HomeMy WebLinkAboutRevised plan request 10.29.2025
75 State Street, Suite 701
Boston, Massachusetts 02109
tel: 617 452-6000
October 29, 2025
Yarmouth Conservation Commission
1146 Route 28
South Yarmouth, MA 02664
Subject: Plan Revision Request
Order of Conditions DEP Wetlands File No: 083-2442
Dear Commission Members:
On behalf of the Town of Yarmouth, Department of Public Works, CDM Smith Inc. (CDM Smith)
submits this Plan Revision request to existing Order of Conditions (OOC) (DEP File No. 083-2442)
issued on September 24, 2024, and valid until September 24, 2027. The Plan Revision consists of
relocation of proposed Pumping Station No. 2 (PS2) in Contract No. 6.
A nonbinding measure was approved at special Town meeting in December 2024 to move PS2 from
its original proposed location at 316 Route 28. The Town is now proposing to construct PS2 at 280
Route 28 (Map 38 Lot 4), on land owned by Bellew Realty. The parcel is previously developed and
the portion proposed for the relocated PS2 consists of a gravel parking area (see attached photos)
where the leaching field for the building on the parcel was constructed; that is, the area has been
previously disturbed.
The Town is in the process of securing a utility easement on this privately owned property for the
purpose of building and maintaining the pumping station. Since the new sewer system is a gravity
system, options for relocating PS2 are very limited since the pumping station has to be located
within the lowest portion of the area to be sewered.
Proposed Plan Revision
The relocated PS2 will be the same type of pumping station as the previously proposed station - it
will be submersible type with a wet well (i.e., deep below ground structure) that will house
submersible pumps. Valving and a meter will be housed in separate below grade precast concrete
structures adjacent to the wet well. Each area will be accessed by individual H-20 rated hatches or
traditional manhole covers. An 11.5’ by 17’ precast building (control room) with concrete pad at
the doorway will house all of the electrical and pump control equipment and alarms. A standby
natural gas generator will be placed on a 5’ by 12’ concrete pad. Odor control is not included in this
design but there is space allocated on site (5’ by 8’ concrete pad) for a future odor control system, if
needed. All these components of the pumping station are the same as the originally proposed
station; they are just located on a different site in a slightly different orientation.
Yarmouth Conservation Commission
October 29, 2025
Page 2
Wetland Resource Area Impacts
The relocated PS2 results in a decrease in impacts to wetland resource areas compared to the
original location at 316 Route 28.
The eastern half of the new site for PS2 will encroach into Land Subject to Coastal Storm Flowage
(LSCSF) which extends up to el. 11 ft (see Figure 2: FEMA Flood Map and Plan Sheets. Fill material
will be brought in to build up the site to approximately elevation 13 feet in order to allow the first-
floor elevation (FFE) of the control building and critical infrastructure to be placed at elevation
14. Engineering design standards require that critical infrastructure (i.e., electrical and control
equipment, including natural gas standby generator) be elevated 3 feet above the effective 100-year
floodplain (i.e., 11 feet).
The PS2 site will be final graded with crushed stone and a portion of the existing the gravel parking
area will be paved to provide access to the station for maintenance vehicles. The eastern slope will
be restored to a 3:1 slope and seeded with a native wildflower seed mixture. Tree and shrub
plantings are also proposed to screen the site from Route 28 as shown on Sheet CD-6
It is estimated that approximately 765 square feet (sf) of LSCSF would be permanently altered and
an additional 765 square feet temporarily altered by bringing in approximately 120 cubic yards
(CY) of fill material at a 3:1 slope as shown on attached Plan Sheet CD-6. This is a reduction from
the permanent alteration of approximately 3,490 sf of LSCSF approved under the existing OOC for
the original PS2 site. The relocated PS2 avoids all impacts to the 35-ft and 50-ft setbacks and
reduces impacts to the 100-ft Buffer Zone (from 4,885 sf approved under the existing OOC to 2,630
sf at the new site).
Table 1 provides a summary of wetland resource area and buffer zones impacts for the relocated vs.
previously approved PS2 location.
Table 1: Summary of Wetland Resource Areas and Buffer Zone Impact for PS 2
LSCSF (sf) 100-ft Buffer
Zone (sf)
0-35 ft Setback
(sf) (temp.)
35-50 ft
Setback (sf)
(temp.)
PS2 – Permitted
Location at 316
Route 28
3,490
(permanent)
4,885 656 755
Yarmouth Conservation Commission
October 29, 2025
Page 3
PS 2 – Proposed
Relocation to
280 Route 28
765
(permanent)
765 (temporary)
335 (new
impervious)
2,295
(temporary)
0 0
Stormwater Management Design
Stormwater for the relocated PS2 site will be collected in deep sump hooded catch basins and
treated in a subsurface infiltration system, with all stormwater through the 50-yr storm retained on
site. The stormwater design will meet the required Massachusetts Stormwater Standards for new
development. Treated stormwater over the 100-year storm will be discharged to the existing
stormwater system in Route 28.
Please refer to the enclosed Pumping Station 2 Stormwater Report for a detailed discussion of
existing stormwater conditions, drainage analysis, proposed stormwater management, and
compliance with the Massachusetts Stormwater Standards.
Mitigation Measures
The following summary presents the mitigation measures that will be implemented by the
Contractor to avoid and minimize wetland impacts during construction. There are no proposed
changes to the mitigation measures from the original NOI. Please refer to the original project plans
for typical details of measures to protect wetlands and waterways including coastal resources
during and after construction.
Construction Period
▪ Staked compost logs will be installed at the limit of work prior to commencement of
construction to prevent the transport of sediment and debris to downgradient drainage ditch
and to demarcate the limit of work. A stockpile of compost logs will be stored in an easily
accessible location for routine maintenance and emergency repairs. The compost log barrier
will be inspected weekly and after all storm events and repaired as needed. The barrier will
be left in place until the area is permanently stabilized.
▪ Construction access will be from Route 28. The last crew to leave the site each day would be
responsible for regularly sweeping the roadways, if and when sediment and/or rock have
been tracked onto the street.
▪ Dewatering may be necessary during construction of the proposed PS2. Water will be
pumped into a filter bag or dewatering basin consisting of a filter bag with straw bale or silt
Yarmouth Conservation Commission
October 29, 2025
Page 4
fence perimeter controls which will be located in approved areas outside wetland resource
areas. The pump intake hose will not be allowed to set on the bottom of the excavation
throughout dewatering. The basin and all accumulated sediment will be removed following
dewatering operations, and the area will be seeded and mulched with straw. The bag will be
surrounded with additional sediment filtration such as fiber rolls, straw bales, or other
appropriate containment.
Post Construction Measures
▪ If seeding occurs outside of the growing season, temporary stabilization measures (i.e.,
mulching or erosion control blankets) will be used to prevent erosion until the area can be
seeded during the following growing season.
▪ All disturbed soils will be restored by installing native plantings and seeding with native seed
mixture; and
▪ The compost log barrier will not be removed until a vegetative cover dense enough to
prevent erosion is established.
Summary
The Town of Yarmouth is requesting that the Plan Revision as described above and on shown on
enclosed the Plan Sheets be approved. We look forward to presenting the details of the Plan
Revision at your next meeting scheduled for November 6, 2025.
Feel free to call me at (617) 452-6597 or Michael Guidice, Project Manager, at (401) 457-0310 with
any questions. We look forward to continuing working with the Yarmouth Conservation
Commission on this very important project.
Sincerely,
Magdalena Lofstedt, PWS
Environmental Scientist
CDM Smith Inc.
cc: Jeffrey Colby, P.E., Department of Public Works Director
Michael Guidice, P.E., CDM Smith Project Manager
Enclosures:
Yarmouth Conservation Commission
October 29, 2025
Page 5
Figure 1: Project Location Map
Figure 2: FEMA Floodplain Map
Photographs
Plan Sheets CD-4: Existing Conditions, CD-5: Site Preparation, CD-6: Site Improvements, and CD-11:
Misc. Details
Pumping Station 2 Stormwater Report (bound separately)
Figure 1: Project Location Map, PS 2
Proposed PS 2
Relocation
Previously
Reviewed PS 2
Location
National Flood Hazard Layer FIRMette
0 500 1,000 1,500 2,000250
Feet
Ü
SEE FIS REPORT FOR DETAILED LEGEND AND INDEX MAP FOR FIRM PANEL LAYOUT
SPECIAL FLOOD
HAZARD AREAS
Without Base Flood Elevation (BFE)
Zone A, V, A99
With BFE or Depth Zone AE, AO, AH, VE, AR
Regulatory Floodway
0.2% Annual Chance Flood Hazard, Areas
of 1% annual chance flood with average
depth less than one foot or with drainage
areas of less than one square mile Zone X
Future Conditions 1% Annual
Chance Flood Hazard Zone X
Area with Reduced Flood Risk due to
Levee. See Notes.Zone X
Area with Flood Risk due to Levee Zone D
NO SCREEN Area of Minimal Flood Hazard Zone X
Area of Undetermined Flood Hazard Zone D
Channel, Culvert, or Storm Sewer
Levee, Dike, or Floodwall
Cross Sections with 1% Annual Chance
17.5 Water Surface Elevation
Coastal Transect
Coastal Transect Baseline
Profile Baseline
Hydrographic Feature
Base Flood Elevation Line (BFE)
Effective LOMRs
Limit of Study
Jurisdiction Boundary
Digital Data Available
No Digital Data Available
Unmapped
This map complies with FEMA's standards for the use of
digital flood maps if it is not void as described below.
The basemap shown complies with FEMA's basemap
accuracy standards
The flood hazard information is derived directly from the
authoritative NFHL web services provided by FEMA. This map
was exported on 10/17/2025 at 9:27 PM and does not
reflect changes or amendments subsequent to this date and
time. The NFHL and effective information may change or
become superseded by new data over time.
This map image is void if the one or more of the following map
elements do not appear: basemap imagery, flood zone labels,
legend, scale bar, map creation date, community identifiers,
FIRM panel number, and FIRM effective date. Map images for
unmapped and unmodernized areas cannot be used for
regulatory purposes.
Legend
OTHER AREAS OF
FLOOD HAZARD
OTHER AREAS
GENERAL
STRUCTURES
OTHER
FEATURES
MAP PANELS
8
B 20.2
The pin displayed on the map is an approximate
point selected by the user and does not represent
an authoritative property location.
1:6,000
70°15'25"W 41°39'26"N
70°14'48"W 41°38'59"N
Basemap Imagery Source: USGS National Map 2023
Photo 1: Proposed PS 2 Site Location
Photo 2: Proposed PS 2 Site Location (close-up)