HomeMy WebLinkAbout5207 1308 Route 28 Site Plan Review Comments 11.18.25SITE PLAN REVIEW COMMENT SHEET
Date: November 18, 2025
Applicant: Elie & Rabih Bassil United Gas)
Location: 1308 Route 28
Tim Sears
Barry. Lewis
Kathy Williams
Matt Bearse
Persons Present:
Project Summary
Construct garage addition, and full second floor.
Comments
Formal Review
Map: 60 Lot: 160
Zone: B11B2
3assil
Buildin : Structure and use located in the B1 & B2 zoning district.
Building addition will meet all required setbacks, no increase in the non -conformity of the structure.
Use requires a Special Permit per 104.3.2 para. 4.
Community Development & Planning: The applicant has done a great job making the building look good and it will be <
nice addition to this end of Route 28.
Design Review: Refer to attached October 21, 2025 Design Review Comment Sheet.
Conservation: Work is outside of conservation jurisdiction
An ineerin :
Proposed site plan does not indicate stormwater is being treated, stored or infiltrated on site. No proposed
drainage is shown. Suggest roof surfaces from the addition be handled onsite into leaching structures.
Fire: 527 CMR 1 is the fire code, for access and the repair garage is governed by fire code as well.
alth: The Health Department will need a septic permit for us to sign off on the building permit. The project and business
operation must comply with TOY, BOH Regulations, handling and storage of toxic or hazardous materials, including, but
not limited to, 150% volume secondary containment of all toxic or hazardous materials. On the site plan dated 10-1-25
please revise all references to the term "tight tank" to nonhazardous industrial wastewater holding tank and container
construction, operation and record keeping requirements.
Please consult with the town plumbing inspector to ensure the floor drain, line and holding tank system complies with
plumbing code
Water: Not present.