf of the COC request including application, letter, & as-built plan if needed
emailed to bdirienzo@yarmouth.ma.us and jjerolimo@yarmouth.ma.us
Local filing fee. Refer to Fee Schedule. Make check payable to “Town of
Yarmouth” and include property address in memo.
All forms, Fee Schedule and Meeting schedule can be found at
https://www.yarmouth.ma.us/696/Filing-Forms.
*Chech the Yarmouth Street Index for parcel-related Conservation
documents.
Yarmouth Conservation Commission • 1146 Route 28 • South Yarmouth, MA 02664-4492
Tel. (508)-398-2231 Ext. 1288 • Fax (508)-398-0836 • TTD# (508) 398-2231 • bdiriezno@yarmouth.ma.us
CONSERVATION
OFFICE
N/A
MassDEP File No. 83-1415
N/A
21 day waiver Rev July 2024 New Logo
CONSERVATION
OFFICE
Town of Yarmouth
Conservation Commission
21-DAY WAIVER
Please complete this form, sign at the bottom and return to the Conservation Office.
I, , hereby waive the
21-day time period for a public hearing/meeting and/or issuance of the:
OOC / DOA / COC / ORAD following receipt of my filing of a:
Notice of Intent
Request for Determination of Applicability
Request for Certificate of Compliance
Other
by the Yarmouth Conservation Commission under Massachusetts General Laws,
Ch. 131, sec. 40, and/or under Yarmouth Wetland Bylaw.
The application was submitted on
(date received by Conservation Office)
for work at
(project address/location)
I am the: Applicant
Applicant's Representative
Property Owner
Signature Date
NOTE: Please be advised that you will be notified of the meeting date once this
application has been assigned to a Conservation Meeting Agenda at the email address
listed on the application.
Kathryn S. Barnicle
July 2, 2025
July 2, 2025
DEP File No. 83-1415
Bay View Street, Yarmouth