Re: Notice of Exempt Gas Main Replacement Activities
Union Street and Route 6A, Yarmouth Port, Massachusetts
Dear Members of the Yarmouth Conservation Commission:
Boston Gas Company respectfully submits this written notification of the intent to conduct
exempt gas main replacement activities located in the roadway right-of-way (ROW) on Union
Street and Route 6A in Yarmouth Port, Massachusetts. The proposed work consists of the
relay of approximately 3,865 linear feet of four-inch subsurface coated steel gas main with
six-inch plastic gas main from 10 Union Street to Route 6A eastward to the intersection of
Route 6A and Hockanom Road. Portions of the proposed work will take place within Bordering
Land Subject to Flooding, the 200-foot Riverfront Area to Whites Brook, and the 100-foot
Buffer Zone to Bank and Bordering Vegetated Wetlands. The location of the project area is
depicted on the Site Location Map included as Attachment A.
The proposed work is considered to be exempt from the Massachusetts Wetlands Protection
Act (MA WPA, M.G.L. c. 131 §40) in accordance with 310 CMR 10.02(2)(a)(2), as the work
consists of “activities conducted to maintain, repair or replace, but not substantially change
or enlarge an existing and lawfully located structure or facility used in the service of the public
and used to provide electric, gas, water, sewer, telephone, telegraph and other
communication services, provided said work utilizes the best practical measures to avoid or
minimize impacts to wetland resource areas outside the footprint of said structure or facility.”
The Town of Yarmouth Wetlands Protection Bylaw (Chapter 143, Section 1.02(3b)) provides
a similar exemption. This letter is intended to serve as a written notice of exempt work.
In general, the gas main activities will entail the excavation of an approximately two -foot
wide trench for safe installation. The trench bottom will be excavated and graded such that
the pipe will be supported for its entire length on undisturbed bottom at a depth of
approximately three feet below surface grade. The trench will be excavated within the existing
impervious surface of Union Street and Route 6A, with the precise location of the gas line to
be determined in the field so that existing utilities can be avoided . Upon installation of the
replacement line, the trench will be backfilled and restored in -kind.
No direct impacts to wetland resource areas are anticipated as a result of this project. This
work is primarily within the existing paved roadway. Best Management Practices (BMPs) will
be implemented as needed. Attachment B of this submittal includes details of standard erosion
control measures that have been used in past projects of similar scope. Following the
completion of construction activities, disturbed areas will be restored in-kind.
- 2 -
Please refer to the attached Site Location Map for the project location. Should you have any
questions regarding this notification or require any additional information, please do not
hesitate to contact me at (774) 384-5221 or my agent, Maria Johnsenberg, Project Manager
with Tighe & Bond, at (508) 304-6343 or via email at MJohnsenberg@tighebond.com.
Thank you in advance for your attention to this matter.
Respectfully,
Patrick Hutchinson
Environmental Scientist
National Grid
170 Data Drive, Waltham, MA 02451
Attachments:
A – Site Location Map
B – National Grid Best Management Practice Details
Attachment A
A
Created by:Created for:
THIS DOCUMENT IS INTENDED FOR GENERAL PLANNING & INFORMATION PURPOSES ONLY. ALL MEASUREMENTS & LOCATIONS ARE APPROXIMATE.
File Location: G:\GIS\MA\SiteLocus\Yarmouth\NGridRoute6APipeRelay_N5141\NGridRoute6APipeRelay_N5141.aprx\Fig1_Topo_Route6A_UnionStGasPipeline
Date Saved: 9/30/2026 10:43 AM
Index Map
Ü
1 inch = 1,000 feet
0 500 1,000
Feet
Based on USGS National Map Topo Basemap.
Contour Interval Equals 10 Feet.
Figure 1
Site Location
Route 6A and Union Street
Yarmouth, Massachusetts
UTILITY MAINTENANCE - GAS PIPELINE REPLACEMENT,SITE LOCATIONSITE LOCATION
Gas Pipeline Replacement
Attachment B
A
ENVIRONMENTAL GUIDANCE Date
Doc. No.EG-303NE
02/20/18
SUBJECT
Access, Maintenance and Construction
Best Management Practices
Reference
EP No. 3 - Natural Resource
Protection (Chapter 6)
Rev. No. 4
SEC-1
WEED FREE BALE BARRIER
BMP DETAIL
BMP PICTURE
Page: 7-1
ENVIRONMENTAL GUIDANCE Date
Doc. No.EG-303NE
02/20/18
SUBJECT
Access, Maintenance and Construction
Best Management Practices
Reference
EP No. 3 - Natural Resource
Protection (Chapter 6)
Rev. No. 4
SEC-2
SEDIMENT CONTROL FENCE
BMP DETAIL
BMP PICTURE
Page: 7-2
ENVIRONMENTAL GUIDANCE Date
Doc. No.EG-303NE
02/20/18
SUBJECT
Access, Maintenance and Construction
Best Management Practices
Reference
EP No. 3 - Natural Resource
Protection (Chapter 6)
Rev. No. 4
SEC-3
SILT FENCE /
WEED FREE BARRIER
BMP DETAIL
BMP PICTURE
Page: 7-3
ENVIRONMENTAL GUIDANCE Date
Doc. No.EG-303NE
02/20/18
SUBJECT
Access, Maintenance and Construction
Best Management Practices
Reference
EP No. 3 - Natural Resource
Protection (Chapter 6)
Rev. No. 4
SEC-4
SILT SOXX *
BMP DETAIL
BMP PICTURE
Page: 7-4
1
2
3
ENVIRONMENTAL GUIDANCE Date
Doc. No.EG-303NE
02/20/18
SUBJECT
Access, Maintenance and Construction
Best Management Practices
Reference
EP No. 3 - Natural Resource
Protection (Chapter 6)
Rev. No. 4
SEC-5
STRAW WATTLE * (1 OF 2)
BMP DETAIL
Page: 7-5
ENVIRONMENTAL GUIDANCE Date
Doc. No.EG-303NE
02/20/18
SUBJECT
Access, Maintenance and Construction
Best Management Practices
Reference
EP No. 3 - Natural Resource
Protection (Chapter 6)
Rev. No. 4
SEC-5
STRAW WATTLE * (2 OF 2)
BMP PICTURE
Page: 7-6
ENVIRONMENTAL GUIDANCE Date
Doc. No.EG-303NE
02/20/18
SUBJECT
Access, Maintenance and Construction
Best Management Practices
Reference
EP No. 3 - Natural Resource
Protection (Chapter 6)
Rev. No. 4
AA-20
SILT SACK *
BMP DETAIL
BMP PICTURE
Page: 7-48