HomeMy WebLinkAboutRE Well Installation at Baxter Ave for Barnstable County PFAS InvestigationHi Flora,
Thanks for the detailed information. Please use erosion control straw wattles as needed to contain the work and ensure none takes place on the conservation parcel or within wetland resource
areas. No vehicles or machinery are allowed in the wetland. Once the work is completed and the holes backfilled, disturbed areas must be restored to pre-existing conditions. Please
send a photo upon completion. The work is administratively approved, and no further permitting is required.
Best regards,
Brittany DiRienzo
Conservation Administrator
Town of Yarmouth
bdirienzo@yarmouth.ma.us
508-398-2231 x1288
Conservation Website <https://www.yarmouth.ma.us/325/Conservation>
From: Flora Su <Flora.Su@gza.com>
Sent: Wednesday, October 7, 2026 2:10 PM
To: Jerolimo, Joseph <JJerolimo@yarmouth.ma.us>; DiRienzo, Brittany <BDiRienzo@yarmouth.ma.us>
Cc: John Paquin <john.paquin@gza.com>; Jenn McKechnie <jennifer.mckechnie@gza.com>
Subject: RE: Well Installation at Baxter Ave for Barnstable County PFAS Investigation
Attention!: This email originates outside of the organization. Do not open attachments or click links unless you are sure this email is from a known sender and you know the content
is safe. Call the sender to verify if unsure. Otherwise delete this email.
Hi Joe,
Pardon the extra email; please find attached the map showing the proposed work area.
Thank you,
Flora
Flora Su
Assistant Project Manager
Pronouns (she/her/hers)
Environmental Site Assessment & Investigation
GZA | 249 Vanderbilt Avenue | Norwood, MA 02062
o: 781.278.3869 | c: 781.364.0905 | flora.su@gza.com <mailto:flora.su@gza.com> | www.gza.com <http://www.gza.com/> | LinkedIn <https://www.linkedin.com/in/floraksu/>
Geotechnical | Environmental | Ecological | Water | Construction Management
Known for excellence. Built on trust.
From: Flora Su
Sent: Wednesday, October 7, 2026 2:06 PM
To: 'jjerolimo@yarmouth.ma.us' <jjerolimo@yarmouth.ma.us <mailto:jjerolimo@yarmouth.ma.us> >; 'bdirienzo@yarmouth.ma.us' <bdirienzo@yarmouth.ma.us <mailto:bdirienzo@yarmouth.ma.us> >
Cc: John Paquin <john.paquin@gza.com <mailto:john.paquin@gza.com> >; Jenn McKechnie <jennifer.mckechnie@gza.com <mailto:jennifer.mckechnie@gza.com> >
Subject: RE: Well Installation at Baxter Ave for Barnstable County PFAS Investigation
Hi Joe,
Thanks again for speaking with us about our on-going PFAS investigation project in Hyannis and Yarmouth. As we discussed, GZA has been retained by the County of Barnstable (County)
to investigate the potential extent of PFAS-impacted water originating from the County’s former Municipal Fire Training Facility (MFTF) located at 15 Flintrock Road in Hyannis. This
assessment work is being performed pursuant to the requirements of the Massachusetts Contingency Plan (MCP; 310 CMR 40.0000); the Site has been assigned Release Tracking Number (RTN)
4-26179 by the MassDEP. One of our current tasks is to install additional small-diameter groundwater monitoring wells southwest of the MFTF site, including two locations in the Town
of Yarmouth; one of those locations is proximate to the Yarmouth Conservation land off Gleason Avenue as shown on the attached map. We worked with Amanda Lima of the Yarmouth DPW and
Yarmouth’s consulting engineer, Lisa Stone of Kleinfelder, to select these locations.
At the Gleason Avenue location, a multi-level monitoring well cluster, consisting of three individual monitoring wells drilled to three different depths, will be installed. Each boring
shall be pre-cleared for utilities to at least 5 feet below ground surface using vacuum excavation (VacEx) and/or hand auger methods to limit potential damage to unknown subsurface
utilities. The completed VacEx borings typically are approximately 1-foot in diameter, and will be temporarily backfilled with soil cuttings pending performance of the final monitoring
well drilling and installations through the same boring alignments. The borings are anticipated to be installed within an approximately 10-foot radius area at the ground surface.
Following vacuum excavation, the deeper members of the well cluster will be drilled using a drive and wash drilling method and temporary 4-inch diameter drilling casing. This method
involves driving the casing to the desired depth with a 300-lb hammer and periodically washing the soil contents from the interior of the casing using clean potable water to be obtained
from the MFTF site. The target depth for deepest member of the well cluster is the top of a clayey silt layer anticipated to be approximately 50-70 feet below the ground. After the
target depth is reached, a 2-inch PVC monitoring well screen attached to 2-inch PVC riser pipe will be lowered through the temporary 4-inch drilling casing, and the annulus between
the 2-inch PVC well screen and the 4-inch steel drilling casing will be backfilled with filter sand. The remainder of the borehole will be sealed with a bentonite clay/portland cement
grout. The 4-inch casing will be incrementally removed as the 2-inch PVC well casing is backfilled.
Hollow stem drilling methods may be used for the installation of the shallow well if appropriate for the actual drilling conditions encountered during completion of the deep boring.
Waste drilling water, including drilling wash water, and soil cuttings will be containerized and transported to the MFTF for subsequent proper off-site disposal or reuse. The drilling
subcontractor will place protective plywood mats on the ground surface before mobilizing equipment onto the unpaved areas to limit ground surface impacts. Steel protective casings
or road boxes will be installed at the ground surface over the PVC monitoring wells to secure the wells.
We anticipate that this work can be completed within 3-4 consecutive work days at the Gleason Road location.
Thank you again for your assistance to quickly assess if an NOI is needed to support this work. As we discussed, the drilling firm is prepared to initiate this work this week.
Please do not hesitate to contact me at 781-278-3869 or John Paquin at 781-278-3867.
Thank you,
Flora Su
Flora Su
Assistant Project Manager
Pronouns (she/her/hers)
Environmental Site Assessment & Investigation
GZA | 249 Vanderbilt Avenue | Norwood, MA 02062
o: 781.278.3869 | c: 781.364.0905 | flora.su@gza.com <mailto:flora.su@gza.com> | www.gza.com <http://www.gza.com/> | LinkedIn <https://www.linkedin.com/in/floraksu/>
Geotechnical | Environmental | Ecological | Water | Construction Management
Known for excellence. Built on trust.
-----Original Appointment-----
From: Flora Su
Sent: Wednesday, October 7, 2026 11:25 AM
To: Flora Su; John Paquin; jjerolimo@yarmouth.ma.us <mailto:jjerolimo@yarmouth.ma.us>
Cc: bdirienzo@yarmouth.ma.us <mailto:bdirienzo@yarmouth.ma.us>
Subject: Well Installation at Baxter Ave for Barnstable County PFAS Investigation
When: Wednesday, October 7, 2026 11:30 AM-12:00 PM (UTC-05:00) Eastern Time (US & Canada).
Where: Microsoft Teams Meeting
Hi Joe and Brittany,
Please find below the Teams meeting link, for discussion of the proposed monitoring well installation and drilling work in Yarmouth off Gleason Avenue.
Brittany, we understand that you are on another call this morning, but if you become available, we would love to have you join this meeting, too.
________________________________________________________________________________
Microsoft Teams meeting
Join: https://teams.microsoft.com/meet/222726021494180?p=5IjHNPmWhq48BgCvQk <https://teams.microsoft.com/meet/222726021494180?p=5IjHNPmWhq48BgCvQk>
Meeting ID: 222 726 021 494 180
Passcode: Pf2xF3pw
________________________________
Need help? <https://aka.ms/JoinTeamsMeeting?omkt=en-US> | System reference <https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZjZjZTUyMmMtZjYzZS00OWQ2LTgyMWEtN2ZmZmU2ZWE1MWQw%40thread.v2/0?cont
ext=%7b%22Tid%22%3a%224d4ce8c8-2dc3-4ba7-94ee-6674dd2754ee%22%2c%22Oid%22%3a%2213ce3088-b450-486e-ac0f-530d46c4a260%22%7d>
Dial in by phone
+1 857-299-6190,,400855627# <tel:+18572996190,,400855627> United States, Belmont
Find a local number <https://dialin.teams.cloud.microsoft/f73a9eb1-b86f-4225-bd7b-4efedb7eec2a?id=400855627>
Phone conference ID: 400 855 627#
For organizers: Meeting options <https://teams.microsoft.com/meetingOptions/?organizerId=13ce3088-b450-486e-ac0f-530d46c4a260&tenantId=4d4ce8c8-2dc3-4ba7-94ee-6674dd2754ee&threadId=19_meeting_ZjZjZTU
yMmMtZjYzZS00OWQ2LTgyMWEtN2ZmZmU2ZWE1MWQw@thread.v2&messageId=0&language=en-US> | Reset dial-in PIN <https://dialin.teams.cloud.microsoft/usp/pstnconferencing>
________________________________________________________________________________
Thank you,
Flora
Flora Su
Assistant Project Manager
Pronouns (she/her/hers)
Environmental Site Assessment & Investigation
GZA | 249 Vanderbilt Avenue | Norwood, MA 02062
o: 781.278.3869 | c: 781.364.0905 | flora.su@gza.com <mailto:flora.su@gza.com> | www.gza.com <http://www.gza.com/> | LinkedIn <https://www.linkedin.com/in/floraksu/>
Geotechnical | Environmental | Ecological | Water | Construction Management
Known for excellence. Built on trust.
________________________________
This electronic message is intended to be viewed only by the individual or entity to which it is addressed and may
contain privileged and/or confidential information intended for the exclusive use of the addressee(s). If you are
not the intended recipient, please be aware that any disclosure, printing, copying, distribution or use of this
information is prohibited. If you have received this message in error, please notify the sender immediately and
destroy this message and its attachments from your system.
________________________________
For information about GZA GeoEnvironmental, Inc. and its services, please visit our website at www.gza.com <http://www.gza.com/> .