HomeMy WebLinkAboutRiverwalk Park Site Inspection_2025-10-27_Optimized
MEMORANDUM
BETA GROUP, INC.
www.BETA-Inc.com
BACKGROUND
On October 27, 2025, BETA staff visited the Yarmouth Riverwalk Park Site located at 669 Route 28 in
Yarmouth, MA to perform environmental monitoring during construction and to monitor the
establishment of restoration plantings within the salt marsh. The purpose of this inspection was to
document the conditions of the salt marsh, erosion controls, and park during construction.
CURRENT CONSTRUCTION
Construction of the site is underway, and the following approved site elements have been constructed or
partially constructed prior to this inspection:
Invasive species management has been conducted throughout the site;
Construction of the boardwalk has been substantially completed (Photo 1);
Construction of the playground has been substantially completed (Photo 2);
Stormwater infrastructure has been installed;
Stabilized aggregate walking paths have been installed;
Plantings have been installed;
Some site elements including light fixtures, bikes racks, and benches have been installed;
Pavement has been installed where proposed and the topcoat of pavement has been installed in
various locations (Photo 3);
Portions of the site have become partially stabilized (Photo 4);
Utilities have been partially installed; and,
The restroom facility has been partially constructed (Photo 5);
During the site visit work to construct the restroom facility was occurring (Photo 5) and mulch was being
installed in planted beds in various locations throughout the site (Photo 6).
SALT MARSH RECOVERY
During the previous site visit on September 19, 2025, BETA staff oversaw Chase Landscaping
(Subcontractor to Robert B Our) installation of plug plantings consisting of 850 saltmeadow cordgrass
(Spartina patens) plugs and 1,200 smooth cordgrass (Spartina alterniflora) plugs into areas of exposed soil
within the salt marsh.
Date: November 10, 2025 Job No.: 22.10056.00
To: Amanda Lima, PE Town Engineer
Kathy Williams, PE, Town Planner
Brittany DiRienzo, Conservation Administrator
From: Arek Galle, RLA, AICP, Senior Associate, BETA Group
Prepared: Anna Haznar, Staff Scientist
Laura Krause, Senior Project Manager
Subject: Site Monitoring Visit 10/27/2025
Yarmouth Riverwalk Park and Boardwalk
Yarmouth, MA
November 10, 2025
Page 2 of 3
During this Site visit plugs were observed to be in good condition and were exhibiting fall color (Photos 7
and 8). Plugs installed throughout the salt marsh will continue to be monitored periodically in the months
ahead. It is expected that the success of the planting will be evaluated during the Spring 2026 growing
season. Additional restoration of these areas is not anticipated at this time based on the present
conditions observed.
SALT MARSH/BOARDWALK APPROACH AREAS
Areas of salt marsh outside of the locations where grass plugs were being installed have become fully
revegetated. Vegetation was observed to be in good health, now showing fall colors (Photo 9).
In the boardwalk approach areas, grass plugs and seed were previously installed within the areas of
exposed soil on both the eastern and western boardwalk approaches. These areas are upgradient of the
salt marsh. Plugs in these areas were observed as being in good condition, however seed should be applied
to the area on both sides of each of the boardwalk approaches to more fully stabilize the exposed soil
(Photo 10). Frost seeding (in dormancy) of these areas may provide a jump-start on grass establishment
in the spring. The sections of erosion controls upgradient of the salt marsh was observed to be in good
condition (Photo 11).
EROSION CONTROLS
The majority of the erosion controls have been removed due to successful establishment of vegetation
throughout the site. Erosion controls consisting of silt fence and/or compost filter tubes are still present
along areas that are not fully vegetated or directly adjacent to Resource Areas. Both compost filter tubes
and silt fence were observed as degraded and damaged in areas throughout the Site (Photo 12). Erosion
controls adjacent to the kayak launch were observed to be in good condition (Photo 13). Erosion controls
near the upweller adjacent to the Parker River were observed to be damaged (Photo 14) with exposed,
loose compost. The area upgradient of the damaged erosion control is partially stabilized. The erosion
controls showing damage - closest to the upweller - should be replaced to limit compost from the filter
tube entering the river. This location should be monitored to ensure no sediment enters Resource Areas.
RIVERWALK PARK UPLAND AREAS
Currently, the Riverwalk Park is under construction. Multiple small stockpiles of soil were present during
the site visit that are associated with active construction of the restroom facility (Photo 5). Stabilization
of stockpiles should commence if active work is not occurring, or within 14 days of the cessation of work
in the area. Exposed soil that requires stabilization is present throughout the site in various locations
(Photos 5, 10, 11, and 15), including adjacent to the trailers, upgradient of the woodland path, on either
side of the path, and various other locations. Soil should be stabilized if work has concluded in these areas.
Erosion controls downgradient of exposed soil were observed in various states and should be replaced or
maintained.
During this inspection, minimal invasive plant species pressure was observed within the limits of work;
however, the site should continue to be monitored for success of the invasive species removal plan. Some
invasive species were exhibiting fall color and die-back. Species including bush honeysuckle (Lonicera
spp.), autumn olive (Elaeagnus umbellate), black swallowwort (Cynanchum louiseae), tree of heaven
(Ailanthus altissima), and bittersweet (Celastrus orbiculatus) were observed in small populations within
the landscaped beds along the entrance road and directly adjacent to the limits of work and erosion
controls (Photos 16 and 17). A small population of bittersweet was also observed adjacent to the erosion
controls in back of the trailers. Japanese knotweed (Fallopia japonica) is present within the landscaped
November 10, 2025
Page 3 of 3
beds along the entrance where a large population was removed (Photo 18). Additionally, a population of
bittersweet was observed within the boulders adjacent to the walking path (Photo 19). The population of
cypress spurge (Euphorbia cyparissias) – a species considered likely invasive by the Massachusetts Invasive
Plant Advisory Group (MIPAG) - is also present within the boulders adjacent to the walking path and one
additional plant was observed in a planted bed adjacent to the entrance road (Photo 20).
SUMMARY
Currently, work on the Yarmouth Riverwalk Park and Boardwalk Project is underway. Generally,
installation of site features is complete and stabilization of the remainder of exposed soil is required.
Observations made during the October 27, 2025, site inspection include the following:
Restoration plantings installed into the salt marsh appear to be in good condition, further
monitoring of these plantings should be conducted in the Spring of 2026,
Erosion/sediment controls throughout the site are in varying condition and are generally
degraded. Erosion controls upgradient of the Parkers River adjacent to the upweller require
replacement,
Areas of exposed soil that require stabilization are present throughout the site and should be
stabilized if work has been completed in these areas,
All soil stockpiles at the site are associated with active work and should be temporarily stabilized
if not in use for 14 days or more,
Invasive plant species presence /pressure was observed within the landscaped beds adjacent to
the entrance driveway, directly adjacent to erosion controls, and within a naturalized area near
the kayak launch. Treatment of invasive plant species present should be conducted as part of the
Invasive Plant Management Strategy.
Attachments:
- Attachment A Photographic Documentation
- Attachment B Site Aerial Image w/ Photo Key
PHOTOGRAPHIC DOCUMENTATION
Yarmouth Riverwalk
Yarmouth, Massachusetts
Photographs Documented October 27, 2025
Photo 2
View of the playground—facing south.
View of the current conditions of the boardwalk—facing south.
Photo 1
Site Monitoring Report Attachment A
PHOTOGRAPHIC DOCUMENTATION
Yarmouth Riverwalk
Yarmouth, Massachusetts
Photographs Documented October 27, 2025
Photo 4
Typical view of the stabilized field internal of the site—facing south.
View of the location where the top coat of pavement has been installed—facing south.
Photo 3
Site Monitoring Report Attachment A
PHOTOGRAPHIC DOCUMENTATION
Yarmouth Riverwalk
Yarmouth, Massachusetts
Photographs Documented October 27, 2025
Photo 6
View of mulch being installed in the southern portion of the park—facing east.
View of active work on the restroom facility– facing south.
Photo 5
Site Monitoring Report Attachment A
PHOTOGRAPHIC DOCUMENTATION
Yarmouth Riverwalk
Yarmouth, Massachusetts
Photographs Documented October 27, 2025
Photo 8
View of plugs installed within Area C-1—facing east.
View of the plugs installed within Area W-1—facing north.
Photo 7
Site Monitoring Report Attachment A
PHOTOGRAPHIC DOCUMENTATION
Yarmouth Riverwalk
Yarmouth, Massachusetts
Photographs Documented October 27, 2025
Photo 10
View of the plugs and exposed soils upgradient of the western side of the boardwalk—facing south.
View of a fully vegetated area adjacent to the boardwalk —facing north.
Photo 9
Site Monitoring Report Attachment A
PHOTOGRAPHIC DOCUMENTATION
Yarmouth Riverwalk
Yarmouth, Massachusetts
Photographs Documented October 27, 2025
Photo 12
View of the silt fence along the path near the kayak launch requiring repair—facing northeast.
View of the plugs, erosion control, and exposed soil upgradient of the eastern side of the boardwalk —
facing north.
Photo 11
Site Monitoring Report Attachment A
PHOTOGRAPHIC DOCUMENTATION
Yarmouth Riverwalk
Yarmouth, Massachusetts
Photographs Documented October 27, 2025
View of erosion controls adjacent to the Parker River under the kayak launch in good condition – facing
south.
Photo 13
View of the erosion controls adjacent to the upweller that require replacement —facing east.
Photo 14
Site Monitoring Report Attachment A
PHOTOGRAPHIC DOCUMENTATION
Yarmouth Riverwalk
Yarmouth, Massachusetts
Photographs Documented September 19, 2025
View of a location of exposed soil adjacent to the trailer —facing west.
Photo 15
View of tree of heaven and bittersweet within the planted beds adjacent to the entrance road —facing west.
Photo 16
Site Monitoring Report Attachment A
PHOTOGRAPHIC DOCUMENTATION
Yarmouth Riverwalk
Yarmouth, Massachusetts
Photographs Documented October 27, 2025
View of autumn olive, bittersweet, and black swallowwort adjacent to the limits of work —facing west.
Photo 17
View of Japanese knotweed within the landscaped bed adjacent to the entrance road—facing west.
Photo 18
Site Monitoring Report Attachment A
PHOTOGRAPHIC DOCUMENTATION
Yarmouth Riverwalk
Yarmouth, Massachusetts
Photographs Documented October 27 , 2025
View of the population of bittersweet exhibiting fall color within the boulders adjacent to the walking
path—facing east.
Photo 19
View of the cypress spurge observed within a planted bed adjacent to the entrance road—facing east.
Photo 20
Site Monitoring Report Attachment A
Yarmouth Riverwalk Park — October 27, 2025
偨潴漠ㄲ
偨潴漠ㄳ
偨潴漠ㄴ
偨潴漠ㄵ
偨潴漠ㄶ
偨潴漠ㄷ
偨潴漠ㄸ
偨潴漠ㄹ
偨潴漠㈰
卩瑥⁍潮楴潲楮朠剥灯牴⁁瑴慣桭敮琠䈠
Yarmouth Riverwalk Park — October 27, 2025
偨潴漠
偨潴漠ㄱ
卩瑥⁍潮楴潲楮朠剥灯牴⁁瑴慣桭敮琠䈠