Loading...
HomeMy WebLinkAboutRiverwalk Park Inspection Report 2025-08-05 MEMORANDUM BETA GROUP, INC. www.BETA-Inc.com BACKGROUND On August 5, 2025, BETA staff visited the Yarmouth Riverwalk Park Site located at 669 Route 28 in Yarmouth, MA to perform environmental monitoring during the Phase 1 construction period. The purpose of this inspection was to document the conditions of the salt marsh, erosion controls, and park during Phase 1 of construction. The following was observed during the inspection: CURRENT CONSTRUCTION Construction of the site is underway (Photo 1), and the following approved site elements have been constructed or partially constructed:  Invasive species have been removed throughout the site;  Construction of the boardwalk has been substantially completed (Photo 2);  Construction of the playground has been substantially completed (Photo 3);  Stormwater infrastructure has been installed;  Stabilized aggregate walking paths have been installed (Photo 4);  Plantings have been installed;  Some site elements including light fixtures, bikes racks, and benches have been installed;  Pavement has been installed where proposed (Photo 4);  Portions of the site have become partially stabilized;  Utilities have been partially installed; and  The restroom facility has been partially constructed (Photo 5). During the site visit, no work was occurring. BOARDWALK/SALT MARSH During this inspection areas of exposed soil in the salt marsh adjacent to the constructed boardwalk were measured using drone and on the ground measurements (Attachment A). Generally, areas of exposed soil on the eastern side of the boardwalk have become revegetated (Photos 6 and 7). The western side of the boardwalk was observed as having less vegetative cover than the eastern side of the boardwalk (Photos 8 and 9). The salt marsh conditions will continue to be monitored, and supplemental plantings proposed to be planted in areas of exposed soil can be found in Attachment A. Date: August 22, 2025 Job No.: 22.10056.00 To: Amanda Lima, PE Town Engineer Kathy Williams, PE, Town Planner Brittany DiRienzo, Conservation Administrator From: Arek Galle, RLA, AICP, Senior Associate, BETA Group Prepared: Anna Haznar, Staff Scientist Laura Krause, Senior Project Manager Subject: Yarmouth Riverwalk Park and Boardwalk Phase 1 Yarmouth, MA Site Monitoring August 22, 2025 Page 2 of 3 Plugs and seed were installed within the area of exposed soil on both the eastern and western trail upgradient of the salt marsh (Photo 10 and 11). Erosion controls upgradient of the salt marsh were recently replaced and are in good condition. These areas will continue to be monitored to determine if supplementary seeding is necessary. EROSION CONTROLS Two (2) layers of erosion controls consisting of silt fence and compost filter tubes are present along a majority of the limits of work (Photo 12), except in locations where compost filter tubes have been removed and in locations where silt fence was not proposed. Compost filter tubes were observed in varying stages of biodegradation in multiple locations throughout the site. All erosion controls in proximity to Resource Areas, including the Parker River, were observed in good condition (Photo 13), and no sedimentation was observed past the limits of work. To ensure no sediment enters Resource Areas, erosion controls should be maintained. During this site visit, a section of erosion controls adjacent to the to the woodland path and erosion controls along the woodland path were approved for removal (Photo 14) and another section was approved for relocation. This is further discussed in Attachment A. RIVERWALK PARK Currently, Phase 1 of the Riverwalk Park is under construction. There is one (1) soil stockpile located onsite associated with active construction and stabilization. Stabilization of stockpiles should commence if active work is not occurring, or within 14 days of the cessation of work in the area. Exposed soil that requires stabilization is present throughout the site in areas where work is ongoing (Photos 3 and 4). Erosion controls were found to be in good condition downgradient of all areas of exposed soil. During this inspection, no significant invasive plant species pressure was observed internal of erosion controls; however, the site should continue to be monitored for success of the invasive species removal plan. Species including bush honeysuckle (Lonicera spp.), autumn olive (Elaeagnus umbellate), black swallowwort (Cynanchum louiseae), and bittersweet (Celastrus orbiculatus) were observed in small populations outside of the limits of work directly adjacent to erosion controls. Japanese knotweed (Fallopia japonica) was also observed within a planted area, where a large population was removed (Photo 15). Additionally, a population of bittersweet was observed (Photo 16) within the boulders adjacent to the walking path. The population of cypress spurge (Euphorbia cyparissias) – a species considered likely invasive by the Massachusetts Invasive Plant Advisory Group (MIPAG) - is present within the boulders adjacent to the walking path. SUMMARY Currently, Phase 1 of the Yarmouth Riverwalk Park and Boardwalk Project is near completion, with work primarily concentrated at the Phase 2 restroom facility, an future work associated with installation of the kayak launch. Generally, pathway work is now complete and stabilization of the remainder of exposed soil is required. Observations made during the August 5, 2025 site inspection include the following:  Areas of exposed soil within the salt marsh adjacent to the boardwalk have been measured and proposed installation of plugs can be found in Attachment A,  Plugs and seed have been installed within the areas of exposed soil adjacent to the western and eastern side of the boardwalk upgradient of salt mash,  Erosion/sediment controls throughout the site are in varying condition, with all erosion controls upgradient of Resource Areas being in good condition, August 22, 2025 Page 3 of 3  With review and concurrence with Conservation, upland erosion controls may be removed in some areas,  Areas of exposed soil that require stabilization are present throughout the site but generally were found to have erosion controls downgradient,  Soil stockpiles at the site that are currently being used and should be temporarily stabilized if not in use for 14 days or more,  Minor invasive plant species presence /pressure was observed outside of the work area directly adjacent to erosion controls and within a naturalized area near the kayak launch. Attachments: - Photographic Documentation - Site Aerial Image - Attachment A – Site Walk - Outcomes PHOTOGRAPHIC DOCUMENTATION Yarmouth Riverwalk Yarmouth, Massachusetts Photographs Documented August 5, 2025 Photo 4 View of the constructed roadway, aggregate paths, and exposed soils– facing north. View of the constructed playground. Note exposed soils present adjacent to the playground require stabili- zation—facing southwest. Photo 3 PHOTOGRAPHIC DOCUMENTATION Yarmouth Riverwalk Yarmouth, Massachusetts Photographs Documented August 5, 2025 Photo 6 View of an areas of marsh vegetative regrowth on the eastern side of the boardwalk —facing west. View of the partially constructed restroom facility – facing north. Photo 5 PHOTOGRAPHIC DOCUMENTATION Yarmouth Riverwalk Yarmouth, Massachusetts Photographs Documented August 5, 2025 Photo 8 View of an area on the western side of the boardwalk with minimal vegetative recovery —facing south. Another view of an area of marsh vegetative regrowth on the eastern side of the boardwalk —facing north. Photo 7 PHOTOGRAPHIC DOCUMENTATION Yarmouth Riverwalk Yarmouth, Massachusetts Photographs Documented August 5 and 12, 2025 Photo 10 View of the plugs and seed installed in an area of exposed soil upgradient of the eastern side of the salt marsh—facing east. Another view of an area of minimal vegetative recovery on the western side of the boardwalk —facing northeast. Photo 9 PHOTOGRAPHIC DOCUMENTATION Yarmouth Riverwalk Yarmouth, Massachusetts Photographs Documented August 12, 2025 Photo 12 Typical view of erosion controls in good condition at the Site —facing south. View of the plugs and seed installed in an area of exposed soil upgradient of the western side of the salt marsh—facing southeast. Photo 11 PHOTOGRAPHIC DOCUMENTATION Yarmouth Riverwalk Yarmouth, Massachusetts Photographs Documented August 12, 2025 View of erosion controls adjacent to the Parker River under the kayak launch in good condition – facing east. Photo 13 View of erosion controls approved for removal along the woodland path—facing south. Photo 14 PHOTOGRAPHIC DOCUMENTATION Yarmouth Riverwalk Yarmouth, Massachusetts Photographs Documented August 12, 2025 View of a population of Japanese knotweed within a planted area —facing west. Photo 15 View of the population of bittersweet within the boulders adjacent to the walking path —facing east. Photo 16 Yarmouth Riverwalk Park — August 5, 2025 偨潴漠ㄲ 偨潴漠ㄳ 偨潴漠ㄵ 偨潴漠ㄶ Yarmouth Riverwalk Park — August 5, 2025 偨潴漠㄰ 偨潴漠ㄱ 偨潴漠ㄴ Attachment A Marsh Site Walk BETA GROUP, INC. www.BETA-Inc.com BACKGROUND On August 5, 2025, a site walk was conducted to assess current conditions of the Riverwalk Park as well as discuss conditions found at the salt marsh and proposed removal of specific locations of erosion controls. Attendees of the site walk included: - Brittany DiRienzo, Town of Yarmouth - Amanda Lima, Town of Yarmouth - Kevin Morrissey, Town of Yarmouth - Arek Galle, BETA Group Inc. - Laura Krause, BETA Group Inc. - Bill McGrath, BETA Group Inc. - Andrew Pichette, BETA Group Inc. - Anna Haznar, BETA Group Inc. - David Ankener, BETA Group Inc. - Rob Doane, Robert B Our Co Inc. - Justin Spurr, Robert B Our Co Inc. - Jay Merriman, Chase Landscape Inc The following items were reviewed and discussed at the site walk: 1. SALT MARSH RECOVERY During this site walk pink survey flags were placed along the perimeter of exposed soils within the salt marsh. These locations were approved by the Conservation Administrator as locations requiring installation of supplemental plantings. Drone footage and on the ground measurements were then taken to determine the extent of exposed soil within the salt marsh. Four (4) distinct areas (W-1, W-2, C-1, and C-2) totaling approximately 3,950 square feet of exposed soil were mapped throughout the salt marsh. It was determined that bare root plug plantings will be installed in these areas. Areas of high marsh will be supplemented with salt meadow cordgrass (Spartina patens) and areas of lower marsh will be supplemented with smooth cordgrass (Spartina alterniflora). The location of species has been determined by topography and by observing species growing in the general vicinity of the proposed plantings. Plantings for each area as follows: Marsh Area Size of area (Square feet) Qty. Spartina alterniflora plugs Qty. Spartina patens plugs W-1 2,240 428 720 W-2 290 N/A 150 C-1 1,060 550 N/A C-2 340 170 N/A TOTAL 3,950 SAY 1,130 SAY 870 Date: August 22, 2025 Job No.: 22.10056.00 Attachment A – Site Walk Outcomes August 25, 2025 Page 2 of 3 Marsh grass plug plantings shall be installed approximately 18-inches on center. Bare root plugs will be installed per Natural Resource Conservation Service (NRCS)1 guidelines which states; 1) installation of plugs should occur before September 30th, 2) into holes that are approximately 3 inches in diameters, and 3) deep enough to fully cover the roots when fully extended. 2. TREES PLANTED IN SALT MARSH Eastern Red Cedar trees (Juniperus virginiana) were planted in the marsh in 2024 as visual screens as required for neighbor mitigation during the permitting process. Eight (8) trees were planted in 2024. Five trees were omitted from the planting in 2024 due to conflicts with the helical pile installation work. They remain to be planted in 2025. Several of the trees that were planted did not survive the winter. The following decisions were made: 1) Trees planted in 2024 that were determined to be dead or showing low vigor and growth shall be left in place. Any burlap, rope and tree stakes shall be removed. 2) The missing five trees and tree replacements to offset dead trees installed in 2024 shall be planted. 3) The new trees may be furnished at a smaller size than originally specified (7’h-8’h B&B) 4) Additional trees may be required depending on the size sourced and proposed, contingent on availability. 4) The new trees shall be planted at higher marsh elevations and closer to existing trees where possible, generally off to the north-west of Overlook #3. 3. ILEX OPACA -HOLLY TREE PLANTINGS The project specifies plantings of American Holly (Ilex opaca) in wooded areas of the project along the woodland trails. These will supplement existing holly trees observed to occur on site. Jay Merriman of Chase Landscape advised that sourcing the holly trees specified was presenting challenges. The Conservation Administrator was of the opinion that the native species (Ilex opaca) sourced at a smaller size than specified (4’h-6’h B&B) and in an increased quantity could be considered as a substitution. It was also discussed that a small percentage of the holly trees could be furnished as a cultivar such as Ilex x ‘Nellie R. Stevens’, along with smaller, native Ilex opaca resulting in a mix. Chase Landscape advised they will continue to source plant material and provide options to the group based on their research on availability. 4. UPLAND EROSION CONTROLS A review of the erosion controls in the forested areas was conducted. Approval by the Conservation Administrator was granted to remove silt fence erosion controls along the woodland pathways leading to the boardwalk approaches. The existing straw wattles immediately up-gradient to the salt marsh at the eastern approach will remain in place on the east approach. Replacement/repairs shall be made as needed. Locations where erosion controls were approved for removal are approved to be finish graded and stabilized with the approved seed mix. A portion of the silt fence erosion controls east of the at the convergence of the two paths in the woods was approved to be reconfigured to facilitate grading and drainage. Erosion controls in place closest to the Parkers River will remain at the limits of work and will be monitored to ensure they are in good condition. See attached plan calling out locations for erosion control removal, relocation, and maintenance, as discussed in the field. 1 Smooth cordgrass (Spartina alterniflora Loisel.) Plant Guide August 25, 2025 Page 3 of 3 The following Attachments provide additional information: - Marsh Restoration Areas - Erosion Control Removal and Relocation Areas 250 SF 128 SPARTINA ALTERNIFLORA AREA W-2 - 290 SF 552 SF 285 SPARTINA PATENS 265 SF 135 SPARTINA ALTERNIFLORA 849 SF 435 SPARTINA PATENS 322 SF 165 SPARTINA ALTERNIFLORA AREA W-1 - 2,240 SF 290 SF 150 SPARTINA PATENS AREA C-1 - 1,058 SF 1058 SF 550 SPARTINA ALTERNIFLORA AREA C-2 - 333 SF 333 SF 170 SPARTINA ALTERNIFLORA Marsh Restoration Areas Scale: 1"=30'0 Parker's River Park Boardwalk Loop 8/12/2025 Yarmouth, MA 25 50 100 D MA R O U T E 2 8 PARKERS RIVER PARKERS RIVER E S - 4 E S - 4 E S - 4 E S - 4 E S - 4 E S - 4 E S - 4 E S - 4 APPROXIMATE LIMITS OF TOWN WASTEWATER PUMP STATION PROJECT CONTRACTOR SHALL COORDINATE WORK WITH TOWN PROJECT TEMPORARY SEDIMENT CONTROL BASIN NO. 1 TEMPORARY SEDIMENT CONTROL BASIN NO. 2 D D D PHASE 2 WORK IN THIS AREA UNDER SEPARATE CONTRACT LIMIT OF CLEARING (TYP.) LIMIT OF CLEARING (TYP.) MIN. 20' WIDE CONSTRUCTION ACCESS ROAD (ON-GRADE) ROUGH GRADE TO WITHIN 1' OF FINISH GRADE (TYP.) INSTALL PARK ACCESS DRIVE INSTALL INFILTRATION SYSTEM NO. 1 GRADE & SEED STORMWATER SWALE INSTALL TIDEGATES EACH PIPE (TYP) INSTALL OUTLET FLARED END INSTALL AREA DRAIN 2 & 8" DI PIPE PROTECT WITH HAY BALES DURING STAGE 2 INSTALL OUTLET CONTROL STRUCTURE 1 STAGING AREA FOR BOARDWALK UTILIZE TRACKING PADS TO REDUCE IMPACT OF CONSTRUCTION GRADE & SEED BERM MIN. 20' WIDE CONSTRUCTION ACCESS ROAD (ON-GRADE) INFILTRATION BASIN NO. 1 - CONSTRUCTION STAGE 2 ROUGH GRADE TO WITHIN 1' OF FINISH GRADE 8" DISCHARGE PIPE (TEMPORARY) EQUIPMENT STORAGE AREA AND PARKING. CLEANING & FUELING OF VEHICLES AND MACHINERY SHALL BE LIMITED TO THIS AREA CONSTRUCTION TRAILERS - FINAL LOCATION TO BE DETERMINED BY CONTRACTOR STAGING AREA FOR KAYAK LAUNCH FLOAT AND BOARDWALK PROVIDE SPACE & UTILITIES FOR PHASE 2 CONSTRUCTION TRAILER (BY OTHERS) INSTALL RESERVOIR COURSE AND ROUGH GRADE TO WITHIN 1' OF FINISH GRADE 8" DISCHARGE PIPE (TEMPORARY) INSTALL 12" HDPE PHASE 2 ACCESS INSTALL 8" DI PIPE INSTALL STONE AT PIPE ENDS, FLARED ENDS, 8" HDPE PIPE INSTALL FLARED END INSTALL STONES AT PIPE ENDS (TYP) INSTALL 12" HDPE LAND & WATER CONSERVATION FUND GRANT LIMITS* INSTALL HMA PATHWAY INSTALL PLAYGROUND, PATHS AND SITE FURNISHINGS PARC GRANT LIMITS* C.2.1 CONSTRUCTION SEQUENCING NOTES STAGE 1 CONSTRUCTION - PARK SITE: 1.SET ALL PERIMETER EROSION CONTROL MEASURES FOR THE SITE. 2.STAKE LIMIT OF WORK LINE AT REGULAR INTERVALS REVIEW WITH OWNER'S REPRESENTATIVE FOR FINAL APPROVAL. SET VEGETATION PROTECTION MEASURES. 3.ESTABLISH LAY-DOWN, WASH-OUT, CLEANING, FUELING & STAGING AREA FOR EQUIPMENT AND EMPLOYEE PARKING. 4.INSTALL CONSTRUCTION ENTRANCE TRACKING PAD, CONSTRUCTION GATE AND FENCING 5.PROVIDE ACCESS DRIVEWAY AND STAGING AREA FOR BOARDWALK CONSTRUCTION. 6.CLEAR VEGETATION TO LIMITS SHOWN IN THE PLANS AND AS APPROVED IN THE FIELD. 7.PRUNE AND THIN TREES AND SHRUBS AS DIRECTED. 8.IMPLEMENT STAGED INVASIVE PLANT MANAGEMENT PROGRAM. 9.GRUB AREAS WITHIN THE PRIMARY LIMITS OF STAGE I AREA AS INDICATED. 10.GRUB FOR WOODLAND PATHWAY AREAS UNDER STAGE 2. 11.REMOVE EXISTING EXPOSED ASPHALT AND CONCRETE PAVEMENT. REMOVE MISC. DEBRIS & RUBBISH. 12.STRIP ALL AREAS IN STAGE 1 OF UPPER SOIL STRATA AS INDICATED. (ORDINARY FILL FOR RE-USE). 13.CRUSH/PULVERIZE & PROCESS REMNANT PAVEMENT LAYER WITH EXISTING SAND AND FILL SOIL. 14.COORDINATE WITH ENGINEER FOR PLACEMENT OF MIXED PULVERIZED REMNANT PAVEMENT. 15.CONSTRUCT TEMPORARY SEDIMENT CONTROL BASINS. 16.INSTALL PRIMARY ELECTRICAL SERVICE AND XMRF PAD. 17.INSTALL FORCE MAIN SEWER LINE 18.ROUGH GRADE FILL SLOPES, PARK DRIVEWAY AND PARKING LOT AREAS. INSTALL CURBING. 19.INSTALL SITE LIGHTING CONDUITS AND SITE LIGHT FOUNDATIONS. 20.CONSTRUCT DRAINAGE INFILTRATION SYSTEM 1. AFTER PARK DRIVEWAY HAS BEEN PAVED AND CONTRIBUTING WATERSHED AREA HAS BEEN STABILIZED. 21.PLACE PULVERIZED ON-SITE FILL/GRAVEL BASE FOR PARK DRIVEWAY TO PARKING AREA. 22.COMPLETE INSTALLATION OF ALL DRAINAGE PIPING IN THE ENTRANCE DRIVEWAY. 23.INSTALL BASE LAYERS FOR POROUS PAVEMENT. RESTRICT VEHICLE PASSAGE TO MAINTAIN CLEAN STONE RESERVOIR COURSE. 24.INSTALL BASE COURSE PAVEMENT AT ENTRANCE DRIVEWAY. 25.PROVIDE VEGETATIVE COVER ON ALL EXPOSED SLOPES ALONG THE ENTRANCE DRIVEWAY OR PERMANENTLY LOAM & SEED . 26.PROVIDE SEDIMENT PROTECTION AT ALL INLETS INTO INFILTRATION SYSTEMS. PERMIT FLOW INTO SYSTEMS AS COMPLETED. CONSTRUCTION SEQUENCING PLAN - STAGE 1 - PARK SITE UNLESS OTHERWISE NOTED OR CHANGED BY REPRODUCTION SHEET NO. SCALE DATE DESIGNED BY: 10056 CHECKED BY: BETA JOB NO.: ISSUE DATE: DRAWN BY: REVISIONSNO. TITLE PROJECT PREPARED BY West Yarmouth, MA RIVERWALK PARK, BOARDWALK LOOP & EVENT SPACE PHASE 1 AKP Bid Documents AWG AWG REGISTERED PROFESSIONAL 100 SCALE IN FEET: 1"=50' 50050 BID DOCUMENTS REGISTERED PROFESSIONAL 4/5/2024 G: \ P L A N N I N G L A N D S C A P E \ 1 0 0 0 0 S \ 1 0 0 5 6 - Y A R M O U T H , M A R I V E R W A L K P A R K & B O A R D W A L K \ D R A W I N G F I L E S \ P L A N S E T \ C O N S T R U C T I O N D O C U M E N T S - P H A S E 1 \ 1 0 0 5 6 _ P H A S I N G P L A N - P H 1 . D W G MA T C H L I N E MA T C H L I N E STAGE 2 CONSTRUCTION - PARK SITE 1.INSTALL PILINGS AND BENTS FOR KAYAK LAUNCH. OBSERVE TIME OF YEAR RESTRICTIONS. 2.INSTALL RIVER BOTTOM MOORINGS FOR KAYAK LAUNCH. OBSERVE TIME OF YEAR RESTRICTIONS. 3.INSTALL FRAMING, DECKING AND RAILINGS FOR KAYAK LAUNCH. 4.INSTALL GANGWAYS AND KAYAK LAUNCH FLOAT SYSTEM. 5.CLEAR ALL REMAINING AREAS. REMOVE RUBBISH AND DEBRIS. 6.STRIP ALL AREAS OF UPPER SOIL STRATA AS INDICATED. (ORDINARY FILL FOR RE-USE). 7.CRUSH/PULVERIZE & PROCESS REMNANT PAVEMENT LAYER WITH EXISTING SOIL STRATA. 8.COORDINATE PLACEMENT OF MATERIAL WITH ASPHALT WITH ENGINEER. LOCATE UNDER PATHWAYS. 9.REGRADE AND USE ON-SITE FILL TO SHAPE INFIELD AREA & PERIMETER PATHWAY. 10.ROUGH GRADE ALL INFIELD AND WALKWAY AREAS. 11.INSTALL INFILTRATION BASIN 1 COMPLETE, INCLUDING LOAM & SEED. 12.INSTALL ALL UTILITIES TO SERVICE LANDSCAPED AREAS AND EVENT SPACE. 13.INSTALL GRAVEL BASE FOR PERIMETER PATHWAY WEST OF THE ACCESS DRIVEWAY. 14.INSTALL GRAVEL BASE FOR ALL WALKWAYS. 15.INSTALL POROUS PAVEMENT AND SET ALL VERTICAL GRANITE CURBING. 16.PAVE PERIMETER PATHWAY AROUND THE INFIELD AREA. 17.INSTALL REINFORCED TURFGRASS SYSTEM. 18.COMPLETE ALL WALKWAYS, SIDEWALKS, AND CONCRETE PADS/SHANTY SLABS. 19.INSTALL LIGHT POLES, LUMINARIES AND ELECTRICAL ENCLOSURES. 20.FINE GRADE, INSTALL FOOTINGS, INSTALL PLAYGROUND EQUIPMENT, INSTALL SURFACING. 21.FINISH PAVE ENTRANCE DRIVEWAY AND INSTALL BITUMINOUS CURB. 23.LOAM & SEED ALL EXPOSED AREAS. COMPLETE AREAS AS THEY BECOME AVAILABLE. 24.INSTALL LANDSCAPE PLANTINGS ALONG THE ENTRANCE DRIVEWAY. 25.INSTALL REMAINING LANDSCAPE PLANTINGS. 26.INSTALL SIGNAGE AND SITE FURNITURE 27.CONTINUE INVASIVE PLANT MANAGEMENT OPERATIONS * NOTE: LIMITS OF THE WORK ASSOCIATED WITH GRANTS ARE SHOWN ON THIS PLAN AS APPROXIMATE. REFER TO THE SPECIFICATIONS FOR WORK TO BE COMPLETED AS PART OF THE PARKLAND ACQUISITION AND RENOVATIONS FOR COMMUNITIES (PARC) GRANT AND LAND & WATER CONSERVATION FUND GRANT, AS WELL AS THE REQUIRED SEQUENCING AND MILESTONES. 䍯湴牯汳⁴漠扥⁲敭潶敤 䍯湴牯汳⁴漠扥⁲敬潣慴敤 䍯湴牯汳⁴漠牥浡楮⁡湤⁢攠牥灡楲敤 PARKERS RIVER STAGING AREA FOR BOARDWALK UTILIZE TRACKING PADS TO REDUCE IMPACT OF CONSTRUCTION INFILTRATION BASIN NO. 1 - CONSTRUCTION STAGE 2 STAGING AREA FOR KAYAK LAUNCH FLOAT AND BOARDWALK INSTALL 12" HDPE 0+00 1+0 0 2+ 0 0 3+00 4 + 0 0 5 + 0 0 6+ 0 0 7+0 0 8+0 0 9+00 10+00 11+00 12 + 0 0 13+ 0 0 UNLESS OTHERWISE NOTED OR CHANGED BY REPRODUCTION SHEET NO. SCALE DATE DESIGNED BY: 10056 CHECKED BY: BETA JOB NO.: ISSUE DATE: DRAWN BY: REVISIONSNO. TITLE PROJECT PREPARED BY West Yarmouth, MA RIVERWALK PARK, BOARDWALK LOOP & EVENT SPACE PHASE 1 AKP Bid Documents AWG AWG REGISTERED PROFESSIONAL 100 SCALE IN FEET: 1"=50' 50050 BID DOCUMENTS REGISTERED PROFESSIONAL 4/5/2024 G: \ P L A N N I N G L A N D S C A P E \ 1 0 0 0 0 S \ 1 0 0 5 6 - Y A R M O U T H , M A R I V E R W A L K P A R K & B O A R D W A L K \ D R A W I N G F I L E S \ P L A N S E T \ C O N S T R U C T I O N D O C U M E N T S - P H A S E 1 \ 1 0 0 5 6 _ P H A S I N G P L A N - P H 1 . D W G C.2.2 PROP. LIMIT OF CLEARING (TYP.) LIMIT OF STAGE 1 CLEARING - PROVIDE ACCESS TO BOARDWALK AREA CONSTRUCTION SEQUENCING PLAN - STAGE 1 - BOARDWALK LIMIT OF STAGE 1 CLEARING - STAGING AREA FOR PEDESTRIAN BRIDGE. ENGINEER SHALL APPROVE LIMITS. LIMIT OF STAGE 1 CLEARING - STAGING AREA FOR BOARDWALK. ENGINEER SHALL APPROVE LIMITS. CONSTRUCTION SEQUENCING NOTES: STAGE 1 CONSTRUCTION - BOARDWALK & WOODLAND PATHS 1. COORDINATE EROSION CONTROL AND ACCESS WITH THE OPEN PARK SITE. 2. ESTABLISH LAY DOWN AND STAGING AREAS FOR MATERIALS AND EQUIPMENT. 3. STAKE LIMIT OF CLEARING, INCLUDING ANY TREES FOR REMOVAL FOR OWNER APPROVAL. 4. ROOT PRUNE, PRUNE AND LIMB TREES SHOWN TO REMAIN WITHIN LIMIT OF WORK. 5. SET VEGETATION PROTECTION MEASURES ALONG PERIMETER OF DEVELOPMENT AREA. 6. CLEAR WOODLAND PATHWAY AREAS TO APPROVED LIMITS. 7. INSTALL EROSION CONTROLS. MAINTAIN EROSION CONTROLS THROUGHOUT PROJECT. 8. GRUB PATHWAYS AND INSTALL GRAVEL PATH BASE. 9. ROUGH GRADE WOODLAND PATHWAYS AND EDGES. 10.PLACE WOOD CHIP MULCH SURFACE TO PROTECT FOREST FLOOR & PATH EDGES. 11.PROVIDE VEGETATIVE COVER ON ANY EXPOSED SOIL. 12.UTILIZE LIGHTWEIGHT MARSH MATS TO PROTECT THE SALT MARSH. REMOVE DAILY. 13.STAKE OUT BOARDWALK ALIGNMENT FOR APPROVAL BY THE OWNER. 14.HAND CUT AND REMOVE CONFLICTING PLANT MATERIAL IDENTIFIED BY OWNER. 15.OBSERVE TIME OF YEAR RESTRICTIONS. 16.UTILIZE RUBBER TRACKED EQUIPMENT AND MARSH MATTING. REMOVE DAILY. 17.INSTALL HELICAL PILES AND PILE BENT FRAMING. 18.INSTALL WOODEN BEAMS FOR PEDESTRIAN BRIDGE. 19.NO OVERNIGHT STORAGE OF EQUIPMENT ON THE SALT MARSH. 20.NO FUELING OF EQUIPMENT ON THE SALT MARSH. 21.NO STORAGE OF MATERIAL ON THE SURFACE OF THE SALT MARSH. EXIST. SALT MARSH EXIST. WOODED AREA EXIST. WOODED AREA EXIST. WOODED AREA EXIST. SALT MARSH MA T C H L I N E MA T C H L I N E STAGE 2 CONSTRUCTION - BOARDWALK & WOODLAND PATHS 1.INSTALL ALL BOARDWALK FRAMING ON BENTS. 2.INSTALL BOARDWALK RAILING POSTS AND DECKING. 3.INSTALL PEDESTRIAN BRIDGE WOOD DECKING. 4.INSTALL BOARDWALK RAILINGS, BENCHES, INTERPRETIVE PANELS. 5.UTILIZE LIGHTWEIGHT MARSH MATS TO PROTECT THE SALT MARSH. 6.NO OVERNIGHT STORAGE OF EQUIPMENT ON THE SALT MARSH 7.NO FUELING OF EQUIPMENT ON THE SALT MARSH 8.NO STORAGE OF MATERIAL ON THE SURFACE OF THE SALT MARSH. 9.INSTALL ALL LANDSCAPE PLANTINGS. 10.LOAM AND SEE ALL DISTURBED AREAS. 11.INSTALL STABILIZED AGGREGATE PATHWAYS. 12.INSTALL SIGNAGE AND BENCHES. 13.COMPLETE REMAINING LANDSCAPE PLANTINGS. 14.CONTINUE INVASIVE PLANT MANAGEMENT OPERATIONS. PROP. BOARDWALK ALIGNMENT - CONSTRUCTION SHALL UTILIZE PROTECTIVE MATTING TO PROTECT EXISTING MARSH PROP. LIMIT OF WORK (TYP.) 䕲潳楯渠捯湴牯汳 䍯湴牯汳⁴漠扥⁲敭潶敤 䍯湴牯汳⁴漠扥⁲敬潣慴敤 䍯湴牯汳⁴漠牥浡楮⁡湤⁢攠牥灡楲敤