HomeMy WebLinkAboutCCOR 02-27-2026 792-100 to 792-101Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. , , , • Tel • Fax • www.swcole.com Project Name:Town of Yarmouth Water Resource Recovery Facility Project NO.:25-0468Location:Yarmouth MA Date:2/27/2026 Client:Wright-Pierce Client Rep:Eric SaloWeather:Clear 31 - 38°F S.W.COLE Rep:Kellie Jigerjian General Contractor:Nickerson Time Onsite:07:30 - 12:00 Placement Type: Footing  Wall  Slab  OtherPlacement Location:Solids handling building SE and N walls Concrete Placement Observations Observed Comments Required mix used Yes 4500psi 3/4", 4500psi 1-1/2" Concrete properly conveyed to all areas of placement Yes pump truck Internal vibration / consolidation of concrete Yes handheld vibrator Even layering around openings and embedments Yes troweled evenly around openings and enbedments Post placement observations (finishing, curing, etc.)Yes smooth trowel finish Field Testing of Concrete performed:Yes *CYLINDER SET NO:792-100 to 792-101  *Refer to associated concrete test report Notes: S.W. COLE Construction Serviced Technician KEJ arrived on site at 7:30AM for concrete testing/ sampling for the location referenced above. The pours for the SE and N walls were considered two different placements as the mix did change.  Concrete arrived onsite at 8:00AM (load 1) for the SE wall pour carrying 11CY of 4500psi 3/4" with SIKA control 75, and 1% nonchloride added prior for all loads.  placed via pump truck One set of tests were taken with the following results Load 1: slump: 8-1/4” air content: 3.9% temperature: 63deg F A set of six compression cylinders (4x8) were cast for testing at 7, 14, 28(3), and one held in reserve   Concrete arrived onsite for the N wall pour at 10:55AM (load 1) carrying 10CY of 4500psi 1-1/2", with SIKA control 75, and 1% nonchloride  added prior for all loads Load1: slump: 9” air content: 3.6% temperature: 65deg F Six compression cylinders (6x12) were cast for testing at 7, 14, 28(3), and one held in reserve KEJ spoke with Eric Salo onsite After testing KEJ had time onsite corroborated and left at 12:00PM Attachments: 3 Photos Reviewed by:2/27/2026 Kaylie OSuivKaylie OSullivan Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. , , , • Tel • Fax • www.swcole.com Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. , , , • Tel • Fax • www.swcole.com