HomeMy WebLinkAboutMonitoring report 2025
MONITORING REPORT
DEP File Number: SE 83-2279
Project Address: 162B Pleasant Street
Assessment Period: October 2024– October 2025
Project Documents: Site Plan Showing the Proposed Re-Building of an Existing
Licensed Pier System in and Over the Waters of Bass River by
Down Cape Engineering, Inc., signed and stamped by Daniel A
Ojala, P.E., P.L.S., dated 5/8/2021
Project Overview
This project involved the re-building of an existing pier system in and over the waters of Bass
River, along with the installation and anchoring of a coir roll array. After installation of the coir
roll array, it was covered with coir matting and nourished with compatible native sand. The array
was then planted with a mix of native shrubs and grasses to stabilize the bank. Additional native
shrubs were added at the bottom of the bank after the initial planting.
Project Activities Completed during Assessment Period
CLM completed one late season maintenance visit in early November 2024. No maintenance
visits were completed in 2025 while CLM was in the process of permitting additional
stabilization work. Minimal instances of aggressive weedy species and several hightide bush
(Iva frutescens) that had not survived were removed. However, the shrubs that were
removed were all voluntarily planted by the owner and were not part of the permit
requirements. Additional permitting was completed in 2025 to allow for additional shoreline
stabilization measures, including an additional row of coir rolls and supplemental
nourishment and plantings. This work was approved in September 2025 as an amendment
to the original permit.
Assessment of Current Site Conditions
Coir Fiber Roll Array
The coir roll array has remained in good condition with little to no damage sustained. The
sand nourishment has been translocated over time, as anticipated, to reveal more of the top
row in the array. The wrack line has also continued to serve as a good buffer to help prevent
damage to the coir logs, but also makes establishing herbaceous plants difficult and
challenging due to the thickness of the wrack layer. Surveying stakes have been placed in
preparation for the addition of coir logs above the existing array where there are signs of
scarping for the newly acquired work permissions.
Invasive Species Management
Invasive species were still present along the bank, but in very minimal quantities. Very small
amounts of Oriental bittersweet (Celastrus orbiculatus) and spotted knapweed (Centaurea
stoebe) persist as the only state-listed invasives present. Sporadic and minimal instances of
aggressive vegetation are also present. These include climbing bindweed (Fallopia
scandens) and American burnweed (Erechtites hieraciifolius). Both invasive and aggressive
vegetation have been controlled effectively with only minor maintenance necessary. Annual
maintenance will be necessary in order to remove invasive or aggressive plant material that
is deposited from neighboring properties or waterways, but with regular maintenance
populations are effectively controlled.
Restoration Planting Establishment
The plantings along the bottom of the coastal bank have had the most difficulty becoming
established. This is likely due to regular tidal inundation and wave energy as well as the
build-up of wrack. The American beachgrass (Ammophila breviligulata) has done well
establishing in areas along the bottom of the coir array, but is sparse in most areas where
the nourishment has washed away. Seaside goldenrod (Solidago sempervirens) has
continued to establish well, with large, tall stands in the middle of the bank. No additional
high-tide bush (Iva frutescens) have died during the second growing season after their
planting. The surviving high-tide bush appear healthy with some spreading to form large
clusters. These plantings were not required per the permit, but were planted because it was
believed they could provide an added buffer layer to protect the bank. The wrack line along
with the additional plantings have done well to protect the coir array from any major
damage, but the sand nourishment continues to wash away. Supplemental nourishment and
plantings were approved under the Amended Order of Conditions, which should address
some of these items.
Anticipated Activities to be Completed Over the Next Monitoring Period
Over the next monitoring period, CLM anticipates completing the following activities:
• Monitor restoration area and treat or hand weed all invasive, non-native, and
aggressive vegetation that has sprouted back from the soil seed bank or remaining
roots in the soil.
• The placement of additional coir logs above the current installation to prevent
further progression of scarping on the top of the coastal bank under the newly
acquired permissions.
• Continue to place supplemental nourishment over the existing and new coir logs and
re-plant with American beachgrass and other native grasses as necessary to help
hold sediment in place and establish a vegetative groundcover.
Recommendations for any Changes in Land Management Techniques
Work approved under the Amended Order of Conditions should address some of the issues
noted in this and prior reports, such as the minor scarp at the top of the bank and the lack
of vegetation establishment.
Unexpected or Arbitrary Changes to the Project Area
After noticing signs of scarping above the uppermost coir log, CLM permitted an
amendment to the permit which provides for the installation of an additional row of coir logs
in the scarped area at the top of the bank. Installation of the additional row of rolls and
nourishment will likely be completed in winter 2025 or early spring 2026.
Representative Project Area Photographs
Coastal bank during late season maintenance visit. November 2024.
Large stands of seaside goldenrod have established along the coastal bank. Beach
grass is spreading in the area as well. September 2025.
Signs of scarping above the top coir log. Stakes for proposed additional coir
logs. September 2025.