HomeMy WebLinkAboutCCOR 09-23-2026 792-211 to 792-213Concrete Construction Observation Report
The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control.
58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com
Project Name:Town of Yarmouth Water Resource Recovery Facility Project NO.:25-0468Location:Yarmouth MA Date:9/23/2026
Client:Wright-Pierce Client Rep:Eric SaloWeather:Cloudy 58 - 62°F S.W.COLE Rep:Robert Reuter
General Contractor:Wright Pierce Time Onsite:05:15 - 14:00
Placement Type: Footing Wall Slab OtherPlacement Location:Process building slab three
Concrete Placement Observations Observed Comments
Required mix used Yes 4500 psi
Concrete properly conveyed to all areas of placement Yes Concrete placement was done by a pump truck
Internal vibration / consolidation of concrete Yes Internal vibration was continuously used
throughout placement
Even layering around openings and embedments Yes Concrete was evenly laid around openings and
embedment
Post placement observations (finishing, curing, etc.)Yes Concrete was finished manually with a hand trowel
Field Testing of Concrete performed:Yes
*CYLINDER SET NO:792-211 to 792-213 *Refer to associated concrete test report
Notes:
S.W. Cole Engineering Construction Services Technician Robert Reuter arrived onsite at 5:15 AM for "Concrete Field Testing"
and for the placement location referenced above. Upon arrival, met with Eric Salo with CDM Smith who provided information
about today's job duties.
Concrete was delivered by "Cape Cod ready mix." and was 3/4” & 1-1/2” 4500 PSI Concrete. A total of (200) cubic yards of
concrete was placed.
A sample was collected from load (1) of the 3/4”concrete. Loads (1) of the 1-1/2”. Loads and the standardized testing was
performed with; one set of 1-1/2” (5) cylinders were cast from the load for laboratory compressive strength testing at 7, 14,
and (2) 28 days. One cylinder was made for 'Hold' purposes. Two sets of 3/4” (6) cylinders were cast
from the load for laboratory compressive strength testing at 7, 14, and (3) 28 days. One cylinder was made for 'Hold'
purposes.
The results Truck 1 of 3/4”
•Slump 7-3/4”
•Air 4%
•Temperature 70°
The results Truck 1 of 1-1/2”
•Slump 8-3/4”
•Air 4 %
•Temperature 69°
Observations and Results of the Inspection were continually communicated to Client Representative Eric Salo from "CDM
Smith ". Once the inspection was completed RR left the site.
Attachments: 2 Photos Reviewed by:10/5/2026 Kaylie O'Su iv Kaylie O'Sullivan