HomeMy WebLinkAboutCCOR 08-28-2026 798-197 to 798-199Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. 58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com Project Name:Town of Yarmouth Water Resource Recovery Facility Project NO.:25-0468Location:Yarmouth MA Date:8/28/2026 Client:Wright-Pierce Client Rep:Rayssa FonteWeather:Clear 67 - 75°F S.W.COLE Rep:Alexander Charnitsky General Contractor:Nickerson Time Onsite:05:30 - 09:30Placement Type: Footing  Wall  Slab  Other Placement Location:SBR Slabs 45, 47 and 57 Concrete Placement Observations Observed Comments Required mix used Yes 4500psi, 1 1/2", Sika 75 Concrete properly conveyed to all areas of placement Yes Pump Truck Internal vibration / consolidation of concrete Yes Handheld vibrator Even layering around openings and embedments Yes Concrete evenly layered and vibrated around openings and embedments Post placement observations (finishing, curing, etc.)Yes Concrete Manually Finished Field Testing of Concrete performed:Yes *CYLINDER SET NO:798-197 to 798-199  *Refer to associated concrete test report Notes: As requested by Wright-Pierce, S.W. COLE rep was onsite to perform concrete sampling and concrete testing at the locations referenced above. S.W. COLE rep Alex Charnitsky arrived onsite at approximately 9:30 AM to perform the requested services. S.W. COLE rep observed concrete placement during the sampling and testing activities. Concrete Delivery Truck 81, Load 2, arrived onsite carrying approximately 11 cubic yards of 4,500-psi concrete containing 1½-inch aggregate. Project personnel added Sika 75 admixture to the concrete prior to placement. The contractor placed the concrete via pump truck. Approximately 264 cubic yards of concrete were placed during this visit. Three sets of field tests were performed on sampled concrete and yielded the following results: Truck 81 – Load 2 Slump: 8.5 inches Air Content: 3.5% Concrete Temperature: 79°F Truck 52 – Load 8 Slump: 7.5 inches Air Content: 4.5% Concrete Temperature: 79°F Truck 69 – Load 19 Slump: 7.5 inches Air Content: 3.9% Concrete Temperature: 78° Three sets of 6×12-inch compression test cylinders were fabricated for laboratory testing at 7, 14, and 28 days (two cylinders), along with one additional hold cylinder. Laboratory compressive strength test Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. 58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com results will be reported separately upon completion of testing. Test results and observations were verbally reported to the onsite client representative, Rayssa Fonte, while onsite. S.W. COLE rep departed the site at approximately 9:30 PM after completing the requested services. Attachments: 2 Photos Reviewed by:8/28/2026 Kaylie O'SuivKaylie O'Sullivan Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. 58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com