Loading...
HomeMy WebLinkAboutAtt 5B_Alternatives Analysis - Weir Road Bridge Weir Road Culvert Yarmouth, MA Alternatives Analysis Report Friends of Bass River June 2024 Revised October 202 4 ALTERNATIVES ANALYSIS REPORT Tighe&Bond Table of Contents Table of Contents ....................................................................................................... 1 Introduction .............................................................................................................. 2 Existing Conditions and Constraints .............................................................................. 3 Survey & Site Review ............................................................................................... 3 Roadway Conditions ................................................................................................. 3 Hamblins Brook ....................................................................................................... 5 Hydrologic and Hydraulic (H&H) Analysis .................................................................... 5 Geotechnical Analysis ............................................................................................... 7 Permitting .............................................................................................................. 7 Traffic Management ............................................................................................... 10 Alternatives Analysis and Recommendations ................................................................ 11 Alternative 1: 24-foot Span Precast Concrete Arch..................................................... 12 Alternative 2: 24-foot Span Precast Concrete Arch with Raised Road ........................... 13 Alternative 3: 24-foot Span Precast Concrete Rigid Frame .......................................... 14 Alternative 4: 24-foot Span Prestressed Concrete Beams ........................................... 15 Summary and Opinion of Probable Construction Cost ................................................. 16 Recommendations ................................................................................................. 16 Appendix A: Conceptual Drawings (2024) Appendix B: Field Report with Photograph Documentation (2020) Appendix C: Hydrologic and Hydraulic Report (2024) Appendix D: Geotechnical Report (2024) Appendix E: Opinions of Probable Construction Cost (2024) ALTERNATIVES ANALYSIS REPORT Tighe&Bond -2- Introduction This report describes an evaluation of alternatives for replacement of the Weir Road Culvert over Hamblins Brook in Yarmouth, Massachusetts as part of the Bass River Restoration Project. Friends of Bass River (FOBR) obtained grant funding from the Division of Ecological Restoration, and in turn requested that Tighe & Bond perform this conceptual study , thus refining a previous version prepared in July 2021 which was funded through the Southeast New England Program (SNEP) Watersheds Grant . The Yarmouth Community Preservation Committee awarded grant funding to FOBR for preliminary design. A NOAA Coastal Zone Habitat and Restoration Grant was announced, which will fund final design and construction. The existing culvert carries Weir Road over Hamblins Brook flowing southwest to northeast. The culvert length overall is approximately 36’-3” perpendicular to the roadway and consists of stone slabs and piled stone walls. The approximate culvert opening varies between 1’-6” wide with a rise of 2’-0” at the inlet and 3-feet wide with a rise of 2’-2” at the outlet. The structure does not have a designated MassDOT culvert ID number. The culvert is believed to have been constructed in the late 1800’s or early 1900’s. Drawings for the existing structure are not available. Proposed replacement of the Weir Road culvert is intended to be part of a larger project to restore the Bass River, which includes upsizing the river crossing at North Dennis Road, improving nutrient flushing of Mill Pond, and restoring wetlands along Hamblins Brook between Miss Thatchers Pond and Mill Pond. The wetlands in this area consist of abandoned cranberry bogs and a network of small streams. Restoration is intended to consolidate flows to provide a continuous river. The purpose of the river restoration project is to provide environmental improvements for the wetlands and waterway. R eplacing the existing structure is required to maintain continuity of the stream under Weir Road. Since the existing culvert is insufficient for required flows, is unsuitable for aquatic organism passage, and is in overall poor condition, it was determined that rehabilitation of the existing structure is not an option. The replacement structure on Weir Road will satisfy Massachusetts River and Stream Crossing Standards (MARSCS) and accommodate proposed flows of the restored river, as designed by Inter-Fluve, Inc. The purpose of this Alternatives Analysis Report is to outline existing conditions that need to be considered for a replacement structure, identify general replacement structure alternatives, and provide conceptual costs for each alternative. This report describes site conditions and constraints, including: • A survey and site review • Existing roadway conditions • An analysis of hydrologic and hydraulic conditions • A geotechnical analysis • A discussion of permitting and environmental considerations • Traffic management ALTERNATIVES ANALYSIS REPORT Tighe&Bond -3- Existing Conditions and Constraints Survey & Site Review Survey data was collected by Inter-Fluve in October/November 2020. Survey data in the vicinity of the culvert includes the road, culvert, guardrails, other surface features, edge of water, and existing contours. Survey data is depicted on conceptual drawings included in Appendix A. Tighe & Bond conducted a visual field review of the site in April and November 2020 to document existing conditions and verify general site conditions identified in the survey. A field report containing photos with descriptions of findings is included in Appendix B. The culvert is in poor condition overall with numerous deficiencies, including collapsed roof - stones in the stream within the culvert, debris buildup, and settlement. The downstream headwall is 8-feet tall with cracked or missing mortar, has missing stones with loss of backfill material, and is heaving forward. Roadway fill material is degrading and eroding into the stream through areas of missing stones or large gaps between stones. It is not possible to review the interior of the culvert because stones ha ve collapsed into the waterway at both ends, blocking visual access and the flow of water. Portions of the culvert have already failed, and due to the lack of access to the interior, the risk of full failure is unknown. However, if subject to high flows, further significant degradation is likely. Maintenance options for this partially collapsed structure are limited. Backfilling can be performed to replace roadway materials that have eroded into the stream. The collapsed stones prevent proper maintenance to the interior of the culvert. Streamflows currently have found alternate paths around the stones but continue to erode soils and the collapsed stones prevent aquatic and terrestrial organism passage. Roadway Conditions Weir Road is a Town-accepted road in the Town of Yarmouth, MA. It is classified as an urban collector or rural minor collector by MassDOT. It provides an east-west connection between Route 6A in the Yarmouth Port section of Yarmouth to North Dennis Road. According to the Cape Cod Metropolitan Planning Organization (MPO), the average daily traffic (ADT) is 1,465 vehicles per day as of June 2009. The traffic volume is seasonal to an extent, with higher traffic volumes during the summer vacation season. Weir Road crosses Hamblins Brook between the junctions of Seminole Drive and Lexington Lane. The horizontal alignment of the road at the culvert location is on a curve that is superelevated. There is no speed limit posted, but for purposes of sight distance analysis, 30mph was assumed to be consistent in character to other nearby roads with posted speed limits of 30mph. The existing roadway alignment does not provide the minimum horizontal radius of 371 feet for the design speed as specified in AASHTO: A Policy on Geometric Design of Highways and Streets. The existing road is a two-lane road at the culvert location with a guardrail-to-guardrail width of approximately 24’-0”. Each travel lane is approximately 10 feet wide and does not include a striped shoulder. The travel lanes meet the minimum design criteria for travel lanes of a collector classification, according to the 2006 MassDOT Project Development & Design Guide. There are no pedestrian or bicycle accommodations on or nearby the existing structure. The ALTERNATIVES ANALYSIS REPORT Tighe&Bond -4- pavement is in satisfactory condition. Notable intersections along Weir Road in the vicinity of the culvert include: • Seminole Drive, approx. 300 feet northwest of the culvert • Private Driveway for 72 Seminole Drive, approx. 200 feet northwest of the culvert • Private Driveway for 3 Lexington Lane, approx. 40 feet southeast of the culvert • Private Driveway for 142 Weir Road, approx. 160 feet southeast of the culvert • Lexington Lane, approx. 200 feet southeast of the culvert Utilities at the site were identified by survey, dig-safe, and verified by the Town and include: • Overhead electric- [Eversource Energy] • Communications– [Cox] • Underground Gas – [National Grid] • Drainage Structures –Town of Yarmouth • Water Main – Town of Yarmouth A utility pole is located approximately 12 feet northwest of the upstream invert of the culvert and therefore will need to be permanently relocated for all alternatives evaluated. Additionally, the 2-inch gas main will need to be temporarily relocated during construction. Based on discussions with the Water Superintendent, the water main can be taken offline during construction which will avoid a temporary bypass and reconstructed as part of the new structure. The gas and water main will need to be protected, and considerations for frost, loads, and exposure to potential damage will need to be considered. Sewer lines are not present at the site. The current alternatives make no accommodations for future sewer retrofit. The proposed roadway for the culvert replacement includes two 11-foot lanes with varying minimum width shoulders to provide a total minimum roadway width of 25-feet. Although sidewalks are not anticipated along each roadway approach, a sidewalk is included in the proposed stream crossing, resulting in a 33’-9” wide structure. The sidewalk will provide protection to buried utilities (i.e. gas and water). The horizontal alignment of the roadway is proposed to remain in the existing location. This is proposed to limit environmental impacts to the wetlands and stream as well as impacts to private property and utilities. Since the horizontal alignment does not meet the design requirements for the design speed, an advisory speed limit is suggested to warn drivers of the sharp curve. Additionally, new guidelines in the MassDOT 2023 Project Development and Design Guide provide allowance for consideration of a target speed in design of horizontal geometry. The Town of Yarmouth has noted that residents complain about the high speeds of vehicles and would prefer to implement an advisory speed limit around this curve. These dimensions are in accordance with A Policy on Geometric Design of Highways and Streets, 7th Edition. A roadway plan is included in Appendix A and an overview of the site is shown below, in Figure 1. ALTERNATIVES ANALYSIS REPORT Tighe&Bond -5- Figure 1- Overview of the Project Site (taken from google.com) Hamblins Brook Hamblins Brook flows from the southwest (upstream) to the northeast (downstream) at Weir Road. The Brook was historically part of the Bass River and allowed free-flowing tide waters from the Atlantic Ocean through Bass River and Mill Pond in the 1800’s. This allowed for an ecosystem which thrived on the tidal influence that reached Weir Road and beyond, and it included a large Herring population. In the early 1900’s, the wetlands area upstream of Mill Pond was dammed and modified for cranberry farming. Flows are channelized through various farming channels with control structures along Hamblins Brook. A goal of the Bass River Restoration Project is to restore historic free-flowing hydraulic connectivity to Bass River to restore the ecosystem and nutrient levels. The bankfull width of the Brook in the vicinity of the culvert is 14 feet according to Inter-Fluve’s report included in Appendix C. Hydrologic and Hydraulic (H&H) Analysis Various Hydrologic and Hydraulic Analyses have been performed to support this project to understand the tidal influence, the restoration of the wetland, and the upsizing of the culvert structure. The H&H work completed to date includes the following: • 2021 – Woods Hole Group Upper Bass River Restoration: Mill Pond & Crab Creek (Tidal Flushing Analysis) • 2021 – Inter-Fluve Bass River Headwaters Restoration Design Report • 2021 – Tighe & Bond Preliminary H&H Modeling for Bridge Structure • 2022 – Woods Hole Group Upper Bass River Restoration: Model Expansion & Inundation Mapping • 2024 – Woods Hole Group Upper Bass River Restoration, Hydraulic & Hydrologic Study (Coastal H&H) • 2024 – Tighe & Bond Upper Bass River Restoration, Hydraulic & Hydrologic Study (Bridge Structure H&H) Tighe & Bond’s Hydrologic and Hydraulic Analysis Report dated June 2024, and revised September 2024, for the existing and proposed conditions at the Weir Road Culvert is included Weir Road Culvert ALTERNATIVES ANALYSIS REPORT Tighe&Bond -6- in Appendix C. The analysis built upon the evaluation performed by Inter-Fluve as part of the Bass River Restoration Project and the coastal modeling performed by Woods Hole Group (WHG) for the Bass River. It is anticipated that the Bass River Restoration Project will include the removal of berms and hydraulic barriers, resulting in tidally influenced saltwater flows at the culvert which will, therefore, need to be designed for exposure to salt water. Furthermore, the widening of structures downstream of Weir Road, including the proposed widening of North Dennis Road culvert, will result in additional tidal flows that are anticipated at the Weir Road culvert. WHG’s coastal analysis conservatively assumed that all of the downstream stream crossing restrictions (Route 28, Highbank Road, CCRT, Route 6, and North Dennis Road) would be upsized such that the proposed Weir Road structure can accommodate future conditions. The proposed structure was evaluated for storm events in accordance with MassDOT LRFD Bridge Manual standards for hydraulic design. These include 10% Average Exceedance Probability (AEP) event for capacity with 2 feet of freeboard, a 4% AEP storm for scour design, and a 2% AEP storm for scour check. The stream configuration and bankfull width of 14 feet will generally not change as part of Inter-Fluve’s bog restoration design in the vicinity of the culvert. MARSCS do not apply to tidally-influenced streams, but were referenced as a basis of comparison between existing conditions and proposed alternatives. Satisfying MARSCS would require a bridge span greater than 16.8-feet to meet the 1.2 x bankfull requirement. The improved stream could be relocated to a new alignment which in turn can help with control of water during construction. However, a new stream alignment would negatively impact existing driveways, utility poles, or right-of-way. Maintaining the existing alignment was assumed for this report. As part of the modeling performed by Woods Hole Group, coastal effects are considered as part of the design alternatives. Effects include high tides, surges due to storms (i.e. tropical storms and Nor’easters), and future Sea Level Rise (SLR). These consid erations are expected to have increasing impacts as the restored river is reconnected to tidal flow at the location of the bridge crossing. A 24-foot span structure with a minimum low chord at 7.2 feet is determined to satisfy the requirements of MassDOT to pass a 10% AEP frequency riverine storm event with an excess of 2 feet of freeboard. However, it is not anticipated to provide adequate capacity to pass the 10% AEP coastal storm surge event without raising the low chord. Based on the Town's desired level of service for the roadway, the low chord could be raised to 9.0 feet NAVD88 to pass the 10% AEP coastal surge event with two feet of freeboard, but this would require raising the roadway profile to an elevation of 12.2 feet NAVD88 to provide adequate headroom for existing utilities, leading to additional environmental impacts that have not been evaluated. Scour was evaluated for the structure to inform the foundation depth and type. The scour design storm (4% AEP storm) and the scour check storm (2% AEP storm) are anticipated to be 1.8 feet and 3.3 feet, respectively. The bridge foundations will be constructed below the anticipated design scour depths in accordance with MassDOT guidelines. ALTERNATIVES ANALYSIS REPORT Tighe&Bond -7- Geotechnical Analysis Tighe & Bond conducted a subsurface explorations program to evaluate the suitability of the site’s subsurface conditions to support the proposed structure. Two borings (TB-1 and TB-2) were drilled by New England Boring Contractors of Brockton, Massachusetts on October 19, 2020. Due to uncertainty in N-values in boring TB-1 and shallow completion depth of boring TB-2, a supplemental geotechnical boring (TB-101) was drilled by Seaboard Drilling, LLC of Chicopee, Massachusetts on June 12, 2023. Borings were advanced with 4-inch-diameter flush-joint casing using drive-and-wash methods to depths of 54 feet, 11 feet, and 57 feet below the existing ground surface. Split-spoon sampling and Standard Penetration Tests (SPTs) were conducted continuously at depths of 9 to 19 feet, and at 5-foot intervals elsewhere in boring TB-101. Recovered soil samples were visually classified in the fiel d and eight mechanical particle size analysis tests were performed in a laboratory. The Geotechnical Evaluation report is included in Appendix D. Subsurface conditions observed in the explorations generally consisted of 12 inches of asphalt pavement, overlying approximately 4 to 9 feet of loose to medium dense existing fill, overlying approximately 2 to 4 feet of very soft organic soils (fibrous peat), overlying loose to medium dense, native sands, which were penetrated up to 48 feet before the explorations were terminated. Footings should bear a minimum of 4 feet below adjacent ground surface exposed to freezing temperatures for frost protection, and the depth should consider scour depth. Shallow foundations for the proposed bridge and wingwalls are anticipated to bear on native sands, which are considered suitable bearing materials. Subgrades may be easily disturbed during construction if they become wet; therefore, it is recommended that subgrades be over - excavated by 6 to 12 inches to allow for placement of compacted Crushed Stone wrapped in a nonwoven geotextile to provide a stable working subgrade. Although the existing soils are considered suitable to support a shallow foundation system, pile foundations are assumed for the purpose of this report for budgetary planning purposes due to the organic and loose subsurface material that was encountered and low bearing resistance to avoid settlement. The applied bearing pressure will be calculated during design phase and suitability of spread footings will be reviewed, if viable. We assume that a deep foundation system may be required to support the bridge. Technically feasible deep foundation alternatives include driven pipe piles, driven taper piles, ductile iron pipe piles (DIPs), and drilled micropiles (DMPs). Due to the proximity of residences to the proposed replacement bridge, vibrations from construction equipment will need to be carefully controlled and monitored. As such, micropiles or DIPs are considered to be lower risk deep foundation alternatives as th ey can be installed with minimal vibration compared to driven piles. If there are no “Made-in-America” provisions associated with the project, DIPs are recommended as they are typically quicker and less expensive to install than traditional micropiles with out producing drilling spoils. Permitting Proposed work for replacing the structure will require authorization under local, state, and federal environmental regulations. Freshwater stream crossings are required to comply with the Massachusetts Stream Crossing Standards to the maximum extent practicable, and are a consideration for this site even though they are not required for tidally influenced stream crossings. ALTERNATIVES ANALYSIS REPORT Tighe&Bond -8- Wetland resource area boundaries were delineated by Tighe & Bond, Inc. on June 15, 2023 as part of this study in order to inform project design and support environmental permit applications. For the purposes of identifying probable permits that will be required, t he following types of wetlands are present at the site, but are not limited to: • Bordering Vegetated Wetlands (BVW) • Inland Bank/Mean Annual High Water • Land Under Waterbodies and Waterways • 200-foot Riverfront Area • 100-foot Buffer Zone Proposed work will occur within areas subject to protection and jurisdiction under local, state, and federal regulatory programs. Based on the assumed wetland resources relative to the proposed structure location, Table 1 below summarizes anticipated permit requirements. It is likely that permits will be obtained jointly with the adjacent river restoration work, but the following requirements are anticipated for the culvert replacement in and of itself. TABLE 1 Summary of Anticipated Permits Agency Permit, Review, or Approval Local Yarmouth Conservation Commission Order of Conditions under the Massachusetts Wetlands Protection Act (MAWPA) and Yarmouth Wetlands Regulations (Chapter 143) State Massachusetts Department of Environmental Protection (MassDEP) Superseding Order of Conditions (only required upon appeal of local Order) 401 Water Quality Certification (if greater than 5,000 sf of work, cumulatively, in Land Under Water, BVW and/or IVW; or 100 cubic yards of dredging or more) Chapter 91 Waterways License Massachusetts Historical Commission (MHC) & Massachusetts Board of Underwater Archaeological Resources (MABUAR) Determination of No Adverse Effect (if filing Pre- Construction Notification with the Corps) Massachusetts Department of Transportation (MassDOT) Municipal Bridge Projects Massachusetts General Law (MGL) Chapter 85 Section 35 Review Process Federal U.S. Army Corps of Engineers (Corps) Section 404 Self Verification (if less than 5,000 sf of work, cumulatively, in land under water, BVW and/or IVW; or other categorical triggers) Section 404 Pre-Construction Notification (if greater than 5,000 sf of work, cumulatively, in land under water, BVW and/or IVW; or other categorical triggers) A Project Notification Form (PNF) will need to be prepared and submitted to the Massachusetts Historical Commission (MHC), which serves as the State Historical Preservation Office (SHPO), along with the geographically pertinent Tribal Historic Preservation Officers ALTERNATIVES ANALYSIS REPORT Tighe&Bond -9- (THPOs) that have an interest in the area per the United States Army Corps of Engineers (Corps) MA General Permit, and with the Massachusetts Board of Underwater Archaeological Resources (MA BUAR). A Chapter 91 Waterways License may also be required from MassDEP, as the replacement structure may require licensing pursuant to 310 CMR 9.00. A Notice of Intent (NOI) will be required for proposed work within jurisdictional resource areas and the 100-foot Buffer Zone in accordance with the Massachusetts Wetlands Protection Act (MAWPA) and Chapter 143. A site visit may be required as well as attendance at public hearings with the Yarmouth Conservation Commission. The Order of Conditions (i.e., permit) will need to be recorded at the Barnstable County Registry of Deeds. Section 404 of the Clean Water Act is administered by the Corps. We anticipate that the project will qualify for a Pre-Construction Notification under General Permits 1 (maintenance) and 14 (temporary construction, access, and dewatering). Additionally, as part of the adjacent bog restoration, a certificate of the Secretary of Energy and Environmental Affairs on the Expanded Environmental Notification Form (EENF) pursuant to the Massachusetts Environmental Policy Act (MEPA) has been obtained and is dated March 3, 2023. Massachusetts River and Stream Crossing Standards Massachusetts River and Stream Crossing Standards (MARSCS) do not apply to tidally - influenced streams such as this one, but were referenced as a basis of comparison between existing conditions and proposed alternatives. The MARSCS would require the span length to be at least 1.2 times the bankfull width of the stream. The top width of the proposed channel is 14 feet according to Inter-Fluve’s Design Report, leading to a minimum culvert width of approximately 16.8 feet to meet MARSCS. MARSCS are summarized below and are intended to be met to the greatest extent practicable on this project to provide sufficient aquatic organism passage. General standards include: • Structure Type: Open bottom span or Bridge • Embedment: Open bottom span or 2-feet embedment • Span: Minimum 1.2 x bankfull width • Substrate: Match stream substrate • Water depth / velocity: Match natural parameters over a range of flows • Openness ratio / height: 0.82 (General Standard) 2.46 / 8 ft (if wildlife passage inhibited 1.64 / 6 ft (otherwise) • Banks: Match existing on both sides & no wildlife hinderance Based upon standards set forth in the MARSCS, an openness (cross-sectional area divided by the crossing length parallel to stream) of 1.64 feet is preferred since conditions that significantly inhibit wildlife passage are not present at the site. MassDOT Chapter 85 Section 35 Review In accordance with Massachusetts General Law Chater 85 Section 35 “No bridge on a public highway having a span in excess of ten feet, except a bridge constructed under the provisions of chapter one hundred and fifty-nine, shall be constructed or reconstructed by any county or ALTERNATIVES ANALYSIS REPORT Tighe&Bond -10- town except in accordance with plans and specifications therefor approved by the department.” As such, these proposed alternatives resulting in a bridge span of 24 feet will be subject to review and approval by MassDOT. Traffic Management The roadway will be closed throughout the entire duration of construction of the replacement structure and a detour will be required. The proposed detour is anticipated to be Route 6A, Union Street, Station Ave, Whites Path, North Main Street, North Dennis Road, and W Great Western Road for a total detour length of 5.7 miles. Alternatively, Setucket Road and North Dennis Road could be used for a total detour length of 4.2 miles. In lieu of a full roadway closure, other options could be considered. These may be cost prohibitive for the site and trigger additional permitting requirements. Accelerated Bridge Construction (ABC) could be used to mitigate the closure duration, however, ABC is extremely costly and not warranted for this rural site. Staged construction could also be used with lane shifts and alternating single lanes of traffic. However, the existing roadway is narrow and maintaining a portion of the fill over the existing buried structure would be challenging and costly. Additionally, the proposed lane configuration is relatively narrow and buried structure options would be challenging to backfill using stag ed construction. A temporary bridge could be constructed at the site to limit the roadway closure. But in addition to increased design and construction costs, the temporary alignment would have substantial environmental impacts. It would be difficult to permit and would also lead to challenging right-of-way takings and impacts. ALTERNATIVES ANALYSIS REPORT Tighe&Bond -11- Alternatives Analysis and Recommendations In this section, alternative structural types for the proposed culvert replacement are described and evaluated. Four structural types/configurations that were evaluated are: • Alternative 1: 24-foot span Precast Concrete Arch • Alternative 2: 24-foot span Precast Concrete Arch with Raised Road • Alternative 3: 24-foot span Precast Concrete Rigid Frame • Alternative 4: 24-foot span Precast Prestressed Concrete Beams Each alternative considered structural requirements, geometric recommendations outlined previously, cost, and durability. All bridge components would be designed to support HL-93 live loading in accordance with AASHTO Load and Resistance Factor (LRFD) design criteria. All alternatives satisfy MARSCS with open-bottom natural streambeds. It was assumed that the existing horizontal and vertical alignments would remain, except for Alternative #2 which includes a raised roadway profile. All alternatives provide sufficient hydraulic capacity to pass a 10% AEP riverine event during MHHW with over 2 feet of freeboard. However, the roadway would need to be raised to accommodate raising the precast concrete arch structure to achieve 2 feet of freeboard during a 10% AEP coastal storm event. Alternative 2 focuses on meeting this criterion. The four alternatives are further described and evaluated below. A summary of conceptual design Opinions of Probable Construction Cost and recommendations for further design development are provided. For reference, structure types that were considered but not further evaluated as part of this analysis include: • A series of pipe culverts: This would consist of numerous 2 to 6-foot diameter pipe culverts in a series to convey flows. This option would not meet many of the MARSCS and are not considered feasible due to environmental permitting requirements. This alternative would also not be conducive to ecological improvements proposed for the Bass River Restoration Project. • Four-sided box culverts: Open bottom structures are preferred for MARSCS and a box culvert would require deep embedment below the streambed. Box culverts are more cost effective for spans under 10 feet and were not considered for the larger spans. Each alternative includes precast concrete sections, which would be manufactured offsite in a precast concrete plant and delivered to the site. Using precast components where possible will reduce the construction schedule on -site by avoiding lengthy set up and cure times. Precast concrete also provides a superior quality control compared to cast -in-place concrete since it is fabricated in a facility with regulated climate and ideal casting conditions. All of the structure types require minimal maintenance compared to larger bridges. Joints may be avoided at the roadway level due to the short span with minimal thermal expansion and contraction. Periodic cleaning and concrete sealing could be performed to extend the service life. General repairs should be performed based on findings and recommendations from DOT inspection reports. Conceptual drawings for each alternative are included in Appendix A. Conceptual opinions of probable construction cost are provided in Appendix E and are summarized in Table 2. ALTERNATIVES ANALYSIS REPORT Tighe&Bond -12- Alternative 1: 24-foot Span Precast Concrete Arch This alternative includes a precast concrete arch on pedestal footings to provide an open- bottom natural streambed. This buried structure alternative utilizes fill to distribute the load effects from trucks. Deep foundations are anticipated due to the soil conditions and proposed loads. Piles would be driven and pile caps would be constructed. The arch would be placed on the concrete pile caps. The arch would be backfilled with gravel. A minimum of 24 inches of cover over the top of the concrete would be provided to prevent pavement deformations. Precast headwalls would be placed on the upstream and downstream ends of the structure and bridge barrier would be attached to the top of the headwalls. Some utilities may be placed within the fill such as the gas and water mains. The utilities can be protected from axle loads by placing below a future sidewalk, outside of the traveled way. A precast arch shape is aesthetically attractive and provides opportunities for enhancement through use of formliners and stonework. The shape is well -suited for this semi-rural Cape Cod location. This is the preferred alternative as selected by the Town. The increased impacts to wetlands, private property, overhead utility clearance, and land under Article 97 restrictions to raise the low chord as in Alternative 2 would result in substantial cost and schedule impacts. The Town’s preference is to maintain the existing roadway elevation. Figure 2 - Typical Precast Concrete Arch ALTERNATIVES ANALYSIS REPORT Tighe&Bond -13- Alternative 2: 24-foot Span Precast Concrete Arch with Raised Road This alternative uses a precast concrete arch as described under Alternative 1, but with a raised roadway profile. The road would be raised approximately two feet so the low chord would be at 9.0 feet NAVD88. This would allow the arch to pass the 10% AEP coastal storm event with 2-feet of freeboard, which the MassDOT Municipal Bridge Project MGL Chapter 85 Section 35 Review Process Design Requirements and Submittal for New Bridge and Full Bridge Replacement Projects considers optimal. Without raising the road, the precast concrete arch passes the 10% AEP coastal surge event, but without 2 feet of freeboard as discussed under Alternative 1. An arch was used for this alternative for consistency with the refined coastal inundation modeling. While this alternative would increase the hydraulic performance compared to Alternative 1, it would also increase costs and impacts to wetlands, private property, overhead utility clearance, and land under Article 97 restrictions. Further review of these impacts would be required. Appendix A details the approximate impact areas. ALTERNATIVES ANALYSIS REPORT Tighe&Bond -14- Alternative 3: 24-foot Span Precast Concrete Rigid Frame This alternative is similar to the precast concrete arch (Alternative 1). The key difference is that the top of the frame would be flat rather than arched. This difference may result in a thicker top-slab of the frame compared to an arch. Approach slabs can be avoided for arch structures due to their rounded shape but are typically required for 3-sided frames, which increases cost. A possible conservative benefit with a three-sided concrete rigid frame is the additional hydraulic capacity that can be provided with a rectangular shape compared to an arch during infrequent storm events when the arch is at 100% capacity; however, increased hydraulic capacity would need to be carefully reviewed for tidal inundation impacts. This type of structure was evaluated as part of the project's initial hydraulic modeling, but was not included with the refined modeling that considered coastal surges. The refined modeling was performed for the arch (the preferred alternative). Figure 3 - Typical Precast Concrete Rigid Frame ALTERNATIVES ANALYSIS REPORT Tighe&Bond -15- Alternative 4: 24-foot Span Prestressed Concrete Beams This alternative includes precast prestressed concrete beams on abutments. Deep foundations are anticipated due to the soil conditions and proposed loads. Piles would be driven and pile caps would be constructed as abutments. The beams would be placed on the concrete pile cap abutments. Precast concrete voided slab beams are assumed for this span. The joints between abutting beams would be grouted together and a concrete overlay would be provided to distribute loads into the beams. Pavement would be provided over the concrete. Bridge rail or concrete barrier would be attached at each curbline. Rubber bearings would be provided on the abutments to resist deterioration. A utility bay could be provided between the beams to accommodate the gas and water mains. A utility bay could also be placed for future utilities such as sewer, underground electric, telephone, cable, or fiberoptic. Similar to Alternative 3, the increased hydraulic capacity would need to be carefully reviewed for tidal inundation impacts. This type of structure was evaluated as part of the project's initial hydraulic modeling, but was not included with the refined modeling that considered coastal surges. The refined modeling was performed for the arch (the preferred alternative). Figure 4 - Typical Bridge Comprised of Precast/Prestressed Concrete Voided Slab Beams ALTERNATIVES ANALYSIS REPORT Tighe&Bond -16- Summary and Opinion of Probable Construction Cost Conceptual opinions of probable construction cost are presented below in Table 2 and detailed breakdowns are included in Appendix E. The costs include a 30% Construction Contingency and a 20% Material and Bidding Contingency. TABLE 2 Summary of Opinions of Probable Construction Cost Alternative Opinion of Probable Construction Cost 1 – 24’ Precast Concrete Arch $2,200,000 2 – 24’ Precast Concrete Arch with Raised Road $2,330,000* 3 – 24’ Precast Concrete Rigid Frame $2,340,000 4 – 24’ Precast Prestressed Concrete Beams $2,440,000 *Further review would be needed to understand the full impacts of raising the roadway. This cost does not include additional expenses which may be needed as a result of raising the road, such as additional survey, right-of-way acquisition, utility impacts, restorative landscaping on private property, wetland restoration and/or replication, or associated design. Recommendations This report provides an analysis of alternatives for replacement of a culvert carrying Weir Road over Hamblins Brook in Yarmouth, Massachusetts. Of the alternatives evaluated, the recommended alternative is the 24’ clear span precast concrete arch bridge, Alternative 1, based on the Town's desired aesthetic, level of service for the roadway, and preference to maintain the existing roadway elevation. The recommended alternative has the lowest construction costs, provides adequate hydraulic capacity, and meets MARSCS. Furthermore, it avoids raising the roadway to minimize impacts to overhead utilities, adjacent wetlands, private property, and open space protected by Article 97. Since 2’ of freeboard will not be provided for the preferred alternative, it is recommended that the structure be designed for stream pressure which considers an appropriate drag coefficient for possible debris buildup. Precast concrete arch bridges are durable with a long service life and require very little maintenance. They are aesthetically attractive alternatives that can be designed and detailed to fit well at the crossing site. \\tighebond.com\data\Data\Projects\B\B5091 Friends of Bass River\003 Weir Road Bridge\Reports\Alternatives Analysis\Alternatives Analysis - Weir Road_2024.docx