May 6, 2025
Mr. Tim Sears
Deputy Building Commissioner
Town of Yarmouth
1146 Route 28
South Yarmouth, MA 02664
RE: Controlled Construction Report No. 1
New Industrial Bay Building
212 Mid Tech Drive, West Yarmouth, MA
Dear Mr. Sears,
Construction activities are ongoing at the subject project. Over the months from October
2024 through April 2025.
1. Completion of Steel Fram
2. Installation of roof insulation system within the suspended air barrier membrane
3. Installation of wooden roof sheathing, ice & water shield membrane, and asphalt roof
4. Installation of steel wall panels at both ends and rear sidewalls
5. Installation of all sidewall batt insulation and interior air barrier membrane
6. Installation of windows
7. Install of all below slab rough mechanical and electrical piping and conduits
8. Placement of concrete floor slab
9. Placement of front apron slab, and concrete pads at rear egress doors
10. Installation of all overhead doors on front (west) side.
11. Installation of gas manifold, and individual services to the rear of each unit
12. Installation of electric service panels on the north façade including meter sockets (
13. Installation of the water and fire service (inspected by the Water Dept.)
14. Install of the back flow preventer and check valves in the sprinkler room
15. Rough installation of all building systems including fire protection, plumbing,
mechanical and bath vents, as well as the electric
203 WILLOW STREET SUITE A PH 508-362-8382
YARMOUTHPORT MA 02675 FAX 508-362-2828
WWW.CATALYSTARCHITECTS.COM
Northeast Geotechnical Solutions continued to monitor excavation and backfill
operations, with reports sent directly to the town.
Our consulting Engineer has visited one final time and has transmitted to your attention a
letter confirming his satisfaction with the work (a copy is attached here for convenience).
Our mechanical engineers recently visited the site and provided the attached report. At
the time the rough work was about 50% completed. CES visited the site again this
morning to review the rough work completed by all the mechanical trades, prior to the
start of insulation in the interior walls and the arrival of the gypsum wall board
subcontractor later this week. I will transmit the engineers next report upon receipt.
Catalyst continues to attends on-site construction meetings with the project team every
other Tuesday (or twice monthly) to monitor work in progress and adherence to the
construction documents.
Pic 2.1
Finished interior roof membrane
with batt insulation between
purlins.
Note front wall is wood sheathing
on horizontal purlins
Pic 2.2
End wall and rear wall (left side)
are corrugated steel panels.
Sliding aluminum windows and
all associated flashings are
installed at this point.
203 WILLOW STREET SUITE A PH 508-362-8382
YARMOUTHPORT MA 02675 FAX 508-362-2828
WWW.CATALYSTARCHITECTS.COM
Pic -2.3
Exterior of North Wall with
Electric conduits roughed in and
thru wall to below grade.
Pic -2.4
All MEP system roughs installed
below slab per plans
Pic -2.5
Batt Insulation installed between
horizontal purlins at end wall.
Rear wall similar is covered with
interior air barrier.
From wall is similar with purlins at
24” OC and similar batts.
203 WILLOW STREET SUITE A PH 508-362-8382
YARMOUTHPORT MA 02675 FAX 508-362-2828
WWW.CATALYSTARCHITECTS.COM
Pic -2.6
Overhead doors are being
installed with high-lift tack.
Image also shows fire sprinkler
main being hung
Pic -2.7
Workers installing fire protection
laterals.
Others framing interior partions
and sprinkler room walls
Pic -2.8
Typical interior wall framing
Note we have added RO
between units
These will be infilled with solid
wall unless a tenant comes
forward that wishes to occupy
two or more adjacent bays.
203 WILLOW STREET SUITE A PH 508-362-8382
YARMOUTHPORT MA 02675 FAX 508-362-2828
WWW.CATALYSTARCHITECTS.COM
Pic -2.9
Modine style heaters being hung
above toilet room framing
Pic 2.10
Installation of septic tank, tights
tanks, and associated plumbing.
Baxter Nye Eng has been on site
to observe the installation of the
elements alongside the Board of
Health.
Pic 2.10
Lohr Construction has started
installation of finish clapboard
siding at front (west) side of the
building.
203 WILLOW STREET SUITE A PH 508-362-8382
YARMOUTHPORT MA 02675 FAX 508-362-2828
WWW.CATALYSTARCHITECTS.COM
All work completed to date has been done in a good and workmanlike manner and in
general accordance with the construction documents. If you have any questions, please
feel free to contact me at any time.
Sincerely,
Kurt E. Raber
Project Architect
CC: Waylon Lohr, Lohr Construction (General Contractor)
Jeff Bilezikian (Owner)
Rick Fenuccio (OPM, ClearPath Advisors)
Enc. SER letter dated 4/14/25
CES Site Observation Report dated 4/4/25
C o n s u l t i n g E n g i n e e r i n g S e r v i c e s , L L C
128 Carnegie Row, Suite 204, Norwood, MA. 02062 T 617.261.7161 ceseng.com
Field Observation Report
Report Date: April 4, 2025
Written To: Kurt Raber
Project Name: 212 Midtech Drive
CES Project Number: 2021607.00
Written By: Edward Wellington, PE
The following report includes items that require completion and or correction for the above mentioned
project. These items were noted during our field observation on 4/2/2025. Items included in this report
are limited to those that were accessible and visible during the time of our field observation. Completion
and or correction of those items included in this report does not relieve the contractor of his responsibility
to provide complete and operational systems in accordance with the contract documents.
DIVISION 21 – FIRE PROTECTION
# Comment Photo
1 General: The installation of fire
protection systems is nearing
completion. Upon completion, the
contractor shall submit closeout
documentation including NFPA 13
form indicating sign-off by the local
Fire Marshall.
2
2 Fire service is installed.
3 Test and drain are roughed in.
Termination fittings are not yet
provided.
4 Sprinkler piping is generally installed
throughout.
3
DIVISION 22 – PLUMBING
# Comment Photo
1 Gas meters are installed.
2 Gas piping observed under pressure
test.
3 Trench drain observed as installed in
unit #11.
4
4 Domestic cold water, hot water,
sanitary and vent piping is roughed in.
Installation of fixtures has not begun.
Trap primers and water heaters have
not yet been installed.
5 Domestic water lines observed stubbed
up in the water service room.
6 Floor drains, floor clean outs have been
installed. Underground piping is
installed. Venting from exterior oil
separator is stubbed into the building.
5
DIVISION 23 – MECHANICAL
# Comment Photo
1 General: Installation of mechanical
equipment is in progress.
As a reminder, upon completion of
construction the contractor shall
provide closeout documentation
including TAB reports, as-built
drawings, O&M manuals, warranty
information, spare parts, equipment
start-up reports, and other closeout
submittals required by the specifications.
2 Typical GUH-1 (gas unit heaters)
observed to be installed. Gas
connection, controls and flue have not
been installed. Please mount units at
approximately 15’-0” above floor as per
M1.0.
3 ECH-1 (electric heater) and EF-1
(ceiling exhaust fan) have not yet been
installed in the bathroom ceilings.
EUH-1 (electric unit heater) has not yet
been installed in the fire service room.
6
DIVISION 26 & 28 – ELECTRICAL & FIRE ALARM
# Comment Photo
1 General: Contractor shall submit
closeout documentation including O&M
manuals, test reports and NFPA 72
form for the fire alarm system.
2 Electrical service including meter bank
is installed.
3 Exit signs observed as installed.
Installation of receptacles and general
electrical distribution is in progress.
4 Conduit observed stubbed up in the
fire service room.
7
5 Conduit observed stubbed up in typical
unit bays. Electrical panels have not yet
been installed in typical bays.
Installation of light fixtures is nearly
complete in the bays, and wiring is in
progress. Lighting, including EBU’s,
has not yet been installed in bathrooms
or water service room. Fire alarm
devices are not yet installed.