Construction Protocol — Building Raise & Foundation Work
1. Pre -Construction Preparation
• Obtain all required permits and approvals.
• Utility disconnects (electric, gas, water, sewer).
• Interior prep as needed (remove fragile finishes, secure structure).
• Install temporary bracing to reinforce the structure prior to lifting.
2. Structure Lifting & Temporary Support
• Excavate around the existing foundation as required.
• Install engineered steel beams beneath the structure.
• Use synchronized hydraulic jacking system to lift the building in controlled
increments.
• Place the structure on temporary cribbing supports at the required elevation.
3. Existing Foundation
I
Once the structure is fully supported, the existing foundation will be:
o Demolished and removed in accordance with local regulations, or
o Partially removed if any section is approved to remain (to be confirmed per final
engineering).
All debris will be properly disposed of off -site.
4. New Foundation Construction
• Excavation to required depth and elevation.
• Install footings per approved structural plans.
• Form and pour new concrete foundation walls (or install engineered foundation
system as specified).
• Install waterproofing, drainage system, and insulation as required.
5. Setting Structure on New Foundation
• After the new foundation has achieved required strength, the structure will be lowered
and permanently secured to the new foundation.
Install anchor bolts, sill plates, and structural connections per engineered details.
6. Finalization
Reconnect utilities.
Backfill and site grading.
Complete any required exterior or interior tie-in work.
2
All work will be performed in accordance with approved structural engineering plans and
local building code requirements.
Please let me know if the Conservation Commission would like additional detail or
engineering documentation.
Best regards,
Hamisses Lobo
Wolf Carpentry INC.
508-815-9708
From: Danny Gonsalves <dgonsalves@downcape.com>
Sent: Tuesday, February 17, 2026 11:28:32 AM
To:
Subject: 29 Lewis Bay Blvd (Cosenzi)
Hamisses,
At the Conservation meeting one of the members was interested in the process of how the existing building will be
raised and moved.
They were also asking about what will happen to the existing foundation.
Could you send me a short construction protocol on the sequence and process of construction for this job?
Thanks,
Danny E. Gonsalves, PE
Professional Engineer
Down Cape Engineering _Inc.
Tel: 508-362-4541
This Electronic Message contains information
from the engineering firm of down cape engineering, inc.,
which may be privileged. The information is intended
to be for the use of the addressee only. If you are not
the addressee, note that any disclosure, copy, distribution
or use of the contents of this message is prohibited.