HomeMy WebLinkAboutWWSAC minutes 11.18.2024 On 12/16/2024, on a motion by committee member Crawford, seconded by committee member
Churchill, the Waterways & Shellfish Advisory Committee voted 3-0 to approve these minutes as
written.
MINUTES YARMOUTH WATERWAYS AND SHELLFISH ADVISORY COMMITTEE MEETING
November 18, 2024
MEMBERS PRESENT: Julian Mallett (Chairman), Rick Crawford, Mike Dunbar, Al Keller, Bob Churchill
STAFF PRESENT: William Bonnetti, Kathryn Brooks
OTHERS PRESENT: Baine and Nadine Gill, Bob Perry, Dan Ojala
_______________________________________________________________________________
At 5:36 p.m. the Director of Natural Resources, Bill Bonnetti, read the open meeting law and explained
the meeting audio was going to be recorded.
Agenda:
1.Public Comment: There was no public comment.
2.Notice of Intent
a.Daniel Ojala, Down Cape Engineering, Inc., 10 Buttercup Lane, proposed construction of
stairs, fixed pier, ramp and floats
The homeowner wants a dinghy dock for kayaks and canoes. There is 1’ at Mean Low Water at the float
but Mr. Ojala said float stops would be used. He explains this dock is much shorter than the dock
regulations require. The dock would not be the full 75’ from the neighboring dock to the east. Mr. Ojala
says the old stair debris will be removed, and the float is under regulation size. They were going for a
modest proposal and are also far from the channel. Mr. Crawford stated shellfishermen would not be
happy about this dock.
Speaking on behalf of the shellfish constable who was unable to attend, Director Bonnetti said there are
concerns for shellfish, which is a year-round fishery and this spot is also a Town propagation area. He
mentioned concerns for boat traffic and disturbing the bottom. A project like this would require a
mitigation fee in addition to shellfish removal. The consultant asked why people could not shellfish
around the docks and mentioned a large dock may have adverse effects but this would be a small dock.
It could potentially allow shellfish to reproduce and repopulate the area.
Chairman Mallett asked what type of craft hey would be putting on the dock and was told only self
propelled crafts. Ms. Brooks added she didn’t think there was any way to regulate or prevent a certain
type of craft from being on a dock once it is built. It was discussed that another dock would be a hazard
to shellfishermen, but Mr. Ojala pointed out that the longer docks on either side would be hit before
they hit the dock being proposed. He clarifies they would need a variance for water depth and distance
to an abutting pier and are looking for a balance between shellfishermen and homeowners.
Committee members voiced their concern for this project and would like to visit the site prior to voting
on the project. Mr. Crawford motioned to continue this meeting until December 9, 2024. This was
seconded by Mr. Churchill and the motion passed 4-0, with 1 abstention.
On 12/16/2024, on a motion by committee member Crawford, seconded by committee member
Churchill, the Waterways & Shellfish Advisory Committee voted 3-0 to approve these minutes as
written.
b.Bob Perry, Down Cape Engineering, 206 South Street, proposed construction of a pier,
ramp, and float, and replacement of an existing stone revetment
Mr. Perry said the original jetty from 1910 was rejected by the Conservation Commission but the Gill’s
are rethinking the project. The proposed dock is in a new location at the north edge of the property. The
length of 128’ is needed to reach the 3’ of water at MLW. The end of the proposed dock would also be
200’+ from the navigational channel. Mr. Perry acknowledges the dock is 48’ longer than the 80’ limit,
but it is still shorter than the neighboring dock to the north. Director Bonnetti adds this area is not
congested with moorings. Mr. Perry states the revetement needs to be rebuilt, and would be done in
the same footprint, and they know the dock is long. Mr. Gill adds they have had a significant amount of
erosion along the revetment, with an estimated 8’ being eroded within the past year or so. On behalf of
the shellfish constable, Director Bonnetti adds there would need to be shellfish removal from the area.
Relocating causes mortality, and a mitigation fee would also be a good addition.
Mr. Churchill motioned to approve the plan with no objections. This was seconded by Mr. Crawford and
the motion carried 4-0 with 1 abstention.
c.Bob Perry, Down Cape Engineering, 59 Oyster Cove Road, proposed
renovation/modification of an existing dock facility
35 Oyster Cover Road has deeded rights to the beach. The Conservation Commission had previous
debris removed, and said they do not want a dock. The floats currently sit on the bottom at low tide, but
they would be changing to a pile supported pier to address this issue. The pier would be in a similar
footprint but would have reduced impact on shellfish because the floats would no longer be on the
bottom. On behalf of the shellfish constable, Director Bonnetti said the elevation of the dock and
removal of floats would be good to keep things off the bottom. He also wanted to confirm the easement
owner is the one applying for the dock, which is correct. Director Bonnetti also said this area is
conditionally approved for commercial shellfishing and would ask that any shellfish be removed from
the area.
Mr. Crawford added that there was no impact to shellfish or navigation and considers this new plan to
be an improvement. Mr. Dunbar said he remembers this area being quite muddy. Mr. Crawford
motioned to move the project to conservation because there is no impact to shellfish/navigation.
Director Bonnetti confirmed last minute the water depth was not met, and Mr. Perry responded that the
floats will be off the bottom although float stops are not currently proposed. The motion is seconded by
Mr. Churchill and the motion passed 5-0.
3.Committee Discussion & Updates
Director Bonnetti will setup a day/time to go on a site visit to 10 Buttercup. He also said the
requirements for submitting a project have changed and require them to be submitted 2 weeks prior to
a meeting so we can get out to the site ahead of time.
Questions were asked about Friends of Bass River and the scallop project. Director Bonnetti said he
doesn’t know all of the details but the Town needs to discuss bandwidth of money and staffing before
On 12/16/2024, on a motion by committee member Crawford, seconded by committee member
Churchill, the Waterways & Shellfish Advisory Committee voted 3-0 to approve these minutes as
written.
expanding the project. The seed this year came from Dan Ward’s hatchery in Falmouth. The director
mentioned the bridge project on Bass River will be moving forward next year and is not sure how that
will impact Packet Landing. The bid should be going out soon.
Chairman Mallett asked what the reservations were on the scallop project. Director Bonnetti agreed it’s
a good program but explained space on the river, access, maintenance, and finding the right depth to
grow at low tide were all factors. Chairman Mallett said 11th Hour did a segment on the oyster upwellers
and good job to Casaundra. Director Bonnetti said the Town is working on a dredge contract for
permitting upper Bass River. Dunbar asked about the Sweetheart Creek dredging and said he noticed
they were dredging the banks where there was a really good set of softshell. Director Bonnetti said
dredging should only be occurring in the center of the channel and it is being cleared out in sections. He
would follow up to make sure the work is being done in the right area.
Mr. Crawford motions to adjourn the meeting, which is seconded by Mr. Churchill. The motion passes 5-
0 and the meeting ends at 7:18 p.m.