The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control.
58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com
Project Name:Town of Yarmouth Water Resource Recovery Facility Project NO.:25-0468Location:Yarmouth MA Date:6/30/2026
Client:Wright-Pierce Client Rep:Rayssa FonteWeather:Cloudy 60 - 75°F S.W.COLE Rep:Riley Nordahl
General Contractor:Nickerson Time Onsite:05:30 - 10:00
Placement Type: Footing Wall Slab OtherPlacement Location:SBR Slabs 42, 34, 33
Concrete Placement Observations Observed Comments
Required mix used Yes 4500psi, 1-1/2", Sika Control 75
Concrete properly conveyed to all areas of placement Yes A Pump truck was used
Internal vibration / consolidation of concrete Yes A handheld vibrator was used for the consolidation
of concrete
Even layering around openings and embedments Yes Concrete was evenly layered around openings and
embedments
Post placement observations (finishing, curing, etc.)Yes Concrete was finished manually
Field Testing of Concrete performed:Yes
*CYLINDER SET NO:792-166 to 792-168 *Refer to associated concrete test report
Notes:
As requested by Rayssa (CDM Smith), an S.W.COLE rep was onsite to perform concrete
sampling, and concrete testing at the locations referenced above.
The S.W.COLE Construction Services representative arrived onsite at approximately 5:30 AM.
Concrete placement was observed during the time of sampling and testing.
Concrete Delivery of Load 2 arrived onsite with approximately 11 cubic yards of 4,500‑psi
concrete with 1‑1/2‑inch aggregate. Sika 75 admixture was added prior to placement. The
concrete was placed via pump truck.
Three sets of field tests total were performed on sampled concrete with the following results:
Truck 52 – Load 2
Slump: 8 inches
Air Content: 4.0 percent
Concrete Temperature: 75°F
Truck 64 – Load 12
Slump: 9.0 inches
Air Content: 3.0 percent
Concrete Temperature: 75°F
Truck 64 – Load 18
Slump: 9.5 inches
Air Content: 3.0 percent
Concrete Temperature: 75°F
Three sets of compression test cylinders were cast for laboratory testing at 6, 14, and 28 days
(2), along with one hold cylinder.
Laboratory compressive strength test results will be reported separately upon completion of
testing.
Test results and observations were verbally reported to the onsite client representative while
onsite.
The S.W.COLE rep departed the site at approximately 10:00 AM after completing the requested
services
Concrete Construction Observation Report
The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control.
58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com
Attachments: 4 Photos Reviewed by:6/30/2026 Kaylie O'Su iv Kaylie O'Sullivan
Concrete Construction Observation Report
The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control.
58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com
Concrete Construction Observation Report
The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control.
58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com