HomeMy WebLinkAboutCCOR 10-08-2026 792-216 to 792-217Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. 58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com Project Name:Town of Yarmouth Water Resource Recovery Facility Project NO.:25-0468Location:Yarmouth MA Date:10/8/2026 Client:Wright-Pierce Client Rep:Rayssa FonteWeather:Mostly Clear 50 - 65°F S.W.COLE Rep:Henry Among General Contractor:CDM Smith Time Onsite:06:30 - 08:30 Placement Type: Footing  Wall  Slab  OtherPlacement Location:SHB upper stairs and SBR walkway Concrete Placement Observations Observed Comments Required mix used Yes 4500 psi Concrete strength and aggregate size of 3/4 "and 1-1/2'' with sika control 75 Concrete properly conveyed to all areas of placement Yes Concrete was pump to all areas of placement Internal vibration / consolidation of concrete Yes Internal vibration by the use of a worm vibrator Even layering around openings and embedments Yes Evenly placed around all corners and openings Post placement observations (finishing, curing, etc.)Yes Concrete was manually finished Field Testing of Concrete performed:Yes *CYLINDER SET NO:792-216 to 792-217  *Refer to associated concrete test report Notes: As requested by CDM Smith., S.W. COLE rep. Henry Among, Construction Services Technician, was onsite to observe concrete placement activities and perform field testing. Upon arrival, Henry spoke with  CDM  representative  regarding the concrete placement activities planned for the day. Concrete was delivered by Cape Cod ready mix. The concrete was reported to be a 3/4-inch  and 1-1/2 inch respectively of nominal aggregate, 4500-psi design strength and sika control admixtures. Approximately 11 cubic yards of3/4 aggregate size of concrete and 24 cubic yards of 1-1/2 aggregate size were placed during the observation period. Concrete sampling and field testing were performed in general accordance with applicable ASTM standards. .Samples were obtained from loads one of 3/4 aggregate size concrete and placed during the observation period.  another sample was obtain from load one of the1-1/2 aggregate size concrete .The following field test results were recorded: For 3/4 aggregate size concrete Slump (ASTM C143) Truck 73 (Load 1): 3 inches Air Content (ASTM C231) Truck 73 (Load 1): 4.5% Concrete Temperature (ASTM C1064) Truck 73 (Load 1): 65°F For 1-1/2 aggregate size concrete Slump (ASTM C143) Truck 67 (Load 1): 6.5 inches Air Content (ASTM C231) Truck 67 (Load 1): 4.5% Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. 58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com Concrete Temperature (ASTM C1064) Truck 67(Load 1): 70°F Concrete placement activities were observed utilizing a concrete pump. Internal consolidation activities were observed utilizing worm vibrators, and the concrete was observed being placed in lifts and distributed using hand tools . A total of twelve (6) 4-inch by 8-inch concrete cylinders were cast, consisting of six (6) cylinders from load one of the 3/4 aggregate size concrete  and  a  total of five (5) 6-inch by 12-inch concrete cylinders were casted,  from load one of the 1-1/2 aggregate size concrete. The cylinders were designated for laboratory compressive strength testing as follows: One (1) cylinder for 7-day testing One (1) cylinder for 14-day testing Three (3) cylinders for 28-day testing One (1) hold specimen. Upon completion of day's activities, Henry communicated the results onsite with CDM Smiths representative  Attachments: 3 Photos Reviewed by:10/19/2026 Kaylie O'SuivKaylie O'Sullivan Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. 58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com Concrete Construction Observation Report The S.W.COLE field representative is on-site at the request of our client to provide construction materials testing and to observe and document construction activities. The Contractor has soleresponsibility for schedule, site safety, methods, completeness and quality control. 58 Norfolk Ave, Easton, MA 02375 • Tel 508 822 6934 • www.swcole.com