HomeMy WebLinkAboutShorefront to Waterways and Conservation 104 River St project 7-6-26 Shorefront Consulting
Professional Services on Land or At Sea
290 Center St., Dennis Port, MA 02639 www.shorefrontconsulting.com
508-280-8046 shorefrontconsulting@gmail.com
Yarmouth Waterways and Shellfish Advisory Commission Updated July 6, 2026
Attn: Kathyrn Brooks
424 Route 28
West Yarmouth, MA 02675
By email
Re: Application Filing Package Review for 104 River Street; Proposed Pier, Ramp, and Float
I am writing to the commission as a private citizen in opposition to the proposed Pier, Ramp, and Float
at 104 River Street. I am a seasoned professional that designs and permits docks in many towns on and
off the Cape, and has done so for over 25 years. I am still concerned with the lack of information and
the lack of correct information for this project. The applicant has been advised several times on how the
project might be improved, and progress is slow and the plan is still lacking information and is incorrect.
Updated Waterways concerns:
I attended the first waterways hearing on April 9th for 5 of my projects on the agenda and listened to
the presentation for the 104 River Street project, where the committee had several questions and
concerns for the project. I share the same concerns that are mentioned in the April 9 minutes with the
committee. The applicant was asked to provide additional information such as distances to adjacent
structures, the public beach, and the distance to the channel. The pier length was also an issue where it
extended too far towards the channel, and where 3 feet of water is reached much closer to shore. There
was a discussion of the 4 variances needed to approve the project, which is within the jurisdiction of
the conservation commission. The hearing was continued to allow time for the applicant to provide the
required information.
I attended the second waterways hearing on June 11, and I have reviewed the revised plan dated 6/22/26
provided by the applicant. The plan STILL incorrectly shows the abutting Hearn dock to the north to
now be only a straight fixed pier. The previous plan showed the correct layout, only that the “L” at the
end of the pier was incorrectly labeled as a float which was incorrect. The revised plan deleted the “L”,
which is still incorrect. The revised plan removes the previous ramp and float, and changes the design
to a fixed pier; similar to the approved pier to the north for Mr. Hearn. The plan still mentions a ramp
and float (notes #9 and #14) and should be deleted from the plan. The plan was revised to show the
distance to the town beach to the north. In my opinion, this is the only revision that is correct.
The previous plan showed the distance to the channel being to the red buoy, which is the farthest edge
of the channel, not the closest edge that is required. The applicant was advised on the channel width and
asked to revise that dimension to show the correct distance to the channel. Instead, that dimension is
deleted from the current revision. The applicant was asked to provide the distance to the McCarthy float.
The distance is shown as 78.9’ to the McCarthy pier, but is incorrect because the distance is required to
be measured from the float, which would be approximately 8 feet closer, or about 70 feet. The float is
not shown on the plan, and this dimension must be corrected so that the distance from the proposed pier
to the McCarthy float is indicated.
The required 3 feet of water depth is reached approximately 12 feet from the bulkhead. The pier was
shortened again but now is too short as there appears to be only 1.5 feet of water at low tide where 3 feet
is required. The pier should now be lengthened to approximately 12 feet (as previously advised) to a
point where 3 feet of water is reached at low tide, in accordance with the regulations.
Generally, the purview of the Waterways and Shellfish Advisory Committee is to review projects with
respect to shellfish and navigation. The revised plan does not provide the requested distances to adjacent
structures and the channel. The plan incorrectly shows the approved dock to the north, and does not
show the McCarthy float to the south or the distance to it. Therefore, the committee does not have
adequate information to evaluate the project with regards to navigation, and the project should not be
allowed to move forward unless and until this information is provided. The attempts made so far by the
applicant to make simple plan changes as requested appear completely inadequate and incorrect. If the
committee decides to give the applicant one more chance to come up with a plan with the required
information and a design that more closely reflects the regulation requirements, it is their ability to do
so. However, if the applicant chooses not to provide this information, or the committee decides that the
applicant has been given sufficient advice and opportunity to provide the required information, but failed
to do so, then the committee should vote to not support this application based on the lack of information.
Conservation concerns:
In a letter from the applicant dated 3/18/2626, the applicant attempted to address several issues related
to the initial NOI filing. I reviewed the revised materials submitted on 3/18/2026. The revised plan dated
5/6/26 is also in the town online documents. The application is still lacking much of the required
information that the agent requested. The plan requirements for NOI filings were implemented on
January 15, 2026, and the NOI was submitted on January 29, 2026. There is no table of resource areas
and impacts on the plan. The required distances to evaluate the project for the variances are not on the
plan. The 35-foot resource area offset is not shown on the plan. The plan does not comply with the
updated plan requirements dated 1/15/26, and requires updating before the commission can review it.
The NOI value for LSCSF was not correct and was not changed, and is therefore still incorrect. I don’t
see where there is 459 square feet of LSCSF when the pier occupies 4’x 16’. The value for the total area
of Riverfront Area on the lot and the associated impact area are incorrect. The value for Land under
ocean is incorrect; the float itself occupies 200 square feet without the ramp and pier included. The value
for Land Containing Shellfish is also incorrect. I do not see an alternatives analysis in the NOI filing,
nor an alternatives analysis for the Riverfront Area.
There are 4 variances requested but the project needs 5. The additional variance comes from the
regulation specifying that the pier must be located in the center of the lot. The pier does not meet this
requirement. My only comment for a pier proposed on property that does not belong to the applicant
without their permission (which admittedly is not within the jurisdiction of the commission), is about as
bold and inconsiderate as it gets. Chapter 91 will require a letter of permission from the property owners
for the license application, and I do not believe the applicant can obtain such letters.
Overall, the application is very incomplete. The applicant was asked to provide more information. While
the plan was revised twice, it still does not have the required information. The NOI doesn’t seem to be
revised at all. This is very disrespectful to the permitting process and the staff and volunteers that serve
to implement that process. The applicant was given a chance to provide the required information and
has chosen not to do so. In my opinion, this project should be denied because of the lack of information
and what appears to be the applicant’s refusal to supply said information. The denial has no bearing on
surrounding piers or structures; it would be based on the applicant’s refusal to cooperate and provide
the required information on the plans and the NOI application. Further, I believe that the project can be
denied because a variance from the 75-foot setback to the abutting dock to the south is still required
whether or not the dock to the north is constructed. Even if the applicant provided the necessary
information, the project can be denied based on its own merits because of the excessive amount of
variances required to obtain approval.
It may be possible to re-design the project to better meet the objectives of both the Waterways
Committee and the Conservation Commission, but the applicant still appears to have provided a minimal
effort to do so. While approval is never guaranteed, there should at least be an attempt to provide the
best available project for the Waterways Committee and the Conservation Commission to consider.
Failure to provide that effort is also grounds for denial.
At this point, the applicant has been given sufficient information (literally spelled out in writing) to
provide a plan and an application that is complete enough for the conservation committee to review. The
revised plan is not complete and requires additional and correct information to proceed with
conservation. The application information is incorrect, the required variances have not been adequately
addressed, and the required alternatives analysis have not been provided. The application as currently
presented can be denied based on the lack of information.
Respectfully submitted,
Mark Burgess
Shorefront Consulting
B.S. Ocean Engineering
cc: Yarmouth Conservation Commission (by email)