Loading...
HomeMy WebLinkAboutCCOR 07-29-2026 792-180 to 792-181Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. 58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com Project Name:Town of Yarmouth Water Resource Recovery Facility Project NO.:25-0468Location:Yarmouth MA Date:7/29/2026 Client:Wright-Pierce Client Rep:Rayssa FonteWeather:Cloudy 68 - 70°F S.W.COLE Rep:Edwardo Baldera General Contractor:CDM SMITH.Time Onsite:05:00 - 10:00 Placement Type: Footing  Wall  Slab  Other: Column.Placement Location:Tee Wall on SBR Slab 23. & Headworks Columns Concrete Placement Observations Observed Comments Required mix used Yes Wall: 1-1/2" Aggregate, 4500psi, Concrete Mix with Sika Control 75. Columns: 3/4" Aggregate, 4500psi, Concrete Mix with Sika Control 75 Concrete properly conveyed to all areas of placement Yes The Pump Truck was used to convey all concrete to the wall and column sections. Internal vibration / consolidation of concrete Yes Hand Held Concrete Vibrator. Even layering around openings and embedments Yes The concrete was evenly layered throughout the sections Field Testing of Concrete performed:Yes *CYLINDER SET NO:792-180 to 792-181  *Refer to associated concrete test report Notes: As requested by Rayssa Fonte, S.W.COLE rep was onsite to perform concrete field testing associated with the concrete placement referenced above. S.W.COLE Construction Services Technician Edwardo Baldera arrived onsite at approximately 5:00 a.m. to perform concrete field testing for the placement location referenced above. Upon arrival, SWC rep met with Rayssa Fonte of CDM Smith, who provided an overview of the planned concrete placement activities for the day. The concrete for the wall placement was supplied by Cape Cod Ready Mix and consisted of a 4,500 psi concrete mix with 1½-inch nominal maximum coarse aggregate and Sika Control 75 admixture. The concrete used for the column placement consisted of the same 4,500 psi mix design with ¾-inch nominal maximum coarse aggregate and the same specified slump and air-content requirements. Approximately 45 cubic yards of concrete were placed during the course of this operation, consisting of approximately 41 cubic yards for the walls and 4 cubic yards for the columns. Specified Concrete Properties Slump: 7 to 10 inches Air Content: 3.0% to 6.0% (air-entrained mix) Concrete samples were obtained from the first load placed for the wall placement and from the first load placed for the column placement. Field testing was performed in general Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. 58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com accordance with applicable ASTM standards, and the following results were obtained: Wall Placement - First Load Placed (Truck #81) Batch Ticket #: 53069 Batch Time: 5:25 a.m. Arrival Time: 6:02 a.m. Slump: 8.0 inches Air Content: 3.2% Concrete Temperature: 79°F Column Placement - First Load Placed (Truck #60) Batch Ticket #: 53073 Arrival Time: 8:45 a.m. Slump: 8.0 inches Air Content: 3.3% Concrete Temperature: 81°F One set of five compression test cylinders was fabricated from each tested load for laboratory compressive strength testing. Cylinders are scheduled for testing at 7 days, 14 days, and two cylinders at 28 days. One cylinder from each set was retained as a hold specimen. Test results and field observations were verbally communicated onsite to Rayssa Fonte of CDM Smith during the course of our services.   Attachments: 2 Photos Reviewed by:7/31/2026 Kaylie O'SuivKaylie O'Sullivan Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. 58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com