HomeMy WebLinkAboutCCOR 02-19-2026 792-99Concrete Construction Observation Report
The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control.
, , , • Tel • Fax • www.swcole.com
Project Name:Town of Yarmouth Water Resource Recovery Facility Project NO.:25-0468Location:Yarmouth MA Date:2/19/2026
Client:Wright-Pierce Client Rep:Eric SaloWeather:Clear 44 - 49°F S.W.COLE Rep:Rob Reuter
General Contractor:Wright Pierce Time Onsite:06:15 - 10:15
Placement Type: Footing Wall Slab OtherPlacement Location:A-Vehicle storage building center slab & knee wall B- Southwest wall section
Concrete Placement Observations Observed Comments
Required mix used Yes 4500 PSI 3/4” aggregate
Concrete properly conveyed to all areas of placement Yes Pump truck used to convey concrete
Internal vibration / consolidation of concrete Yes Worm vibrator used throughout
Even layering around openings and embedments Yes concrete evenly laid around all openings and
embedment
Post placement observations (finishing, curing, etc.)Yes Concrete manually finished and covered with
heated blanket blankets
Field Testing of Concrete performed:Yes
*CYLINDER SET NO:792-99 *Refer to associated concrete test report
Notes:
S.W. Cole Engineering Construction Services Technician Robert Reuter arrived onsite at 6:15 AM for "Concrete Field Testing"
and for the placement location referenced above. Upon arrival, met with Eric Salo with CDM Smith who provided information
about today's job duties.
Concrete was delivered by "Cape Cod ready mix." and was 3/4” 4500 PSI Concrete. A total of (96) cubic yards of concrete was
placed.
A sample was collected from load 2 and the standardized testing was performed with; one set of (5) cylinders were cast from
the load for laboratory compressive strength testing at 7, 14, and (2) 28 days. One cylinder was made for 'Hold' purposes.
The results Truck two
•Slump 6-3/4”
•Air 4.8 %
•Temperature 67°
Note:
Part A. of this inspection was completed. Part B. was cancelled due to the pump truck didn’t
have a long enough hose to get within 4 feet of the bottom of southwest wall. RR observed
Nicholson pouring concrete into southwest corner wall before canceling part B. of this job. RR
informed Eric Salo about concerns for cold joint. Eric informed RR that said concrete would be
removed from the forms before we placed concrete in that wall at a later date.
Observations and Results of the Inspection were continually communicated to Client Representative Eric Salo from "CDM
Smith ". Once the inspection was completed RR left the site.
Attachments: 7 Photos Reviewed by:2/19/2026 Kaylie OSu iv Kaylie OSullivan
Concrete Construction Observation Report
The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control.
, , , • Tel • Fax • www.swcole.com
Concrete Construction Observation Report
The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control.
, , , • Tel • Fax • www.swcole.com
Concrete Construction Observation Report
The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control.
, , , • Tel • Fax • www.swcole.com
Concrete Construction Observation Report
The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control.
, , , • Tel • Fax • www.swcole.com